| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Expanded Driveway | ||||
| Bonus Room | ||||
| Bonus Bath | ||||
| Expanded 10 x 10 patio | ||||
| Spice Rack Cabinet | ||||
| Farmhouse sink- white | ||||
| Double Waste Basket | ||||
| Digital Deadbolt | ||||
| Ceiling Fan Living Room | ||||
| Banquette Seating with under cabinets | ||||
| Painted Stairs to bedroom level | ||||
| Amendment to increase price by $24,370 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 01.04.2024 | ||
| -- | -- | Inspection (Concrete Wall) (1) 01.04.2024 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 02.08.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 02.08.2024 | ||
| -- | -- | Inspection (Slab) (1) 02.08.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 02.08.2024 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 05.01.2024 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 05.01.2024 | ||
| -- | -- | Inspection (Rough In Electric) (1) 05.01.2024 | ||
| -- | -- | Inspection (Framing) (1) * 05.01.2024 | ||
| -- | -- | Inspection (Deck Piers) (0) 05.01.2024 | ||
| -- | -- | Inspection (Insulation) (1) 05.04.2024 | ||
| -- | -- | Inspection (Electric Service) (0) 05.20.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 04.04.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 04.04.2024 | ||
| -- | -- | Inspection (Final HVAC) (1) 07.25.2024 | ||
| -- | -- | Inspection (Final Plumbing) (1) 07.25.2024 | ||
| -- | -- | Inspection (Final Electric) (1) 07.25.2024 | ||
| -- | -- | Inspection (Final Building) (2) * 07.25.2024 | Monday- July 22nd | |