1820 1 2 ADDR
TUSCAN - 2  ::  507 Via Rome
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Jul 1      Building Permit (30)      
Tue    Aug 12      Order Roof & Floor Trusses (1)      
Wed    Aug 13      Order Windows & Doors (0)      
Wed    Aug 13      Stake Out Home (1)      
Thu    Aug 14      Excavate (2)      
Mon    Aug 18      Inspection (Footers) (1)      
Tue    Aug 19      Inspection (Concrete Wall) (1)      
Wed    Aug 20      Pour Footers (1) *       
Thu    Aug 21      Set Forms (2)      
Mon    Aug 25      Pour Foundation Walls (1)      
Tue    Aug 26      Plumb Slab (2)      
Thu    Aug 28      Inspection (Plumbing Under Slab) (1)      
Fri    Aug 29      Inspection (Conduit Under Slab) (1)      
Mon    Sep 1      Prepare Slab (1)      
Tue    Sep 2      Inspection (Slab) (1)      
Wed    Sep 3      Inspection (Drain Tile) (0)      
Wed    Sep 3      Pour Slab (1) *       
Thu    Sep 4      Settlement Agent Confirmed (0)      
Thu    Sep 4      Framing I (9)      
Wed    Sep 17      Order Steps (0)      
Wed    Sep 17      Order Tubs / Showers (0)      
Wed    Sep 17      Framing II (8)      
Mon    Sep 29      Framing III (8) *       
Thu    Oct 9      Verify Window & Roof Structure (0)      
Thu    Oct 9      Install Stairs (0)      
Thu    Oct 9      Windows & Doors (0) *       
Thu    Oct 9      House Number and Status in Window (0)      
Thu    Oct 9      Roofing (0) *       
Thu    Oct 9      Order Cabinets (0)      
Thu    Oct 9      Order Appliances (0)      
Thu    Oct 9      Deck (0)      
Thu    Oct 9      Gutters (0)      
Thu    Oct 9      Driveway (0) *       
Thu    Oct 9      Patio (0)      
Thu    Oct 9      Privacy Divider / Fence (0)      
Thu    Oct 9      Sod / Seed / Landscaping (0)      
Thu    Oct 9      HVAC Rough In (4)      
Wed    Oct 15      Inspection (Rough In HVAC) (1)      
Thu    Oct 16      Rough In Microwave Vent (0)      
Thu    Oct 16      Plumbing Rough In (4)      
Wed    Oct 22      Inspection (Rough In Plumbing) (1)      
Thu    Oct 23      Electric Rough In (4)      
Wed    Oct 29      Inspection (Rough In Electric) (1)      
Thu    Oct 30      Inspection (Deck Piers) (0)      
Thu    Oct 30      Inspection (Framing) (1) *       
Fri    Oct 31      Exterior Vinyl (0) *       
Fri    Oct 31      Exterior Stone (0)      
Fri    Oct 31      Insulation (2) *       
Tue    Nov 4      Inspection (Insulation) (1)      
Wed    Nov 5      Inspection (Electric Service) (0)      
Wed    Nov 5      Set Electric Meter (0) *       
Wed    Nov 5      Inspection (Main Sewer Line) (0)      
Wed    Nov 5      Inspection (Main Water Line) (0)      
Wed    Nov 5      Order Interior Doors & Trim (0)      
Wed    Nov 5      Drywall (Hang) (4) *       
Tue    Nov 11      Loan Approval (0)      
Tue    Nov 11      Deed Preparation (0)      
Tue    Nov 11      Drywall (Tape, Block, Skim, Sand) (6) *       
Wed    Nov 19      Paint 1 (1)      
Thu    Nov 20      Garage Door (0) *       
Thu    Nov 20      House Numbers (0)      
Thu    Nov 20      Mailbox (0)      
Thu    Nov 20      Cabinet Installation (2) *       
Mon    Nov 24      Granite Installation (1) *       
Tue    Nov 25      Interior Trim - Install (3) *       
Fri    Nov 28      Order Plumbing / Lighting Fixtures (0)      
Fri    Nov 28      Interior Trim - Paint (1)      
Mon    Dec 1      Luxury Vinyl Plank (3) *       
Thu    Dec 4      Luxury Vinyl Tile (0)      
Thu    Dec 4      Paint 2 (3)      
Tue    Dec 9      Cover Floors (1)      
Wed    Dec 10      Deliver Plumbing / Lighting Fixtures (0)      
Wed    Dec 10      Shoe Moulding (0)      
Wed    Dec 10      Shelving, Door Knobs, Fire Extinguisher (0) *       
Wed    Dec 10      Install Coded Lockbox (add extra keys) (0)      
Wed    Dec 10      Pay Water / Sewer Taps (0)      
Wed    Dec 10      Set Water Meter (0) *       
Wed    Dec 10      Electric Trim Out (3)      
Mon    Dec 15      Ceiling Fans (0)      
Mon    Dec 15      HVAC Trim Out (1)      
Tue    Dec 16      Blower Door Test (1)      
Wed    Dec 17      Plumbing Trim Out (2)      
Fri    Dec 19      Install Appliances (0) *       
Fri    Dec 19      Paint 3 (2) *       
Tue    Dec 23      Carpet (2)      
Thu    Dec 25      Appraiser Confirms Construction Completion (0)      
Thu    Dec 25      Inspection (Final HVAC) (1)      
Fri    Dec 26      Inspection (Final Plumbing) (1)      
Mon    Dec 29      Inspection (Final Electric) (1)      
Tue    Dec 30      Inspection (Final Building) (2) *       
Thu    Jan 1      Pre Walk Through (0)      
Thu    Jan 1      Stain Hardwood Stairs (1)      
Fri    Jan 2      Cleaning (1)      
Mon    Jan 5      Certificate of Occupancy (1) *       
Tue    Jan 6      C.O. to Lender (0)      
Tue    Jan 6      Schedule Closing (0)      
Tue    Jan 6      Buyer Walk Through (1)      
Wed    Jan 7      Payment for Upgrades (0)      
Wed    Jan 7      Keys to Settlement Agent (0)      
Wed    Jan 7      Review Settlement Statement (0)      
Wed    Jan 7      Jerry Signs Closing Documents (0)      
Wed    Jan 7      Request Trash Tote From POA Manager (0)      
Wed    Jan 7      Closing (1)      
Thu    Jan 8      Remove Coded Lockbox (0)      
-- -- Ratified Contract? (0)  05.12.2025    
-- -- $2500 Deposit Received (0)  05.12.2025    
-- -- Association Packet Requested (0)  05.12.2025    
-- -- Association Packet Received (0)  05.12.2025    
-- -- Selections Meeting (0)  05.12.2025    
-- -- Selections Sheet Signed (0)  05.12.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.12.2025    
-- -- Deposit For Upgrades Received (0)  05.12.2025