CODED LOCKBOX 5656 |
|
|
-- |
-- |
USDA loan |
|
|
-- |
-- |
Dented front awning |
Davenport |
|
-- |
-- |
Install screens |
Jill |
|
-- |
-- |
Door knobs, missing and bonus room, and HVAC vent |
Just door knobs 11/23 |
|
-- |
-- |
Outlet uneven in upstairs hallway |
electrician |
|
-- |
-- |
She doesn’t fully cover gap between flooring and wall in master bedroom |
Shoe Mold - Denny |
|
-- |
-- |
Back patio door does not latch correctly |
Paul, Joe, Don |
|
-- |
-- |
Refrigerator is very loud. Jill check it out. 11/23 |
Jill |
|
-- |
-- |
Reconfigure rear downspout based on larger deck |
Davenport |
|
Wed |
Nov 27 |
Appraiser Confirms Construction Completion (0) |
|
|
Wed |
Nov 27 |
Cleaning (1) |
|
|
Thu |
Nov 28 |
Schedule Closing (0) |
|
|
Thu |
Nov 28 |
Buyer Walk Through (1) |
|
|
Fri |
Nov 29 |
Review Settlement Statement (0) |
|
|
Fri |
Nov 29 |
Jerry Signs Closing Documents (0) |
|
|
Fri |
Nov 29 |
Closing (1) |
Brittany @ West View Title |
|
Mon |
Dec 2 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Can only be 10x10 deck |
|
|
-- |
-- |
This deck has quite a few screws that need to be nailed in or removed? |
|
|
-- |
-- |
Is the farmhouse sink on site? I’m not seeing it. |
|
|
-- |
-- |
All drawer hardware is missing |
|
|
-- |
-- |
Sink is sitting on top of kitchen island |
|
|
-- |
-- |
Can the deck be 12 x 18? |
|
|
-- |
-- |
Prepare basement and bathroom for drywall |
Drywall needs final sanding 10/26 |
|
-- |
-- |
Remove screen from back deck |
|
|
-- |
-- |
Two bathtubs in garage |
|
|
-- |
-- |
Patch holes in basement floor |
|
|
-- |
-- |
Needs bathtub in bonus bath |
|
|
-- |
-- |
A few shelves need to be hung in master closet after carpet is installed |
|
|
-- |
-- |
Powder bath mirror needs installed |
|
|
-- |
-- |
Powder bath light fixture needs installed |
|
|
-- |
-- |
Is the sink set correctly in to the countertops? |
Kate has a plan |
|
-- |
-- |
Reinstall hall bathroom countertop |
|
|
-- |
-- |
Install the master bathroom countertops |
|
|
-- |
-- |
Microwave vent not working |
CJ |
|
-- |
-- |
Incorrect refrigerator has been installed |
CJ |
|
-- |
-- |
Master bathroom needs side, splash |
|
|
-- |
-- |
Install luxury vinyl planks upstairs |
|
|
-- |
-- |
Powder bath, light fixture needed, and pedestal sink |
|
|
-- |
-- |
Black master shower drain is going to be needed here also |
|
|
-- |
-- |
Remove the double vanity top from the master bathroom |
|
|
-- |
-- |
Make a variety of vinyl repairs to where deck was expanded |
Davenport |
|
-- |
-- |
Put gutters back up |
Davenport |
|
-- |
-- |
Deck exterior light needed |
Electrician |
|
-- |
-- |
Light fixture needed powder bath |
Electrician |
|
-- |
-- |
Bonus room needs doors |
|
|
-- |
-- |
When is bonus bathroom vanity being delivered? |
|
|
-- |
-- |
Bonus room needs doors and trim |
George |
|
-- |
-- |
Finish touchup paint |
Painter |
|
-- |
-- |
Large hole in master shower |
Roger |
|
-- |
-- |
Install patio and deck, door screens, and window screens |
Jill |
|
-- |
-- |
Whiteboard needed on back deck, bonus room level |
Tom |
|
-- |
-- |
Install bonus bathroom vanity |
Tom will install |
|
-- |
-- |
Kitchen lightbulb needed |
Jill |
|
-- |
-- |
Put attic access in place |
after final inspection |
|
-- |
-- |
LVP in bonus room being installed 11/13 |
|
|
-- |
-- |
Needs plumbing trim out at sink in bonus room |
we need the vanity first |
|
-- |
-- |
Put HVAC covers in floor |
Master bedroom |
|
-- |
-- |
Ratified Contract? (0) 09.25.2024 |
|
|
-- |
-- |
$2500 Deposit Received (0) 09.25.2024 |
|
|
-- |
-- |
Association Packet Requested (0) 09.25.2024 |
|
|
-- |
-- |
Association Packet Received (0) 10.04.2024 |
|
|
-- |
-- |
Selections Meeting (0) 09.25.2024 |
|
|
-- |
-- |
Selections Sheet Signed (0) 09.25.2024 |
|
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 09.25.2024 |
|
|
-- |
-- |
Deposit For Upgrades Received (0) 09.25.2024 |
|
|
-- |
-- |
Building Permit (30) 02.19.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 05.23.2024 |
|
|
-- |
-- |
Order Windows & Doors (0) 06.19.2024 |
|
|
-- |
-- |
Stake Out Home (1) 02.19.2024 |
|
|
-- |
-- |
Excavate (2) 02.19.2024 |
|
|
-- |
-- |
Inspection (Footers) (1) 02.19.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 02.19.2024 |
|
|
-- |
-- |
Pour Footers (1) 02.19.2024 |
|
|
-- |
-- |
Set Forms (2) 04.18.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1) 04.18.2024 |
|
|
-- |
-- |
Plumb Slab (2) 04.18.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 04.18.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 04.18.2024 |
|
|
-- |
-- |
