37 ADDR
CONGERS-2 - 60  ::  1344 Appaloosa Court
[ BUILD: 20231965 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Driveway - could be expanded but with single width entry
1031 clsoing deadline = early January
1031 closing deadline = early January
Patch hole in garage floor
Hall bath tub is different here as well
Cover hardwood treads
Bathroom vanities need tops
Call vanity needs hardware
Hall vanity needs hardware Fred
Cover hardwood treads Cover has been removed
Few pieces of missing siding 11/20
Pretty deep scratch in the back of the kitchen island. Jill, can you take a look? Will try repair first
Garage door needs window grills Davenport
Silver closet hinges Jill
Final inspection 12/30/24
Few paint touchups needed in powder bathroom Painter
Mirrors needed in master bath and powder bath Tuesday, Jan 7
Quite a bit of supplies need to be removed from garage and house before cleaning can occur Jill
Trim down green pipes in front of townhouses Tom
Paint front door Painter
CODED LOCKBOX 6060
Replace missing rock Dale
Remove blue tape at front door Jill
Remove fridge in garage Jill, CJ
Cover cable box in garage Jill
Install patio screen door Kenny, Jill
Refrigerator seems abnormally loud
Remove ladder from master closet Jill
Crack in master shower Jill is scheduling the repair
Remove trash from deck when snow melts more Jill
Paint touch up near front door Painter
Remove large piece of insulation
Install screens Jill. Few missing. On order.
Patch and paint screw holes by powder bath light fixture Painter
Add insulation above attic access Jill
Fix BR lock on BR 2 George
Primary Bedroom- replace ceiling fan blades Jill
clea off back deck
install window screens Jill
attic access adjustment
remove ladder primary closet Jill
extra air filter Jill
straighten exhaust fan powder bath Jill
primary shower repair Jill scheduling
clean out garage Jill
missing stone at front door
paint touch up throughout
leave extra paint and stain Joanna
reclean floors and surfaces after punch Lynn
Paint ext door trim Johana
UPGRADES - COMPLETED
    Driveway - could be expanded but with single width entry  
    Vinyl Plank in Upstairs Hallway and Bedroom ($2,900 cost included in contract price)  
    Stained Hardwood Treads to Bedroom Level ($1,890 cost included in contract price)  
    Expanded Driveway (single car width entry) ($1,260 cost included in contract price)  
    Eggshell Finish Paint ($1,050 cost included in contract price)  
    Upgraded LVT upstairs Bathrooms  
    Level III Granite Salinas White in Kitchen  
    Level III Granite Salinas White in Up Baths  
    Amendment to increase price by $2,180  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  06.17.2024    
-- -- $2500 Deposit Received (0)  06.19.2024    
-- -- Association Packet Requested (0)  06.17.2024    
-- -- Association Packet Received (0)  06.21.2024    
-- -- Selections Meeting (0)  07.10.2024    
-- -- Selections Sheet Signed (0)  07.20.2024     7/10: sent to Brandon for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  07.25.2024    
-- -- Deposit For Upgrades Received (0)  07.25.2024    
-- -- Building Permit (30) *   04.18.2024    
-- -- Order Roof & Floor Trusses (1)  08.22.2024    
-- -- Order Windows & Doors (0)  09.15.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.22.2024    
-- -- Inspection (Concrete Wall) (1)  05.13.2024    
-- -- Pour Footers (1) *   04.25.2024    
-- -- Set Forms (2)  05.13.2024    
-- -- Pour Foundation Walls (1)  05.13.2024    
-- -- Plumb Slab (2)  05.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  07.08.2024    
-- -- Inspection (Conduit Under Slab) (1)  07.08.2024    
-- -- Prepare Slab (1)  07.08.2024    
-- -- Inspection (Slab) (1)  07.08.2024    
-- -- Inspection (Drain Tile) (0)  07.08.2024    
-- -- Pour Slab (1) *   07.08.2024    
-- -- Settlement Agent Confirmed (0)  07.28.2024     Sent 7/25/2024
-- -- Framing I (9)  08.22.2024    
-- -- Order Steps (0)  09.15.2024    
-- -- Order Tubs / Showers (0)  09.15.2024    
-- -- Framing II (8)  08.22.2024    
-- -- Framing III (8) *   09.12.2024    
-- -- Verify Window & Roof Structure (0)  09.15.2024    
