1 14 73 65 61 62 63 ADDR
CONGERS-2 - 56  ::  1372 Appaloosa Court
[ BUILD: 20231961 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Can only be 10x10 deck
--   --   This deck has quite a few screws that need to be nailed in or removed?
--   --   Is the farmhouse sink on site? I’m not seeing it.
--   --   All drawer hardware is missing
--   --   Sink is sitting on top of kitchen island
--   --   Can the deck be 12 x 18?
--   --   Prepare basement and bathroom for drywall Drywall needs final sanding 10/26
--   --   Remove screen from back deck
--   --   Two bathtubs in garage
--   --   Patch holes in basement floor
--   --   Needs bathtub in bonus bath
--   --   A few shelves need to be hung in master closet after carpet is installed
--   --   Powder bath mirror needs installed
--   --   Powder bath light fixture needs installed
--   --   Is the sink set correctly in to the countertops? Kate has a plan
--   --   Reinstall hall bathroom countertop
--   --   Install the master bathroom countertops
--   --   Microwave vent not working CJ
--   --   Incorrect refrigerator has been installed CJ
--   --   Master bathroom needs side, splash
--   --   Install luxury vinyl planks upstairs
--   --   Powder bath, light fixture needed, and pedestal sink
--   --   Black master shower drain is going to be needed here also
--   --   CODED LOCKBOX 5656
--   --   Remove the double vanity top from the master bathroom
--   --   USDA loan
--   --   Dented front awning Davenport
--   --   Make a variety of vinyl repairs to where deck was expanded Davenport
--   --   Put gutters back up Davenport
--   --   Deck exterior light needed Electrician
--   --   Light fixture needed powder bath Electrician
--   --   Bonus room needs doors
--   --   When is bonus bathroom vanity being delivered?
--   --   Bonus room needs doors and trim George
--   --   Finish touchup paint Painter
--   --   Large hole in master shower Roger
--   --   Install patio and deck, door screens, and window screens Jill
--   --   Whiteboard needed on back deck, bonus room level Tom
--   --   Install bonus bathroom vanity Tom will install
--   --   Install screens Jill
--   --   Kitchen lightbulb needed Jill
--   --   Put attic access in place after final inspection
--   --   LVP in bonus room being installed 11/13
--   --   Door knobs, missing and bonus room, and HVAC vent Just door knobs 11/23
--   --   Needs plumbing trim out at sink in bonus room we need the vanity first
--   --   Outlet uneven in upstairs hallway electrician
--   --   Put HVAC covers in floor Master bedroom
--   --   She doesn’t fully cover gap between flooring and wall in master bedroom Shoe Mold - Denny
--   --   Back patio door does not latch correctly Paul, Joe, Don
--   --   Refrigerator is very loud. Jill check it out. 11/23 Noise sort of resolved
--   --   Reconfigure rear downspout based on larger deck Davenport
--   --  
--   --   Mirror needed, and bonus bath In - Paul
--   --   The white part of the hardwood treads may need to be repainted. Pretty significant staining. Lynn or painters
--   --   Move this splash block over to the gutter and possibly patch holes and vinyl? Holes just need to be patched - Jeremy, Davenport
--   --   Scratch on upstairs landing On flooring - Denny
--   --   Adjust mirror and light fixture drywaller, painter
--   --   Patch drywall where light fixture was moved powder room
--   --   needs white board on lower deck area Tom
--   --   Crack in primary bedroom on wall needs touch up
--   --   Fill holes in siding on back of townhouse where downspout used to be attached Tom
--   --   Range not working Kate will send the warranty info to buyer
--   --   install screens Still waiting on screens of the correct size
-- -- Ratified Contract? (0)  09.25.2024    
-- -- $2500 Deposit Received (0)  09.25.2024    
-- -- Association Packet Requested (0)  09.25.2024    
-- -- Association Packet Received (0)  10.04.2024    
-- -- Selections Meeting (0)  09.25.2024    
-- -- Selections Sheet Signed (0)  09.25.2024    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.25.2024    
-- -- Deposit For Upgrades Received (0)  09.25.2024    
-- -- Building Permit (30)  02.19.2024    
-- -- Order Roof & Floor Trusses (1)  05.23.2024    
-- -- Order Windows & Doors (0)  06.19.2024    
-- -- Stake Out Home (1)  02.19.2024    
-- -- Excavate (2)  02.19.2024    
-- -- Inspection (Footers) (1)  02.19.2024    
-- -- Inspection (Concrete Wall) (1)  02.19.2024    
