1 28 33 37 45 46 47 48 71 52 70 69 67 53 54 55 56 59 58 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 60  ::  1344 Appaloosa Court
[ BUILD: 20231965 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (Sep 18)    show all photos
--   --   1031 closing deadline = early January
--   --   Patch hole in garage floor
    Driveway - could be expanded but with single width entry  
    Vinyl Plank in Upstairs Hallway and Bedroom ($2,900 cost included in contract price)  
    Stained Hardwood Treads to Bedroom Level ($1,890 cost included in contract price)  
    Expanded Driveway (single car width entry) ($1,260 cost included in contract price)  
    Eggshell Finish Paint ($1,050 cost included in contract price)  
    Upgraded LVT upstairs Bathrooms  
    Level III Granite Salinas White in Kitchen  
    Level III Granite Salinas White in Up Baths  
Fri    Sep 20      Windows & Doors (0)      
Fri    Sep 20      House Number and Status in Window (0)      
Fri    Sep 20      Roofing (0)      
Fri    Sep 20      Deck (0)      
Fri    Sep 20      Gutters (0)      
Fri    Sep 20      Driveway (0)      
Fri    Sep 20      Patio (0)      
Fri    Sep 20      Privacy Divider / Fence (0)      
Fri    Sep 20      Sod / Seed / Landscaping (0)      
Fri    Sep 20      HVAC Rough In (4)       In process 9/18
Thu    Sep 26      Inspection (Rough In HVAC) (1)      
Fri    Sep 27      Rough In Microwave Vent (0)      
Fri    Sep 27      Plumbing Rough In (4)      
Thu    Oct 3      Inspection (Rough In Plumbing) (1)      
Fri    Oct 4      Electric Rough In (4)      
Thu    Oct 10      Inspection (Rough In Electric) (1)      
Fri    Oct 11      Inspection (Deck Piers) (0)      
Fri    Oct 11      Inspection (Framing) (1)      
Mon    Oct 14      Exterior Vinyl (0)      
Mon    Oct 14      Exterior Stone (0)      
Mon    Oct 14      Insulation (2)      
Wed    Oct 16      Inspection (Insulation) (1)      
Thu    Oct 17      Inspection (Electric Service) (0)      
Thu    Oct 17      Set Electric Meter (0)      
Thu    Oct 17      Inspection (Main Sewer Line) (0)      
Thu    Oct 17      Inspection (Main Water Line) (0)      
Thu    Oct 17      Order Interior Doors & Trim (0)      
Thu    Oct 17      Drywall (Hang) (4)      
Wed    Oct 23      Loan Approval (0)      
Wed    Oct 23      Deed Preparation (0)      
Wed    Oct 23      Drywall (Tape, Block, Skim, Sand) (6)      
Thu    Oct 31      Paint 1 (1)      
Fri    Nov 1      Garage Door (0)      
Fri    Nov 1      House Numbers (0)      
Fri    Nov 1      Mailbox (0)      
Fri    Nov 1      Cabinet Installation (2)      
Tue    Nov 5      Granite Installation (1)      
Wed    Nov 6      Interior Trim - Install (3)      
Mon    Nov 11      Order Plumbing / Lighting Fixtures (0)      
Mon    Nov 11      Interior Trim - Paint (1)      
Tue    Nov 12      Luxury Vinyl Plank (3)      
Fri    Nov 15      Luxury Vinyl Tile (0)      
Fri    Nov 15      Paint 2 (3)      
Wed    Nov 20      Cover Floors (1)      
Thu    Nov 21      Deliver Plumbing / Lighting Fixtures (0)      
Thu    Nov 21      Shoe Moulding (0)      
Thu    Nov 21      Shelving, Door Knobs, Fire Extinguisher (0)      
Thu    Nov 21      Install Coded Lockbox (add extra keys) (0)      
Thu    Nov 21      Pay Water / Sewer Taps (0)      
Thu    Nov 21      Set Water Meter (0)      
Thu    Nov 21      Electric Trim Out (3)      
Tue    Nov 26      Ceiling Fans (0)      
Tue    Nov 26      HVAC Trim Out (1)      
