1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 52  ::  1394 Appaloosa Court
[ BUILD: 20231957 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Missing side window
--   --   Expand patio
--   --   Bathtub needed in bonus On site 6/1
--   --   Paint ceiling of garage Painter
--   --   Farmhouse sink onsite
--   --   Finish the bonus room and bathroom
--   --   I think callback is supposed to be pale oak not gray Hall bath, Painter
--   --   Front white van piece needs to be caulked or readjusted Vinyl piece Davenport - Jeremy
--   --   Finish trim after cabinets are installed
--   --   Complete drywall finishing in basement bonus room, and bath
--   --   Need Electricity!
--   --   Really wants to close by July 15
--   --   Is bonus room door framing, correct? Door is removed.
--   --   Spice rack door handle is not straight Fred
--   --   Upstairs bedroom needs to be white, not pale oak Painter
--   --   Possible drywall repair needed, and bonus bathroom at trim
--   --   Finish carpet in master closet
--   --   Finish carpet in master closet on order
--   --   Pretty large gaps in kitchen island trim. Is that supposed to be caulked?
--   --   Scribe needed around farmhouse sink Fred
--   --   Middle front window cracked at corner
--   --   remove baseboard to seating can be installed
--   --   replacement cabinets arriving in about 2 weeks from 7/8 Fred - working to schedule
--   --   Finish shelving in master closet Paul
--   --   Drywall repair needed above seating in kitchen Drywallers
--   --   Cable covers needed on electric trim out
--   --   Steps have a few spots that looks like stain, wasn’t absorbed equally. Issac aware
--   --   Remove large block of concrete from yard Tom
--   --   Needs final locks on keyed doors
--   --   Should the fan blades be facing down with the fake wood design? Technically, no, but the blades matched the floor perfectly. We won’t do anything, unless the buyer requests it.
--   --   install dishwasher
--   --   flatten out side yard Pettit
--   --   Add dirt and sod around patio where it’s not level to ground and grass will not grow Pettit. Need sod. 8/3
--   --   Add shoe molding to basement bathroom George
--   --   Sod out front may need replacing as well Pettit
--   --   Clean out garage Jill
--   --   Finish staining steps
--   --   Backsplash in kitchen Greg is aware. Jill following up.
--   --   Repaint black steps Issac aware
--   --   CODED LOCKBOX 5252
--   --   Clean off back patio Jill
--   --  
--   --   Bonus room door needs to be trimmed rubs against carpet George
--   --   Lots of spots were paint is on luxury vinyl plank Issac checking
--   --   Clean off paint off all door hinges Painters
--   --   Paint attic access panel Painters
--   --   Windows screens to be installed Jill
--   --   knick in wall between hall light fixtures Painters
--   --   Cover cable box in garage
--   --   Replace transition strip leading to kitchen Denny - Mon, Jul 29
--   --   Banquette seating needs attention{lots of scuff marks) Parts on order
--   --   Remove the 2 toilets from garage Jill
--   --   Raise the chandelier 1 bar length Electrician
--   --   Raise the 2 pendant lights to the same height as the chandelier Electrician
--   --   Very few paint touch ups!! Painters
--   --   Install bonus bathroom, shoe molding
--   --   Very invisible, scuff marks on risers from foyer to second level Jill or Painter
--   --   Masie Fowler 540-746-4002 mfowler@fowlerfamilymedicine.com
-- -- Ratified Contract? (0)  05.01.2024    
-- -- $2500 Deposit Received (0)  05.04.2024    
-- -- Association Packet Requested (0)  05.04.2024    
-- -- Association Packet Received (0)  05.04.2024    
-- -- Selections Meeting (0)  05.16.2024     Wednesday 5/15 at 3:30
-- -- Selections Sheet Signed (0)  05.23.2024     5/16: sent to buyer for review
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.25.2024     5/25: sent to Jerry
-- -- Deposit For Upgrades Received (0)  05.25.2024    
-- -- Building Permit (30)  01.04.2024    
-- -- Order Roof & Floor Trusses (1)  02.12.2024    
-- -- Order Windows & Doors (0)  02.12.2024    
-- -- Stake Out Home (1)  01.04.2024    
-- -- Excavate (2)  01.04.2024    
-- -- Inspection (Footers) (1)  01.04.2024    
-- -- Inspection (Concrete Wall) (1)  01.04.2024    
-- -- Pour Footers (1)  01.04.2024    
-- -- Set Forms (2)  01.04.2024    
-- -- Pour Foundation Walls (1)  01.04.2024    
-- -- Plumb Slab (2)  01.07.2024    
-- -- Inspection (Plumbing Under Slab) (1)  02.08.2024    
