| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Driveway - could be expanded but with single width entry | ||||
| Vinyl Plank in Upstairs Hallway and Bedroom ($2,900 cost included in contract price) | ||||
| Stained Hardwood Treads to Bedroom Level ($1,890 cost included in contract price) | ||||
| Expanded Driveway (single car width entry) ($1,260 cost included in contract price) | ||||
| Eggshell Finish Paint ($1,050 cost included in contract price) | ||||
| Upgraded LVT upstairs Bathrooms | ||||
| Level III Granite Salinas White in Kitchen | ||||
| Level III Granite Salinas White in Up Baths | ||||
| Amendment to increase price by $2,180 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 04.22.2024 | ||
| -- | -- | Inspection (Concrete Wall) (1) 05.13.2024 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 07.08.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 07.08.2024 | ||
| -- | -- | Inspection (Slab) (1) 07.08.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 07.08.2024 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 10.12.2024 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 10.12.2024 | ||
| -- | -- | Inspection (Rough In Electric) (1) 10.12.2024 | ||
| -- | -- | Inspection (Framing) (1) * 10.12.2024 | ||
| -- | -- | Inspection (Deck Piers) (0) 11.25.2024 | ||
| -- | -- | Inspection (Insulation) (1) 10.23.2024 | ||
| -- | -- | Inspection (Electric Service) (0) 11.25.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 10.14.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 10.14.2024 | ||
| -- | -- | Inspection (Final HVAC) (0) 12.30.2024 | ||
| -- | -- | Inspection (Final Plumbing) (0) 12.30.2024 | ||
| -- | -- | Inspection (Final Electric) (0) 12.30.2024 | ||
| -- | -- | Inspection (Final Building) (4) * 12.30.2024 | ||