Prepare Slab (1) 04.18.2024 |
|
|
-- |
-- |
Inspection (Slab) (1) 04.18.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 04.18.2024 |
|
|
-- |
-- |
Pour Slab (1) * 04.18.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 10.25.2024 |
sent to WVT on 10/24 |
|
-- |
-- |
Framing I (9) 04.22.2024 |
|
|
-- |
-- |
Order Steps (0) 05.23.2024 |
|
|
-- |
-- |
Order Tubs / Showers (0) 06.19.2024 |
|
|
-- |
-- |
Framing II (8) 05.13.2024 |
|
|
-- |
-- |
Framing III (8) * 05.23.2024 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 05.23.2024 |
|
|
-- |
-- |
Install Stairs (0) 05.23.2024 |
|
|
-- |
-- |
Windows & Doors (0) 07.15.2024 |
|
|
-- |
-- |
House Number and Status in Window (0) 07.20.2024 |
|
|
-- |
-- |
Roofing (0) 06.16.2024 |
|
|
-- |
-- |
Order Cabinets (0) 08.06.2024 |
|
|
-- |
-- |
Order Appliances (0) 08.12.2024 |
|
|
-- |
-- |
Deck (0) 07.17.2024 |
|
|
-- |
-- |
Gutters (0) 08.21.2024 |
|
|
-- |
-- |
Driveway (0) 09.04.2024 |
|
|
-- |
-- |
Patio (0) 09.07.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 08.14.2024 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 10.06.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 06.03.2024 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 07.10.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 06.05.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 06.22.2024 |
In process 6/19 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 07.10.2024 |
|
|
-- |
-- |
Electric Rough In (4) 06.30.2024 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 07.10.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 09.05.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 07.10.2024 |
|
|
-- |
-- |
Exterior Vinyl (0) * 08.18.2024 |
|
|
-- |
-- |
Exterior Stone (0) 08.18.2024 |
|
|
-- |
-- |
Insulation (2) 07.10.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 07.17.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 09.05.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 09.17.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 04.04.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 04.04.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 08.15.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 07.17.2024 |
|
|
-- |
-- |
Loan Approval (0) 11.13.2024 |
USDA |
|
-- |
-- |
Deed Preparation (0) 10.28.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 08.07.2024 |
In process 8/3 |
|
-- |
-- |
Paint 1 (1) 08.10.2024 |
|
|
-- |
-- |
Garage Door (0) 08.18.2024 |
|
|
-- |
-- |
House Numbers (0) 09.18.2024 |
|
|
-- |
-- |
Mailbox (0) 09.18.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 08.21.2024 |
|
|
-- |
-- |
Granite Installation (1) * 10.09.2024 |
|
|
-- |
-- |
Interior Trim - Install (3) 09.07.2024 |
In process 9/4 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 09.26.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 09.07.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 09.15.2024 |
In process 9/11 |
|
-- |
-- |
Luxury Vinyl Tile (0) 09.18.2024 |
|
|
-- |
-- |
Paint 2 (3) 09.18.2024 |
|
|
-- |
-- |
Cover Floors (1) 10.30.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 10.10.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 09.28.2024 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 10.02.2024 |
In process 9/28. Few bathroom accessories are in place. |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 10.19.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 09.12.2024 |
|
|
-- |
-- |
Set Water Meter (0) 09.17.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 09.28.2024 |
In process 9/25 |
|
-- |
-- |
Ceiling Fans (0) 09.25.2024 |
|
|
-- |
-- |
HVAC Trim Out (1) 09.18.2024 |
|
|
-- |
-- |
Blower Door Test (1) 11.07.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 10.30.2024 |
In process 10/26 |
|
-- |
-- |
Install Appliances (0) * 10.05.2024 |
|
|
-- |
-- |
Paint 3 (2) * 09.21.2024 |
|
|
-- |
-- |
Carpet (2) 10.05.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 11.21.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 11.21.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 11.21.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 11.23.2024 |
reinspect Fri, Nov 22 |
|
-- |
-- |
Pre Walk Through (0) 11.21.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 10.16.2024 |
In process 10/12 |
|
-- |
-- |
Certificate of Occupancy (1) * 11.27.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 11.27.2024 |
|
|
-- |
-- |
Payment for Upgrades (0) 11.13.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 11.18.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 11.13.2024 |
|
|