-- | -- | Sink is sitting on top of kitchen island | ||
-- | -- | Can the deck be 12 x 18? | ||
-- | -- | Prepare basement and bathroom for drywall | ||
-- | -- | Remove screen from back deck | ||
Fri | Sep 20 | Ratified Contract? (0) | ||
Microwave vented to exterior | ||||
Living Room Ceiling Fan | ||||
Finished Bonus Room | ||||
Finished Bonus Bathroom | ||||
Expanded 12 x 18 deck (replace current) | ||||
Level III Quartz Countertops | ||||
French Style Refrigerator | ||||
Level 3 Quartz countertops Bathroom | ||||
Heavy Glass Shower Door | ||||
LVP in upstairs hallway and Bedrooms | ||||
LVP in Bonus Room | ||||
Painted Carpet Grade Steps | ||||
Eggshell Paint | ||||
Fri | Sep 20 | $2500 Deposit Received (0) | ||
Fri | Sep 20 | Association Packet Requested (0) | ||
Fri | Sep 20 | Association Packet Received (0) | ||
Fri | Sep 20 | Selections Meeting (0) | ||
Fri | Sep 20 | Selections Sheet Signed (0) | ||
Fri | Sep 20 | Amendment for Upgrades (B,S,L,T,BCP) (0) | ||
Fri | Sep 20 | Deposit For Upgrades Received (0) | ||
Fri | Sep 20 | Settlement Agent Confirmed (0) | ||
Fri | Sep 20 | Sod / Seed / Landscaping (0) | ||
Fri | Sep 20 | Loan Approval (0) | ||
Fri | Sep 20 | Deed Preparation (0) | ||
Fri | Sep 20 | Granite Installation (1) | ||
Mon | Sep 23 | Order Plumbing / Lighting Fixtures (0) | ||
Mon | Sep 23 | Cover Floors (1) | ||
Tue | Sep 24 | Deliver Plumbing / Lighting Fixtures (0) | ||
Tue | Sep 24 | Shoe Moulding (0) | ||
Tue | Sep 24 | Shelving, Door Knobs, Fire Extinguisher (0) | ||
Tue | Sep 24 | Install Coded Lockbox (add extra keys) (0) | ||
Tue | Sep 24 | Electric Trim Out (3) | ||
Fri | Sep 27 | Ceiling Fans (0) | ||
Fri | Sep 27 | Blower Door Test (1) | ||
Mon | Sep 30 | Plumbing Trim Out (2) | ||
Wed | Oct 2 | Install Appliances (0) | ||
Wed | Oct 2 | Paint 3 (2) | ||
Fri | Oct 4 | Carpet (2) | ||
Tue | Oct 8 | Appraiser Confirms Construction Completion (0) | ||
Tue | Oct 8 | Inspection (Final HVAC) (1) | ||
Wed | Oct 9 | Inspection (Final Plumbing) (1) | ||
Thu | Oct 10 | Inspection (Final Electric) (1) | ||
Fri | Oct 11 | Inspection (Final Building) (2) | ||
Tue | Oct 15 | Pre Walk Through (0) | ||
Tue | Oct 15 | Stain Hardwood Stairs (1) | ||
Wed | Oct 16 | Cleaning (1) | ||
Thu | Oct 17 | Certificate of Occupancy (1) | ||
Fri | Oct 18 | C.O. to Lender (0) | ||
Fri | Oct 18 | Schedule Closing (0) | ||
Fri | Oct 18 | Buyer Walk Through (1) | ||
Mon | Oct 21 | Payment for Upgrades (0) | ||
Mon | Oct 21 | Keys to Settlement Agent (0) | ||
Mon | Oct 21 | Review Settlement Statement (0) | ||
Mon | Oct 21 | Jerry Signs Closing Documents (0) | ||
Mon | Oct 21 | Request Trash Tote From POA Manager (0) | ||
Mon | Oct 21 | Closing (1) | ||
Tue | Oct 22 | Remove Coded Lockbox (0) | ||
-- | -- | Can only be 10x10 deck | ||
-- | -- | This deck has quite a few screws that need to be nailed in or removed? | ||
-- | -- | Is the farmhouse sink on site? I’m not seeing it. | ||
-- | -- | All drawer hardware is missing | ||
-- | -- | Building Permit (30) 02.19.2024 | ||
-- | -- | Order Roof & Floor Trusses (1) 05.23.2024 | ||
-- | -- | Order Windows & Doors (0) 06.19.2024 | ||
