VILLAS - 501-101  ::  501 Roman Way #101
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Saturday (Jan 31)    show all photos
TO DO
---
UPGRADES
---
CRITICAL PATH
    Deck (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Sod / Seed / Landscaping (0)      
Tue    Feb 3      Inspection (Framing) (1) *       
Wed    Feb 4      Insulation (2) *       
Fri    Feb 6      Inspection (Insulation) (1)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Mon    Feb 9      Drywall (Hang) (4) *       
Fri    Feb 13      Drywall (Tape, Block, Skim, Sand) (6) *       
Mon    Feb 23      Paint 1 (1)      
    House Numbers (0)      
    Mailbox (0)      
Tue    Feb 24      Cabinet Installation (2) *       
Thu    Feb 26      Granite Installation (1) *       
Fri    Feb 27      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Wed    Mar 4      Interior Trim - Paint (1)      
Thu    Mar 5      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Tue    Mar 10      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Fri    Mar 13      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Mon    Mar 16      Set Water Meter (1) *       
Tue    Mar 17      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Fri    Mar 20      HVAC Trim Out (1) *       
Mon    Mar 23      Blower Door Test (1)      
Tue    Mar 24      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Thu    Mar 26      Paint 3 (2) *       
Mon    Mar 30      Carpet (2)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Wed    Apr 1      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Tue    Apr 7      Stain Hardwood Stairs (1) *       
Wed    Apr 8      Cleaning (1)      
Thu    Apr 9      Certificate of Occupancy (1) *       
    Keys to Settlement Agent (0)      
    Request Trash Tote From POA Manager (0)      
Fri    Apr 10      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
Mud in Wilcher parking lot
Plan for mowing?
Internet plan Tom to talk to Danny Beam
ADA shower plan?
Foyer flooring plan
Set bathtub
Construction parking Remind subs not to park at 1820 CCR
Water Metering Confirm plan with third party company
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  05.12.2025    
-- -- $2500 Deposit Received (0)  05.12.2025    
-- -- Association Packet Requested (0)  05.12.2025    
-- -- Association Packet Received (0)  05.12.2025    
-- -- Selections Meeting (0)  05.12.2025    
-- -- Selections Sheet Signed (0)  05.12.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.12.2025    
-- -- Deposit For Upgrades Received (0)  05.12.2025    
-- -- Building Permit (30) *   08.18.2025    
-- -- Order Roof & Floor Trusses (1)  08.28.2025    
-- -- Order Windows & Doors (0)  09.15.2025     Jill will ask Tom, Colby
-- -- Stake Out Home (1)  08.18.2025    
-- -- Excavate (2)  08.18.2025    
-- -- Inspection (Footers) (1)  08.18.2025    
-- -- Inspection (Concrete Wall) (1)  08.18.2025    
-- -- Pour Footers (1) *   08.18.2025    
-- -- Set Forms (2)  08.18.2025    
-- -- Pour Foundation Walls (1)  08.18.2025    
-- -- Plumb Slab (2)  08.18.2025    
-- -- Inspection (Plumbing Under Slab) (1)  08.28.2025    
-- -- Inspection (Conduit Under Slab) (1)  08.28.2025    
-- -- Prepare Slab (1)  08.18.2025    
-- -- Inspection (Slab) (1)  08.18.2025    
-- -- Inspection (Drain Tile) (0)  08.18.2025    
-- -- Pour Slab (1) *   08.18.2025    
-- -- Settlement Agent Confirmed (0)  08.28.2025    
-- -- Framing I (9)  08.18.2025    
-- -- Order Steps (0)  09.02.2025     Jill will ask Luke
-- -- Order Tubs / Showers (0)  09.22.2025     Jill will ask Tom
-- -- Framing II (8)  09.17.2025    
-- -- Framing III (8) *   09.17.2025    
-- -- Verify Window & Roof Structure (0)  08.28.2025    
-- -- Install Stairs (0) *   10.02.2025     in process 9/20
-- -- Windows & Doors (0) *   10.27.2025    
-- -- House Number and Status in Window (0)  08.28.2025    
-- -- Roofing (0) *   09.22.2025    
-- -- Order Cabinets (0)  10.16.2025    
-- -- Order Appliances (0)  10.27.2025    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- HVAC Rough In (4)  10.02.2025    
-- -- Rough In Microwave Vent (0)  10.09.2025    
-- -- Plumbing Rough In (4)  11.20.2025    
-- -- Electric Rough In (4)  01.11.2026     in process 12/3- almost completed
-- -- Inspection (Rough In HVAC) (1)  01.22.2026    
-- -- Inspection (Rough In Plumbing) (1)  02.02.2026    
-- -- Inspection (Rough In Electric) (1)  01.22.2026    
-- -- Inspection (Deck Piers) (0)  01.22.2026    
-- -- Exterior Vinyl (0) *   02.02.2026    
-- -- Exterior Stone (0)  02.02.2026    
-- -- Inspection (Electric Service) (0)  01.15.2026    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Garage Door (0)  09.25.2025    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025