1820 1 2 ADDR
TUSCAN - 2  ::  507 Via Rome
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Jul 1      Inspection (Footers) (1)      
Wed    Jul 2      Inspection (Concrete Wall) (1)      
Thu    Jul 3      Inspection (Plumbing Under Slab) (1)      
Fri    Jul 4      Inspection (Conduit Under Slab) (1)      
Mon    Jul 7      Inspection (Slab) (1)      
Tue    Jul 8      Inspection (Drain Tile) (0)      
Tue    Jul 8      Inspection (Rough In HVAC) (1)      
Wed    Jul 9      Inspection (Rough In Plumbing) (1)      
Thu    Jul 10      Inspection (Rough In Electric) (1)      
Fri    Jul 11      Inspection (Deck Piers) (0)      
Fri    Jul 11      Inspection (Framing) (1) *       
Mon    Jul 14      Inspection (Insulation) (1)      
Tue    Jul 15      Inspection (Electric Service) (0)      
Tue    Jul 15      Inspection (Main Sewer Line) (0)      
Tue    Jul 15      Inspection (Main Water Line) (0)      
Tue    Jul 15      Inspection (Final HVAC) (1)      
Wed    Jul 16      Inspection (Final Plumbing) (1)      
Thu    Jul 17      Inspection (Final Electric) (1)      
Fri    Jul 18      Inspection (Final Building) (2) *