-- | -- | Stake Out Home (1) 02.19.2024 | ||
-- | -- | Excavate (2) 02.19.2024 | ||
-- | -- | Inspection (Footers) (1) 02.19.2024 | ||
-- | -- | Inspection (Concrete Wall) (1) 02.19.2024 | ||
-- | -- | Pour Footers (1) 02.19.2024 | ||
-- | -- | Set Forms (2) 04.18.2024 | ||
-- | -- | Pour Foundation Walls (1) 04.18.2024 | ||
-- | -- | Plumb Slab (2) 04.18.2024 | ||
-- | -- | Inspection (Plumbing Under Slab) (1) 04.18.2024 | ||
-- | -- | Inspection (Conduit Under Slab) (1) 04.18.2024 | ||
-- | -- | Prepare Slab (1) 04.18.2024 | ||
-- | -- | Inspection (Slab) (1) 04.18.2024 | ||
-- | -- | Inspection (Drain Tile) (0) 04.18.2024 | ||
-- | -- | Pour Slab (1) 04.18.2024 | ||
-- | -- | Framing I (9) 04.22.2024 | ||
-- | -- | Order Steps (0) 05.23.2024 | ||
-- | -- | Order Tubs / Showers (0) 06.19.2024 | ||
-- | -- | Framing II (8) 05.13.2024 | ||
-- | -- | Framing III (8) 05.23.2024 | ||
-- | -- | Verify Window & Roof Structure (0) 05.23.2024 | ||
-- | -- | Install Stairs (0) 05.23.2024 | ||
-- | -- | Windows & Doors (0) 07.15.2024 | ||
-- | -- | House Number and Status in Window (0) 07.20.2024 | ||
-- | -- | Roofing (0) 06.16.2024 | ||
-- | -- | Order Cabinets (0) 08.06.2024 | ||
-- | -- | Order Appliances (0) 08.12.2024 | ||
-- | -- | Deck (0) 07.17.2024 | ||
-- | -- | Gutters (0) 08.21.2024 | ||
-- | -- | Driveway (0) 09.04.2024 | ||
-- | -- | Patio (0) 09.07.2024 | ||
-- | -- | Privacy Divider / Fence (0) 08.14.2024 | ||
-- | -- | HVAC Rough In (4) 06.03.2024 | ||
-- | -- | Inspection (Rough In HVAC) (1) 07.10.2024 | ||
-- | -- | Rough In Microwave Vent (0) 06.05.2024 | ||
-- | -- | Plumbing Rough In (4) 06.22.2024 | In process 6/19 | |
-- | -- | Inspection (Rough In Plumbing) (1) 07.10.2024 | ||
-- | -- | Electric Rough In (4) 06.30.2024 | ||
-- | -- | Inspection (Rough In Electric) (1) 07.10.2024 | ||
-- | -- | Inspection (Deck Piers) (0) 09.05.2024 | ||
-- | -- | Inspection (Framing) (1) 07.10.2024 | ||
-- | -- | Exterior Vinyl (0) 08.18.2024 | ||
-- | -- | Exterior Stone (0) 08.18.2024 | ||
-- | -- | Insulation (2) 07.10.2024 | ||
-- | -- | Inspection (Insulation) (1) 07.17.2024 | ||
-- | -- | Inspection (Electric Service) (0) 09.05.2024 | ||
-- | -- | Set Electric Meter (0) 09.17.2024 | ||
-- | -- | Inspection (Main Sewer Line) (0) 04.04.2024 | ||
-- | -- | Inspection (Main Water Line) (0) 04.04.2024 | ||
-- | -- | Order Interior Doors & Trim (0) 08.15.2024 | ||
-- | -- | Drywall (Hang) (4) 07.17.2024 | ||
-- | -- | Drywall (Tape, Block, Skim, Sand) (6) 08.07.2024 | In process 8/3 | |
-- | -- | Paint 1 (1) 08.10.2024 | ||
-- | -- | Garage Door (0) 08.18.2024 | ||
-- | -- | House Numbers (0) 09.18.2024 | ||
-- | -- | Mailbox (0) 09.18.2024 | ||
-- | -- | Cabinet Installation (2) 08.21.2024 | ||
-- | -- | Interior Trim - Install (3) 09.07.2024 | In process 9/4 | |
-- | -- | Interior Trim - Paint (1) 09.07.2024 | ||
-- | -- | Luxury Vinyl Plank (3) 09.15.2024 | In process 9/11 | |
-- | -- | Luxury Vinyl Tile (0) 09.18.2024 | ||
-- | -- | Paint 2 (3) 09.18.2024 | ||
-- | -- | Pay Water / Sewer Taps (0) 09.12.2024 | ||
-- | -- | Set Water Meter (0) 09.17.2024 | ||
-- | -- | HVAC Trim Out (1) 09.18.2024 | ||