-- -- Install Stairs (0) *   09.18.2024    
-- -- Windows & Doors (0) *   10.03.2024    
-- -- House Number and Status in Window (0)  10.03.2024    
-- -- Roofing (0) *   10.12.2024    
-- -- Order Cabinets (0)  09.08.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  12.04.2024    
-- -- Gutters (0)  11.30.2024    
-- -- Driveway (0) *   12.14.2024     Framed
-- -- Patio (0)  12.21.2024     Framed
-- -- Privacy Divider / Fence (0) *   12.14.2024    
-- -- Sod / Seed / Landscaping (0)  03.15.2025    
-- -- HVAC Rough In (4)  09.28.2024     In process 9/21
-- -- Rough In Microwave Vent (0)  09.28.2024    
-- -- Plumbing Rough In (4)  09.28.2024    
-- -- Electric Rough In (4)  10.05.2024    
-- -- Inspection (Rough In HVAC) (1)  10.12.2024    
-- -- Inspection (Rough In Plumbing) (1)  10.12.2024    
-- -- Inspection (Rough In Electric) (1)  10.12.2024    
-- -- Inspection (Framing) (1) *   10.12.2024    
-- -- Inspection (Deck Piers) (0)  11.25.2024    
-- -- Exterior Vinyl (0) *   11.20.2024     In process 11/16
-- -- Exterior Stone (0)  12.07.2024    
-- -- Insulation (2) *   10.12.2024    
-- -- Inspection (Insulation) (1)  10.23.2024    
-- -- Inspection (Electric Service) (0)  11.25.2024    
-- -- Set Electric Meter (0) *   12.12.2024    
-- -- Inspection (Main Sewer Line) (0)  10.14.2024    
-- -- Inspection (Main Water Line) (0)  10.14.2024    
-- -- Order Interior Doors & Trim (0)  10.14.2024    
-- -- Drywall (Hang) (4) *   10.23.2024     Stocked 10/19
-- -- Loan Approval (0)  11.05.2024     Cash, 1031 Exchange
-- -- Deed Preparation (0)  11.05.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   11.06.2024     In process 10/26
-- -- Paint 1 (1)  11.06.2024    
-- -- Garage Door (0)  11.25.2024    
-- -- House Numbers (0)  12.30.2024    
-- -- Mailbox (0)  12.19.2024    
-- -- Cabinet Installation (2) *   11.09.2024     Installed Nov 8
-- -- Granite Installation (1) *   11.16.2024    
-- -- Interior Trim - Install (3) *   11.20.2024     In process 11/16
-- -- Order Plumbing / Lighting Fixtures (0)  12.02.2024    
-- -- Interior Trim - Paint (1)  11.30.2024    
-- -- Luxury Vinyl Plank (3) *   12.14.2024    
-- -- Luxury Vinyl Tile (0)  12.14.2024    
-- -- Paint 2 (3)  12.21.2024    
-- -- Cover Floors (0)  12.21.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.25.2024    
-- -- Shoe Moulding (0)  12.21.2024     In process 12/18
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   01.05.2025     In process 12/21
-- -- Install Coded Lockbox (add extra keys) (0)  01.06.2025    
-- -- Pay Water / Sewer Taps (0)  12.16.2024    
-- -- Set Water Meter (1) *   12.16.2024    
-- -- Electric Trim Out (3) *   12.30.2024     In process 12/21
-- -- Ceiling Fans (0)  12.28.2024    
-- -- HVAC Trim Out (1) *   12.30.2024     In process 12/21
-- -- Blower Door Test (1)  12.30.2024    
-- -- Plumbing Trim Out (2) *   12.21.2024     In process 12/18
-- -- Install Appliances (0) *   12.28.2024     In process 12/21
-- -- Paint 3 (2) *   01.05.2025    
-- -- Carpet (2)  12.21.2024    
-- -- Appraiser Confirms Construction Completion (0)  12.30.2024    
-- -- Inspection (Final HVAC) (0)  12.30.2024    
-- -- Inspection (Final Plumbing) (0)  12.30.2024    
-- -- Inspection (Final Electric) (0)  12.30.2024    
-- -- Inspection (Final Building) (4) *   12.30.2024    
-- -- Pre Walk Through (0)  01.13.2025     Thu, Jan 9
-- -- Stain Hardwood Stairs (1) *   01.11.2025     In process 1/8. Almost completed
-- -- Cleaning (1)  01.11.2025    
-- -- Certificate of Occupancy (1) *   01.09.2025    
-- -- C.O. to Lender (0)  01.13.2025    
-- -- Schedule Closing (0)  01.13.2025    
-- -- Buyer Walk Through (1) *   01.15.2025     Mon, Jan 13 at 11:30 AM
-- -- Payment for Upgrades (0)  12.30.2024    
-- -- Keys to Settlement Agent (0)  01.09.2025    
-- -- Review Settlement Statement (0)  01.13.2025    
-- -- Jerry Signs Closing Documents (0)  01.13.2025    
-- -- Request Trash Tote From POA Manager (0)  01.13.2025    
-- -- Closing (1)  01.15.2025     Brittany @ West View Title, Jan 14
-- -- Remove Coded Lockbox (0)  03.03.2025