| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| Expanded Driveway | ||||
| Finished Bonus Room | ||||
| Finished Bonus Bathroom | ||||
| Expanded 12 x 18 deck (replace current) | ||||
| French Style Refrigerator | ||||
| CRITICAL PATH | ||||
| Tue | Feb 3 | Inspection (Plumbing Under Slab) (1) 04.18.2024 | ||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| White Upgraded Perimeter Kitchen Cabinets | ||||
| Double Waste Basket in Island | ||||
| Three Drawer Base in place of B 36" | ||||
| Microwave vented to exterior | ||||
| LVT Gardenia Upgrade Baths and Laundry | ||||
| Living Room Ceiling Fan | ||||
| Level III Quartz Countertops | ||||
| Level 3 Quartz countertops Bathroom | ||||
| Heavy Glass Shower Door | ||||
| LVP in upstairs hallway and Bedrooms | ||||
| LVP in Bonus Room | ||||
| Painted Carpet Grade Steps | ||||
| Eggshell Paint | ||||
| Upgrades included in contract price | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 12.14.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 02.19.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 04.18.2024 | ||
| -- | -- | Inspection (Slab) (1) 04.18.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 04.18.2024 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 07.10.2024 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 07.10.2024 | ||
| -- | -- | Inspection (Rough In Electric) (1) 07.10.2024 | ||
| -- | -- | Inspection (Framing) (1) * 07.10.2024 | ||
| -- | -- | Inspection (Deck Piers) (0) 09.05.2024 | ||
| -- | -- | Inspection (Insulation) (1) 07.17.2024 | ||
| -- | -- | Inspection (Electric Service) (0) 09.05.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 04.04.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 04.04.2024 | ||
| -- | -- | Inspection (Final HVAC) (0) 11.21.2024 | ||
| -- | -- | Inspection (Final Plumbing) (0) 11.21.2024 | ||
| -- | -- | Inspection (Final Electric) (0) 11.21.2024 | ||
| -- | -- | Inspection (Final Building) (4) * 11.23.2024 | reinspect Fri, Nov 22 | |