| TO DO | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Bonus Room | ||||
| Bonus Bathroom | ||||
| Double Waste basket | ||||
| Spice Rack | ||||
| Expanded Driveway | ||||
| Amendment to increase price by $17,840 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 12.26.2023 | ||
| -- | -- | Inspection (Concrete Wall) (1) 12.26.2023 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 01.04.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 01.04.2024 | ||
| -- | -- | Inspection (Slab) (1) 01.04.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 01.04.2024 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 03.21.2024 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 03.21.2024 | ||
| -- | -- | Inspection (Rough In Electric) (1) 03.21.2024 | ||
| -- | -- | Inspection (Framing) (1) * 03.21.2024 | ||
| -- | -- | Inspection (Deck Piers) (0) 05.20.2024 | ||
| -- | -- | Inspection (Insulation) (1) 03.30.2024 | ||
| -- | -- | Inspection (Electric Service) (0) 04.11.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 03.21.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.21.2024 | ||
| -- | -- | Inspection (Final HVAC) (0) 06.17.2024 | ||
| -- | -- | Inspection (Final Plumbing) (0) 06.17.2024 | ||
| -- | -- | Inspection (Final Electric) (0) 06.17.2024 | ||
| -- | -- | Inspection (Final Building) (4) * 06.17.2024 | Thurs, June 13 | |