Missing side window |
|
|
-- |
-- |
Expand patio |
|
|
-- |
-- |
Bathtub needed in bonus |
On site 6/1 |
|
-- |
-- |
Paint ceiling of garage |
Painter |
|
-- |
-- |
Farmhouse sink onsite |
|
|
-- |
-- |
Finish the bonus room and bathroom |
|
|
-- |
-- |
I think callback is supposed to be pale oak not gray |
Hall bath, Painter |
|
-- |
-- |
Front white van piece needs to be caulked or readjusted |
Vinyl piece Davenport - Jeremy |
|
-- |
-- |
Finish trim after cabinets are installed |
|
|
-- |
-- |
Complete drywall finishing in basement bonus room, and bath |
|
|
-- |
-- |
Need Electricity! |
|
|
-- |
-- |
Really wants to close by July 15 |
|
|
-- |
-- |
Is bonus room door framing, correct? Door is removed. |
|
|
-- |
-- |
Spice rack door handle is not straight |
Fred |
|
-- |
-- |
Upstairs bedroom needs to be white, not pale oak |
Painter |
|
-- |
-- |
Possible drywall repair needed, and bonus bathroom at trim |
|
|
-- |
-- |
Finish carpet in master closet |
|
|
-- |
-- |
Finish carpet in master closet |
on order |
|
-- |
-- |
Pretty large gaps in kitchen island trim. Is that supposed to be caulked? |
|
|
-- |
-- |
Scribe needed around farmhouse sink |
Fred |
|
-- |
-- |
Middle front window cracked at corner |
|
|
-- |
-- |
remove baseboard to seating can be installed |
|
|
-- |
-- |
replacement cabinets arriving in about 2 weeks from 7/8 |
Fred - working to schedule |
|
-- |
-- |
Finish shelving in master closet |
Paul |
|
-- |
-- |
Drywall repair needed above seating in kitchen |
Drywallers |
|
-- |
-- |
Cable covers needed on electric trim out |
|
|
-- |
-- |
Steps have a few spots that looks like stain, wasn’t absorbed equally. |
Issac aware |
|
-- |
-- |
Remove large block of concrete from yard |
Tom |
|
-- |
-- |
Needs final locks on keyed doors |
|
|
-- |
-- |
Should the fan blades be facing down with the fake wood design? |
Technically, no, but the blades matched the floor perfectly. We won’t do anything, unless the buyer requests it. |
|
-- |
-- |
install dishwasher |
|
|
-- |
-- |
flatten out side yard |
Pettit |
|
-- |
-- |
Add dirt and sod around patio where it’s not level to ground and grass will not grow |
Pettit. Need sod. 8/3 |
|
-- |
-- |
Add shoe molding to basement bathroom |
George |
|
-- |
-- |
Sod out front may need replacing as well |
Pettit |
|
-- |
-- |
Clean out garage |
Jill |
|
-- |
-- |
Finish staining steps |
|
|
-- |
-- |
Backsplash in kitchen |
Greg is aware. Jill following up. |
|
-- |
-- |
Repaint black steps |
Issac aware |
|
-- |
-- |
CODED LOCKBOX 5252 |
|
|
-- |
-- |
Clean off back patio |
Jill |
|
-- |
-- |
|
|
|
-- |
-- |
Bonus room door needs to be trimmed rubs against carpet |
George |
|
-- |
-- |
Lots of spots were paint is on luxury vinyl plank |
Issac checking |
|
-- |
-- |
Clean off paint off all door hinges |
Painters |
|
-- |
-- |
Paint attic access panel |
Painters |
|
-- |
-- |
Windows screens to be installed |
Jill |
|
-- |
-- |
knick in wall between hall light fixtures |
Painters |
|
-- |
-- |
Cover cable box in garage |
|
|
-- |
-- |
Replace transition strip leading to kitchen |
Denny - Mon, Jul 29 |
|
-- |
-- |
Banquette seating needs attention{lots of scuff marks) |
Parts on order |
|
-- |
-- |
Remove the 2 toilets from garage |
Jill |
|
-- |
-- |
Raise the chandelier 1 bar length |
Electrician |
|
-- |
-- |
Raise the 2 pendant lights to the same height as the chandelier |
Electrician |
|
-- |
-- |
Very few paint touch ups!! |
Painters |
|
-- |
-- |
Install bonus bathroom, shoe molding |
|
|
-- |
-- |
Very invisible, scuff marks on risers from foyer to second level |
Jill or Painter |
|
-- |
-- |
Masie Fowler 540-746-4002 |
mfowler@fowlerfamilymedicine.com |
|
-- |
-- |
Ratified Contract? (0) 05.01.2024 |
|
|
-- |
-- |
$2500 Deposit Received (0) 05.04.2024 |
|
|
-- |
-- |
Association Packet Requested (0) 05.04.2024 |
|
|
-- |
-- |
Association Packet Received (0) 05.04.2024 |
|
|
-- |
-- |
Selections Meeting (0) 05.16.2024 |
Wednesday 5/15 at 3:30 |
|
-- |
-- |
Selections Sheet Signed (0) 05.23.2024 |
5/16: sent to buyer for review |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 05.25.2024 |
5/25: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 05.25.2024 |
|
|
-- |
-- |
Building Permit (30) 01.04.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 02.12.2024 |
|
|
-- |
-- |
Order Windows & Doors (0) 02.12.2024 |
|
|
-- |
-- |
Stake Out Home (1) 01.04.2024 |
|
|
-- |
-- |
Excavate (2) 01.04.2024 |
|
|
-- |
-- |
Inspection (Footers) (1) 01.04.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 01.04.2024 |
|
|
-- |
-- |
Pour Footers (1) 01.04.2024 |
|
|
-- |
-- |
Set Forms (2) 01.04.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1) 01.04.2024 |
|
|
-- |
-- |
Plumb Slab (2) 01.07.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 02.08.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 02.08.2024 |
|
|
-- |
-- |
Prepare Slab (1) 02.08.2024 |
|
|
-- |
-- |
Inspection (Slab) (1) 02.08.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 02.08.2024 |