Wed    Nov 27      Blower Door Test (1)      
Thu    Nov 28      Plumbing Trim Out (2)      
Mon    Dec 2      Install Appliances (0)      
Mon    Dec 2      Paint 3 (2)      
Wed    Dec 4      Carpet (2)      
Fri    Dec 6      Appraiser Confirms Construction Completion (0)      
Fri    Dec 6      Inspection (Final HVAC) (1)      
Mon    Dec 9      Inspection (Final Plumbing) (1)      
Tue    Dec 10      Inspection (Final Electric) (1)      
Wed    Dec 11      Inspection (Final Building) (2)      
Fri    Dec 13      Pre Walk Through (0)      
Fri    Dec 13      Stain Hardwood Stairs (1)      
Mon    Dec 16      Cleaning (1)      
Tue    Dec 17      Certificate of Occupancy (1)      
Wed    Dec 18      C.O. to Lender (0)      
Wed    Dec 18      Schedule Closing (0)      
Wed    Dec 18      Buyer Walk Through (1)      
Thu    Dec 19      Payment for Upgrades (0)      
Thu    Dec 19      Keys to Settlement Agent (0)      
Thu    Dec 19      Review Settlement Statement (0)      
Thu    Dec 19      Jerry Signs Closing Documents (0)      
Thu    Dec 19      Request Trash Tote From POA Manager (0)      
Thu    Dec 19      Closing (1)       Brittany @ West View Title
Fri    Dec 20      Remove Coded Lockbox (0)      
--   --   Driveway - could be expanded but with single width entry
--   --   1031 clsoing deadline = early January
-- -- Ratified Contract? (0)  06.17.2024    
    Driveway - could be expanded but with single width entry  
    Vinyl Plank in Upstairs Hallway and Bedroom ($2,900 cost included in contract price)  
    Stained Hardwood Treads to Bedroom Level ($1,890 cost included in contract price)  
    Expanded Driveway (single car width entry) ($1,260 cost included in contract price)  
    Eggshell Finish Paint ($1,050 cost included in contract price)  
    Upgraded LVT upstairs Bathrooms  
    Level III Granite Salinas White in Kitchen  
    Level III Granite Salinas White in Up Baths  
-- -- $2500 Deposit Received (0)  06.19.2024    
-- -- Association Packet Requested (0)  06.17.2024    
-- -- Association Packet Received (0)  06.21.2024    
-- -- Selections Meeting (0)  07.10.2024    
-- -- Selections Sheet Signed (0)  07.20.2024     7/10: sent to Brandon for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  07.25.2024    
-- -- Deposit For Upgrades Received (0)  07.25.2024    
-- -- Building Permit (30)  04.18.2024    
-- -- Order Roof & Floor Trusses (1)  08.22.2024    
-- -- Order Windows & Doors (0)  09.15.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.22.2024    
-- -- Inspection (Concrete Wall) (1)  05.13.2024    
-- -- Pour Footers (1)  04.25.2024    
-- -- Set Forms (2)  05.13.2024    
-- -- Pour Foundation Walls (1)  05.13.2024    
-- -- Plumb Slab (2)  05.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  07.08.2024    
-- -- Inspection (Conduit Under Slab) (1)  07.08.2024    
-- -- Prepare Slab (1)  07.08.2024    
-- -- Inspection (Slab) (1)  07.08.2024    
-- -- Inspection (Drain Tile) (0)  07.08.2024    
-- -- Pour Slab (1)  07.08.2024    
-- -- Settlement Agent Confirmed (0)  07.28.2024     Sent 7/25/2024
-- -- Framing I (9)  08.22.2024    
-- -- Order Steps (0)  09.15.2024    
-- -- Order Tubs / Showers (0)  09.15.2024    
-- -- Framing II (8)  08.22.2024    
-- -- Framing III (8)  09.12.2024    
-- -- Verify Window & Roof Structure (0)  09.15.2024    
-- -- Install Stairs (0)  09.18.2024    
-- -- Order Cabinets (0)  09.08.2024    
-- -- Order Appliances (0)  08.12.2024