-- -- Pour Footers (1) *   02.19.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.18.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.18.2024    
-- -- Prepare Slab (1)  04.18.2024    
-- -- Inspection (Slab) (1)  04.18.2024    
-- -- Inspection (Drain Tile) (0)  04.18.2024    
-- -- Pour Slab (1) *   04.18.2024    
-- -- Settlement Agent Confirmed (0)  10.25.2024     sent to WVT on 10/24
-- -- Framing I (9)  04.22.2024    
-- -- Order Steps (0)  05.23.2024    
-- -- Order Tubs / Showers (0)  06.19.2024    
-- -- Framing II (8)  05.13.2024    
-- -- Framing III (8) *   05.23.2024    
-- -- Verify Window & Roof Structure (0)  05.23.2024    
-- -- Install Stairs (0)  05.23.2024    
-- -- Windows & Doors (0) *   07.15.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0) *   06.16.2024    
-- -- Order Cabinets (0)  08.06.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  07.17.2024    
-- -- Gutters (0)  08.21.2024    
-- -- Driveway (0) *   09.04.2024    
-- -- Patio (0)  09.07.2024    
-- -- Privacy Divider / Fence (0)  08.14.2024    
-- -- Sod / Seed / Landscaping (0)  10.06.2024    
-- -- HVAC Rough In (4)  06.03.2024    
-- -- Inspection (Rough In HVAC) (1)  07.10.2024    
-- -- Rough In Microwave Vent (0)  06.05.2024    
-- -- Plumbing Rough In (4)  06.22.2024     In process 6/19
-- -- Inspection (Rough In Plumbing) (1)  07.10.2024    
-- -- Electric Rough In (4)  06.30.2024    
-- -- Inspection (Rough In Electric) (1)  07.10.2024    
-- -- Inspection (Deck Piers) (0)  09.05.2024    
-- -- Inspection (Framing) (1) *   07.10.2024    
-- -- Exterior Vinyl (0) *   08.18.2024    
-- -- Exterior Stone (0)  08.18.2024    
-- -- Insulation (2) *   07.10.2024    
-- -- Inspection (Insulation) (1)  07.17.2024    
-- -- Inspection (Electric Service) (0)  09.05.2024    
-- -- Set Electric Meter (0) *   09.17.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.15.2024    
-- -- Drywall (Hang) (4) *   07.17.2024    
-- -- Loan Approval (0)  11.13.2024     USDA
-- -- Deed Preparation (0)  10.28.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.07.2024     In process 8/3
-- -- Paint 1 (1)  08.10.2024    
-- -- Garage Door (0) *   08.18.2024    
-- -- House Numbers (0)  09.18.2024    
-- -- Mailbox (0)  09.18.2024    
-- -- Cabinet Installation (2) *   08.21.2024    
-- -- Granite Installation (1) *   10.09.2024    
-- -- Interior Trim - Install (3) *   09.07.2024     In process 9/4
-- -- Order Plumbing / Lighting Fixtures (0)  09.26.2024    
-- -- Interior Trim - Paint (1)  09.07.2024    
-- -- Luxury Vinyl Plank (3) *   09.15.2024     In process 9/11
-- -- Luxury Vinyl Tile (0)  09.18.2024    
-- -- Paint 2 (3)  09.18.2024    
-- -- Cover Floors (1)  10.30.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  10.10.2024    
-- -- Shoe Moulding (0)  09.28.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   10.02.2024     In process 9/28. Few bathroom accessories are in place.
-- -- Install Coded Lockbox (add extra keys) (0)  10.19.2024    
-- -- Pay Water / Sewer Taps (0)  09.12.2024    
-- -- Set Water Meter (0) *   09.17.2024    
-- -- Electric Trim Out (3)  09.28.2024     In process 9/25
-- -- Ceiling Fans (0)  09.25.2024    
-- -- HVAC Trim Out (1)  09.18.2024    
-- -- Blower Door Test (1)  11.07.2024    
-- -- Plumbing Trim Out (2)  10.30.2024     In process 10/26
-- -- Install Appliances (0) *   10.05.2024    
-- -- Paint 3 (2) *   09.21.2024    
-- -- Carpet (2)  10.05.2024    
-- -- Appraiser Confirms Construction Completion (0)  12.02.2024    
-- -- Inspection (Final HVAC) (1)  11.21.2024    
-- -- Inspection (Final Plumbing) (1)  11.21.2024    
-- -- Inspection (Final Electric) (1)  11.21.2024    
-- -- Inspection (Final Building) (2) *   11.23.2024     reinspect Fri, Nov 22
-- -- Pre Walk Through (0)  11.21.2024    
-- -- Stain Hardwood Stairs (1)  10.16.2024     In process 10/12
-- -- Cleaning (1)  12.04.2024     In process 11/30
-- -- Certificate of Occupancy (1) *   11.27.2024    
-- -- C.O. to Lender (0)  11.27.2024    
-- -- Schedule Closing (0)  12.05.2024    
-- -- Buyer Walk Through (1)  12.03.2024     Monday 12/2 3:00 PM
-- -- Payment for Upgrades (0)  11.13.2024    
-- -- Keys to Settlement Agent (0)  11.18.2024    
-- -- Review Settlement Statement (0)  12.09.2024    
-- -- Jerry Signs Closing Documents (0)  12.13.2024    
-- -- Request Trash Tote From POA Manager (0)  11.13.2024    
-- -- Closing (1)  12.16.2024     Brittany @ West View Title - Dec 13
-- -- Remove Coded Lockbox (0)  12.18.2024