| TO DO | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Finished Bonus Room | ||||
| Finished Bonus Bathroom | ||||
| Luxury Vinyl Plank in Bonus Room | ||||
| Oak steps to bedroom level | ||||
| Shower Door, heavy glass with black trim | ||||
| Expanded Driveway | ||||
| Expanded 12 x 18 deck | ||||
| Amendment to increase price by $25,550 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 02.08.2024 | ||
| -- | -- | Inspection (Concrete Wall) (1) 02.08.2024 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 03.14.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 03.14.2024 | ||
| -- | -- | Inspection (Slab) (1) 03.14.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 03.14.2024 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 05.18.2024 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 05.18.2024 | ||
| -- | -- | Inspection (Rough In Electric) (1) 05.18.2024 | ||
| -- | -- | Inspection (Framing) (1) * 05.18.2024 | ||
| -- | -- | Inspection (Deck Piers) (0) 05.18.2024 | ||
| -- | -- | Inspection (Insulation) (1) 05.22.2024 | ||
| -- | -- | Inspection (Electric Service) (0) 07.11.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 04.04.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 04.04.2024 | ||
| -- | -- | Inspection (Final HVAC) (0) 08.12.2024 | ||
| -- | -- | Inspection (Final Plumbing) (0) 08.12.2024 | ||
| -- | -- | Inspection (Final Electric) (0) 08.12.2024 | ||
| -- | -- | Inspection (Final Building) (4) * 08.12.2024 | Friday, August 9 | |