TUSCAN - 1  ::  501 Via Rome
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Sunday (Apr 27)    show all photos
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Building Permit (30)      
Tue    Jun 10      Order Roof & Floor Trusses (1)      
Wed    Jun 11      Order Windows & Doors (0)      
Wed    Jun 11      Stake Out Home (1)      
Thu    Jun 12      Excavate (2)      
Mon    Jun 16      Inspection (Footers) (1)      
Tue    Jun 17      Inspection (Concrete Wall) (1)      
Wed    Jun 18      Pour Footers (1) *       
Thu    Jun 19      Set Forms (2)      
Mon    Jun 23      Pour Foundation Walls (1)      
Tue    Jun 24      Plumb Slab (2)      
Thu    Jun 26      Inspection (Plumbing Under Slab) (1)      
Fri    Jun 27      Inspection (Conduit Under Slab) (1)      
Mon    Jun 30      Prepare Slab (1)      
Tue    Jul 1      Inspection (Slab) (1)      
Wed    Jul 2      Inspection (Drain Tile) (0)      
Wed    Jul 2      Pour Slab (1) *       
Thu    Jul 3      Settlement Agent Confirmed (0)      
Thu    Jul 3      Framing I (9)      
Wed    Jul 16      Order Steps (0)      
Wed    Jul 16      Order Tubs / Showers (0)      
Wed    Jul 16      Framing II (8)      
Mon    Jul 28      Framing III (8) *       
Thu    Aug 7      Verify Window & Roof Structure (0)      
Thu    Aug 7      Install Stairs (0)      
Thu    Aug 7      Windows & Doors (0) *       
Thu    Aug 7      House Number and Status in Window (0)      
Thu    Aug 7      Roofing (0) *       
Thu    Aug 7      Order Cabinets (0)      
Thu    Aug 7      Order Appliances (0)      
Thu    Aug 7      Deck (0)      
Thu    Aug 7      Gutters (0)      
Thu    Aug 7      Driveway (0) *       
Thu    Aug 7      Patio (0)      
Thu    Aug 7      Privacy Divider / Fence (0)      
Thu    Aug 7      Sod / Seed / Landscaping (0)      
Thu    Aug 7      HVAC Rough In (4)      
Wed    Aug 13      Inspection (Rough In HVAC) (1)      
Thu    Aug 14      Rough In Microwave Vent (0)      
Thu    Aug 14      Plumbing Rough In (4)      
Wed    Aug 20      Inspection (Rough In Plumbing) (1)      
Thu    Aug 21      Electric Rough In (4)      
Wed    Aug 27      Inspection (Rough In Electric) (1)      
Thu    Aug 28      Inspection (Deck Piers) (0)      
Thu    Aug 28      Inspection (Framing) (1) *       
Fri    Aug 29      Exterior Vinyl (0) *       
Fri    Aug 29      Exterior Stone (0)      
Fri    Aug 29      Insulation (2) *       
Tue    Sep 2      Inspection (Insulation) (1)      
Wed    Sep 3      Inspection (Electric Service) (0)      
Wed    Sep 3      Set Electric Meter (0) *       
Wed    Sep 3      Inspection (Main Sewer Line) (0)      
Wed    Sep 3      Inspection (Main Water Line) (0)      
Wed    Sep 3      Order Interior Doors & Trim (0)      
Wed    Sep 3      Drywall (Hang) (4) *       
Tue    Sep 9      Loan Approval (0)      
Tue    Sep 9      Deed Preparation (0)      
Tue    Sep 9      Drywall (Tape, Block, Skim, Sand) (6) *       
Wed    Sep 17      Paint 1 (1)      
Thu    Sep 18      Garage Door (0) *       
Thu    Sep 18      House Numbers (0)      
Thu    Sep 18      Mailbox (0)      
Thu    Sep 18      Cabinet Installation (2) *       
Mon    Sep 22      Granite Installation (1) *       
Tue    Sep 23      Interior Trim - Install (3) *       
Fri    Sep 26      Order Plumbing / Lighting Fixtures (0)      
Fri    Sep 26      Interior Trim - Paint (1)      
Mon    Sep 29      Luxury Vinyl Plank (3) *       
Thu    Oct 2      Luxury Vinyl Tile (0)      
Thu    Oct 2      Paint 2 (3)      
Tue    Oct 7      Cover Floors (1)      
Wed    Oct 8      Deliver Plumbing / Lighting Fixtures (0)      
Wed    Oct 8      Shoe Moulding (0)      
Wed    Oct 8      Shelving, Door Knobs, Fire Extinguisher (0) *       
Wed    Oct 8      Install Coded Lockbox (add extra keys) (0)      
Wed    Oct 8      Pay Water / Sewer Taps (0)      
Wed    Oct 8      Set Water Meter (0) *       
Wed    Oct 8      Electric Trim Out (3)      
Mon    Oct 13      Ceiling Fans (0)      
Mon    Oct 13      HVAC Trim Out (1)      
Tue    Oct 14      Blower Door Test (1)      
Wed    Oct 15      Plumbing Trim Out (2)      
Fri    Oct 17      Install Appliances (0) *       
Fri    Oct 17      Paint 3 (2) *       
Tue    Oct 21      Carpet (2)      
Thu    Oct 23      Appraiser Confirms Construction Completion (0)      
Thu    Oct 23      Inspection (Final HVAC) (1)      
Fri    Oct 24      Inspection (Final Plumbing) (1)      
Mon    Oct 27      Inspection (Final Electric) (1)      
Tue    Oct 28      Inspection (Final Building) (2) *       
Thu    Oct 30      Pre Walk Through (0)      
Thu    Oct 30      Stain Hardwood Stairs (1)      
Fri    Oct 31      Cleaning (1)      
Mon    Nov 3      Certificate of Occupancy (1) *       
Tue    Nov 4      C.O. to Lender (0)      
Tue    Nov 4      Schedule Closing (0)      
Tue    Nov 4      Buyer Walk Through (1)      
Wed    Nov 5      Payment for Upgrades (0)      
Wed    Nov 5      Keys to Settlement Agent (0)      
Wed    Nov 5      Review Settlement Statement (0)      
Wed    Nov 5      Jerry Signs Closing Documents (0)      
Wed    Nov 5      Request Trash Tote From POA Manager (0)      
Wed    Nov 5      Closing (1)      
Thu    Nov 6      Remove Coded Lockbox (0)