37 ADDR
CONGERS-2 - 52  ::  1394 Appaloosa Court
[ BUILD: 20231957 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Missing side window
Expand patio
Bathtub needed in bonus On site 6/1
Paint ceiling of garage Painter
Farmhouse sink onsite
Finish the bonus room and bathroom
I think callback is supposed to be pale oak not gray Hall bath, Painter
Front white van piece needs to be caulked or readjusted Vinyl piece Davenport - Jeremy
Finish trim after cabinets are installed
Complete drywall finishing in basement bonus room, and bath
Need Electricity!
Really wants to close by July 15
Is bonus room door framing, correct? Door is removed.
Spice rack door handle is not straight Fred
Upstairs bedroom needs to be white, not pale oak Painter
Possible drywall repair needed, and bonus bathroom at trim
Finish carpet in master closet
Finish carpet in master closet on order
Pretty large gaps in kitchen island trim. Is that supposed to be caulked?
Scribe needed around farmhouse sink Fred
Middle front window cracked at corner
remove baseboard to seating can be installed
replacement cabinets arriving in about 2 weeks from 7/8 Fred - working to schedule
Finish shelving in master closet Paul
Drywall repair needed above seating in kitchen Drywallers
Cable covers needed on electric trim out
Steps have a few spots that looks like stain, wasn’t absorbed equally. Issac aware
Remove large block of concrete from yard Tom
Needs final locks on keyed doors
Should the fan blades be facing down with the fake wood design? Technically, no, but the blades matched the floor perfectly. We won’t do anything, unless the buyer requests it.
install dishwasher
flatten out side yard Pettit
Add dirt and sod around patio where it’s not level to ground and grass will not grow Pettit. Need sod. 8/3
Add shoe molding to basement bathroom George
Sod out front may need replacing as well Pettit
Clean out garage Jill
Finish staining steps
Backsplash in kitchen Greg is aware. Jill following up.
Repaint black steps Issac aware
CODED LOCKBOX 5252
Clean off back patio Jill
Bonus room door needs to be trimmed rubs against carpet George
Lots of spots were paint is on luxury vinyl plank Issac checking
Clean off paint off all door hinges Painters
Paint attic access panel Painters
Windows screens to be installed Jill
knick in wall between hall light fixtures Painters
Cover cable box in garage
Replace transition strip leading to kitchen Denny - Mon, Jul 29
Banquette seating needs attention{lots of scuff marks) Parts on order
Remove the 2 toilets from garage Jill
Raise the chandelier 1 bar length Electrician
Raise the 2 pendant lights to the same height as the chandelier Electrician
Very few paint touch ups!! Painters
Install bonus bathroom, shoe molding
Very invisible, scuff marks on risers from foyer to second level Jill or Painter
Masie Fowler 540-746-4002 mfowler@fowlerfamilymedicine.com
UPGRADES - COMPLETED
    Expanded Driveway  
    Bonus Room  
    Bonus Bath  
    Expanded 10 x 10 patio  
    Spice Rack Cabinet  
    Farmhouse sink- white  
    Double Waste Basket  
    Digital Deadbolt  
    Ceiling Fan Living Room  
    Banquette Seating with under cabinets  
    Painted Stairs to bedroom level  
    Amendment to increase price by $24,370  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  05.01.2024    
-- -- $2500 Deposit Received (0)  05.04.2024    
-- -- Association Packet Requested (0)  05.04.2024    
-- -- Association Packet Received (0)  05.04.2024    
-- -- Selections Meeting (0)  05.16.2024     Wednesday 5/15 at 3:30
-- -- Selections Sheet Signed (0)  05.23.2024     5/16: sent to buyer for review
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.25.2024     5/25: sent to Jerry
-- -- Deposit For Upgrades Received (0)  05.25.2024    
-- -- Building Permit (30) *   01.04.2024    
-- -- Order Roof & Floor Trusses (1)  02.12.2024    
-- -- Order Windows & Doors (0)  02.12.2024    
-- -- Stake Out Home (1)  01.04.2024    
-- -- Excavate (2)  01.04.2024    
-- -- Inspection (Footers) (1)  01.04.2024    
-- -- Inspection (Concrete Wall) (1)  01.04.2024    
-- -- Pour Footers (1) *   01.04.2024    
-- -- Set Forms (2)  01.04.2024    
-- -- Pour Foundation Walls (1)  01.04.2024    
-- -- Plumb Slab (2)  01.07.2024    
-- -- Inspection (Plumbing Under Slab) (1)  02.08.2024    
-- -- Inspection (Conduit Under Slab) (1)  02.08.2024    
-- -- Prepare Slab (1)  02.08.2024    