|
|
-- |
-- |
Pour Slab (1) * 02.08.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 06.05.2024 |
sent |
|
-- |
-- |
Framing I (9) 02.15.2024 |
|
|
-- |
-- |
Order Steps (0) 03.11.2024 |
|
|
-- |
-- |
Order Tubs / Showers (0) 03.11.2024 |
|
|
-- |
-- |
Framing II (8) 02.19.2024 |
|
|
-- |
-- |
Framing III (8) * 02.22.2024 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 03.04.2024 |
|
|
-- |
-- |
Install Stairs (0) 03.11.2024 |
|
|
-- |
-- |
Windows & Doors (0) 04.03.2024 |
|
|
-- |
-- |
House Number and Status in Window (0) 04.03.2024 |
|
|
-- |
-- |
Roofing (0) 04.04.2024 |
|
|
-- |
-- |
Order Cabinets (0) 06.13.2024 |
|
|
-- |
-- |
Order Appliances (0) 06.10.2024 |
ordered 5/28 |
|
-- |
-- |
Deck (0) 04.03.2024 |
|
|
-- |
-- |
Gutters (0) 05.26.2024 |
|
|
-- |
-- |
Driveway (0) 05.29.2024 |
|
|
-- |
-- |
Patio (0) 04.03.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 06.26.2024 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 07.20.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 03.16.2024 |
in process 3/13 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 05.01.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 03.13.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 04.17.2024 |
In process 4/12 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 05.01.2024 |
|
|
-- |
-- |
Electric Rough In (4) 04.24.2024 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 05.01.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 05.01.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 05.01.2024 |
|
|
-- |
-- |
Exterior Vinyl (0) * 05.06.2024 |
|
|
-- |
-- |
Exterior Stone (0) 05.18.2024 |
|
|
-- |
-- |
Insulation (2) 05.01.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 05.04.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 05.20.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 07.19.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 04.04.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 04.04.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 06.06.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 05.08.2024 |
In process 5/4 |
|
-- |
-- |
Loan Approval (0) 07.19.2024 |
Cindy Rader, First Citizens (100% MD) |
|
-- |
-- |
Deed Preparation (0) 07.19.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 05.22.2024 |
|
|
-- |
-- |
Paint 1 (1) 05.22.2024 |
|
|
-- |
-- |
Garage Door (0) 06.26.2024 |
|
|
-- |
-- |
House Numbers (0) 06.26.2024 |
|
|
-- |
-- |
Mailbox (0) 07.07.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 06.26.2024 |
June 25 |
|
-- |
-- |
Granite Installation (1) * 07.06.2024 |
|
|
-- |
-- |
Interior Trim - Install (3) 06.12.2024 |
|
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 06.06.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 06.12.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 06.26.2024 |
In process 6/22 |
|
-- |
-- |
Luxury Vinyl Tile (0) 06.22.2024 |
|
|
-- |
-- |
Paint 2 (3) 06.26.2024 |
|
|
-- |
-- |
Cover Floors (1) 07.17.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 06.17.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 07.10.2024 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 07.17.2024 |
In process 7/10 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 07.22.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 06.10.2024 |
|
|
-- |
-- |
Set Water Meter (0) 06.20.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 07.13.2024 |
in process 7/8 |
|
-- |
-- |
Ceiling Fans (0) 07.18.2024 |
|
|
-- |
-- |
HVAC Trim Out (1) 07.22.2024 |
7/18 |
|
-- |
-- |
Blower Door Test (1) 07.25.2024 |
Mon, 7/22 |
|
-- |
-- |
Plumbing Trim Out (2) 07.17.2024 |
In process 7/13 |
|
-- |
-- |
Install Appliances (0) * 07.18.2024 |
|
|
-- |
-- |
Paint 3 (2) * 07.07.2024 |
|
|
-- |
-- |
Carpet (2) 06.30.2024 |
In process 6/26 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 07.28.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 07.25.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 07.25.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 07.25.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 07.25.2024 |
Monday- July 22nd |
|
-- |
-- |
Pre Walk Through (0) 07.22.2024 |
Kate - 7/19 |
|
-- |
-- |
Stain Hardwood Stairs (1) 07.13.2024 |
In process 7/10 |
|
-- |
-- |
Cleaning (1) 07.22.2024 |
Lynn starting 7/18 |
|
-- |
-- |
Certificate of Occupancy (1) * 07.29.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 07.29.2024 |
|
|
-- |
-- |
Schedule Closing (0) 07.28.2024 |
|
|
-- |
-- |
Buyer Walk Through (1) 07.25.2024 |
Hoping for final walkthrough for Wednesday 7/24 |
|
-- |
-- |
Payment for Upgrades (0) 07.28.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 07.25.2024 |
|
|
-- |
-- |
Review Settlement Statement (0) 07.28.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 07.30.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 07.01.2024 |
|
|
-- |
-- |
Closing (1) 08.05.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 08.26.2024 |
|
|