-- -- Inspection (Conduit Under Slab) (1)  02.08.2024    
-- -- Prepare Slab (1)  02.08.2024    
-- -- Inspection (Slab) (1)  02.08.2024    
-- -- Inspection (Drain Tile) (0)  02.08.2024    
-- -- Pour Slab (1) *   02.08.2024    
-- -- Settlement Agent Confirmed (0)  06.05.2024     sent
-- -- Framing I (9)  02.15.2024    
-- -- Order Steps (0)  03.11.2024    
-- -- Order Tubs / Showers (0)  03.11.2024    
-- -- Framing II (8)  02.19.2024    
-- -- Framing III (8) *   02.22.2024    
-- -- Verify Window & Roof Structure (0)  03.04.2024    
-- -- Install Stairs (0)  03.11.2024    
-- -- Windows & Doors (0)  04.03.2024    
-- -- House Number and Status in Window (0)  04.03.2024    
-- -- Roofing (0)  04.04.2024    
-- -- Order Cabinets (0)  06.13.2024    
-- -- Order Appliances (0)  06.10.2024     ordered 5/28
-- -- Deck (0)  04.03.2024    
-- -- Gutters (0)  05.26.2024    
-- -- Driveway (0)  05.29.2024    
-- -- Patio (0)  04.03.2024    
-- -- Privacy Divider / Fence (0)  06.26.2024    
-- -- Sod / Seed / Landscaping (0)  07.20.2024    
-- -- HVAC Rough In (4)  03.16.2024     in process 3/13
-- -- Inspection (Rough In HVAC) (1)  05.01.2024    
-- -- Rough In Microwave Vent (0)  03.13.2024    
-- -- Plumbing Rough In (4)  04.17.2024     In process 4/12
-- -- Inspection (Rough In Plumbing) (1)  05.01.2024    
-- -- Electric Rough In (4)  04.24.2024    
-- -- Inspection (Rough In Electric) (1)  05.01.2024    
-- -- Inspection (Deck Piers) (0)  05.01.2024    
-- -- Inspection (Framing) (1)  05.01.2024    
-- -- Exterior Vinyl (0) *   05.06.2024    
-- -- Exterior Stone (0)  05.18.2024    
-- -- Insulation (2)  05.01.2024    
-- -- Inspection (Insulation) (1)  05.04.2024    
-- -- Inspection (Electric Service) (0)  05.20.2024    
-- -- Set Electric Meter (0)  07.19.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  06.06.2024    
-- -- Drywall (Hang) (4) *   05.08.2024     In process 5/4
-- -- Loan Approval (0)  07.19.2024     Cindy Rader, First Citizens (100% MD)
-- -- Deed Preparation (0)  07.19.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   05.22.2024    
-- -- Paint 1 (1)  05.22.2024    
-- -- Garage Door (0)  06.26.2024    
-- -- House Numbers (0)  06.26.2024    
-- -- Mailbox (0)  07.07.2024    
-- -- Cabinet Installation (2) *   06.26.2024     June 25
-- -- Granite Installation (1) *   07.06.2024    
-- -- Interior Trim - Install (3)  06.12.2024    
-- -- Order Plumbing / Lighting Fixtures (0)  06.06.2024    
-- -- Interior Trim - Paint (1)  06.12.2024    
-- -- Luxury Vinyl Plank (3) *   06.26.2024     In process 6/22
-- -- Luxury Vinyl Tile (0)  06.22.2024    
-- -- Paint 2 (3)  06.26.2024    
-- -- Cover Floors (1)  07.17.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  06.17.2024    
-- -- Shoe Moulding (0)  07.10.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  07.17.2024     In process 7/10
-- -- Install Coded Lockbox (add extra keys) (0)  07.22.2024    
-- -- Pay Water / Sewer Taps (0)  06.10.2024    
-- -- Set Water Meter (0)  06.20.2024    
-- -- Electric Trim Out (3)  07.13.2024     in process 7/8
-- -- Ceiling Fans (0)  07.18.2024    
-- -- HVAC Trim Out (1)  07.22.2024     7/18
-- -- Blower Door Test (1)  07.25.2024     Mon, 7/22
-- -- Plumbing Trim Out (2)  07.17.2024     In process 7/13
-- -- Install Appliances (0) *   07.18.2024    
-- -- Paint 3 (2) *   07.07.2024    
-- -- Carpet (2)  06.30.2024     In process 6/26
-- -- Appraiser Confirms Construction Completion (0)  07.28.2024    
-- -- Inspection (Final HVAC) (1)  07.25.2024    
-- -- Inspection (Final Plumbing) (1)  07.25.2024    
-- -- Inspection (Final Electric) (1)  07.25.2024    
-- -- Inspection (Final Building) (2) *   07.25.2024     Monday- July 22nd
-- -- Pre Walk Through (0)  07.22.2024     Kate - 7/19
-- -- Stain Hardwood Stairs (1)  07.13.2024     In process 7/10
-- -- Cleaning (1)  07.22.2024     Lynn starting 7/18
-- -- Certificate of Occupancy (1) *   07.29.2024    
-- -- C.O. to Lender (0)  07.29.2024    
-- -- Schedule Closing (0)  07.28.2024    
-- -- Buyer Walk Through (1)  07.25.2024     Hoping for final walkthrough for Wednesday 7/24
-- -- Payment for Upgrades (0)  07.28.2024    
-- -- Keys to Settlement Agent (0)  07.25.2024    
-- -- Review Settlement Statement (0)  07.28.2024    
-- -- Jerry Signs Closing Documents (0)  07.30.2024    
-- -- Request Trash Tote From POA Manager (0)  07.01.2024    
-- -- Closing (1)  08.05.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  08.26.2024