-- -- Inspection (Slab) (1)  02.08.2024    
-- -- Inspection (Drain Tile) (0)  02.08.2024    
-- -- Pour Slab (1) *   02.08.2024    
-- -- Settlement Agent Confirmed (0)  06.05.2024     sent
-- -- Framing I (9)  02.15.2024    
-- -- Order Steps (0)  03.11.2024    
-- -- Order Tubs / Showers (0)  03.11.2024    
-- -- Framing II (8)  02.19.2024    
-- -- Framing III (8) *   02.22.2024    
-- -- Verify Window & Roof Structure (0)  03.04.2024    
-- -- Install Stairs (0) *   03.11.2024    
-- -- Windows & Doors (0) *   04.03.2024    
-- -- House Number and Status in Window (0)  04.03.2024    
-- -- Roofing (0) *   04.04.2024    
-- -- Order Cabinets (0)  06.13.2024    
-- -- Order Appliances (0)  06.10.2024     ordered 5/28
-- -- Deck (0)  04.03.2024    
-- -- Gutters (0)  05.26.2024    
-- -- Driveway (0) *   05.29.2024    
-- -- Patio (0)  04.03.2024    
-- -- Privacy Divider / Fence (0) *   06.26.2024    
-- -- Sod / Seed / Landscaping (0)  07.20.2024    
-- -- HVAC Rough In (4)  03.16.2024     in process 3/13
-- -- Rough In Microwave Vent (0)  03.13.2024    
-- -- Plumbing Rough In (4)  04.17.2024     In process 4/12
-- -- Electric Rough In (4)  04.24.2024    
-- -- Inspection (Rough In HVAC) (1)  05.01.2024    
-- -- Inspection (Rough In Plumbing) (1)  05.01.2024    
-- -- Inspection (Rough In Electric) (1)  05.01.2024    
-- -- Inspection (Framing) (1) *   05.01.2024    
-- -- Inspection (Deck Piers) (0)  05.01.2024    
-- -- Exterior Vinyl (0) *   05.06.2024    
-- -- Exterior Stone (0)  05.18.2024    
-- -- Insulation (2) *   05.01.2024    
-- -- Inspection (Insulation) (1)  05.04.2024    
-- -- Inspection (Electric Service) (0)  05.20.2024    
-- -- Set Electric Meter (0) *   07.19.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  06.06.2024    
-- -- Drywall (Hang) (4) *   05.08.2024     In process 5/4
-- -- Loan Approval (0)  07.19.2024     Cindy Rader, First Citizens (100% MD)
-- -- Deed Preparation (0)  07.19.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   05.22.2024    
-- -- Paint 1 (1)  05.22.2024    
-- -- Garage Door (0)  06.26.2024    
-- -- House Numbers (0)  06.26.2024    
-- -- Mailbox (0)  07.07.2024    
-- -- Cabinet Installation (2) *   06.26.2024     June 25
-- -- Granite Installation (1) *   07.06.2024    
-- -- Interior Trim - Install (3) *   06.12.2024    
-- -- Order Plumbing / Lighting Fixtures (0)  06.06.2024    
-- -- Interior Trim - Paint (1)  06.12.2024    
-- -- Luxury Vinyl Plank (3) *   06.26.2024     In process 6/22
-- -- Luxury Vinyl Tile (0)  06.22.2024    
-- -- Paint 2 (3)  06.26.2024    
-- -- Cover Floors (1)  07.17.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  06.17.2024    
-- -- Shoe Moulding (0)  07.10.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   07.17.2024     In process 7/10
-- -- Install Coded Lockbox (add extra keys) (0)  07.22.2024    
-- -- Pay Water / Sewer Taps (0)  06.10.2024    
-- -- Set Water Meter (0) *   06.20.2024    
-- -- Electric Trim Out (3) *   07.13.2024     in process 7/8
-- -- Ceiling Fans (0)  07.18.2024    
-- -- HVAC Trim Out (1) *   07.22.2024     7/18
-- -- Blower Door Test (1)  07.25.2024     Mon, 7/22
-- -- Plumbing Trim Out (2) *   07.17.2024     In process 7/13
-- -- Install Appliances (0) *   07.18.2024    
-- -- Paint 3 (2) *   07.07.2024    
-- -- Carpet (2)  06.30.2024     In process 6/26
-- -- Appraiser Confirms Construction Completion (0)  07.28.2024    
-- -- Inspection (Final HVAC) (1)  07.25.2024    
-- -- Inspection (Final Plumbing) (1)  07.25.2024    
-- -- Inspection (Final Electric) (1)  07.25.2024    
-- -- Inspection (Final Building) (2) *   07.25.2024     Monday- July 22nd
-- -- Pre Walk Through (0)  07.22.2024     Kate - 7/19
-- -- Stain Hardwood Stairs (1) *   07.13.2024     In process 7/10
-- -- Cleaning (1)  07.22.2024     Lynn starting 7/18
-- -- Certificate of Occupancy (1) *   07.29.2024    
-- -- C.O. to Lender (0)  07.29.2024    
-- -- Schedule Closing (0)  07.28.2024    
-- -- Buyer Walk Through (1) *   07.25.2024     Hoping for final walkthrough for Wednesday 7/24
-- -- Payment for Upgrades (0)  07.28.2024    
-- -- Keys to Settlement Agent (0)  07.25.2024    
-- -- Review Settlement Statement (0)  07.28.2024    
-- -- Jerry Signs Closing Documents (0)  07.30.2024    
-- -- Request Trash Tote From POA Manager (0)  07.01.2024    
-- -- Closing (1)  08.05.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  08.26.2024