Wed    Jul 1      Inspection (Final Building) (4) *       
Tue    Jul 7      Cleaning (1)      
Wed    Jul 8      Certificate of Occupancy (1) *       
TO DO - COMPLETED OR DELETED
Mud in Wilcher parking lot
Plan for mowing?
Internet plan Tom to talk to Danny Beam
ADA shower plan?
Foyer flooring plan
Set bathtub
Construction parking Remind subs not to park at 1820 CCR
Water Metering Confirm plan with third party company
CL Mar 21 (102) Missing handle on kitchen cabinet Drawer - Ask Fred Timeline
SR Apr 20 (72) Sink issue
LR Apr 30 (62) Are submeters installed? Power on? Internet on? Jace Musser is asking
SR May 7 (55) All appliances - May 18
CL May 27 (35) One outlet is missing a cover in the kitchen
CL May 31 (31) All mirrors needed
CL Jun 10 (21) Weatherstripping needed at front doors of all units
CL Jun 10 (21) It appears some type of fire alarm still remain remains to be installed in all of the units?
CL Jun 21 (10) Remove fire alarm orange plastic case?
CL Jun 21 (10) Caulk All of the countertop side splashes Bathrooms - all units. Jesus
CL Jun 24 (7) Fuel paint touchups marked with blue tape Few
CL Jun 24 (7) Light bulb missing in entry light fixture
CL Jun 29 (2) install screens
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  05.12.2025    
-- -- $2500 Deposit Received (0)  05.12.2025    
-- -- Association Packet Requested (0)  05.12.2025    
-- -- Association Packet Received (0)  05.12.2025    
-- -- Selections Meeting (0)  05.12.2025    
-- -- Selections Sheet Signed (0)  05.12.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.12.2025    
-- -- Deposit For Upgrades Received (0)  05.12.2025    
-- -- Building Permit (30) *   08.18.2025    
-- -- Order Roof & Floor Trusses (1)  08.28.2025    
-- -- Order Windows & Doors (0)  09.15.2025     Jill will ask Tom, Colby
-- -- Stake Out Home (1)  08.18.2025    
-- -- Excavate (2)  08.18.2025    
-- -- Inspection (Footers) (1)  08.18.2025    
-- -- Inspection (Concrete Wall) (1)  08.18.2025    
-- -- Pour Footers (1) *   08.18.2025    
-- -- Set Forms (2)  08.18.2025    
-- -- Pour Foundation Walls (1)  08.18.2025    
-- -- Plumb Slab (2)  08.18.2025    
-- -- Inspection (Plumbing Under Slab) (1)  08.28.2025    
-- -- Inspection (Conduit Under Slab) (1)  08.28.2025    
-- -- Prepare Slab (1)  08.18.2025    
-- -- Inspection (Slab) (1)  08.18.2025    
-- -- Inspection (Drain Tile) (0)  08.18.2025    
-- -- Pour Slab (1) *   08.18.2025    
-- -- Settlement Agent Confirmed (0)  08.28.2025    
-- -- Framing I (9)  08.18.2025    
-- -- Order Steps (0)  09.02.2025     Jill will ask Luke
-- -- Order Tubs / Showers (0)  09.22.2025     Jill will ask Tom
-- -- Framing II (8)  09.17.2025    
-- -- Framing III (8) *   09.17.2025    
-- -- Verify Window & Roof Structure (0)  08.28.2025    
-- -- Install Stairs (0) *   10.02.2025     in process 9/20
-- -- Windows & Doors (0) *   10.27.2025    
-- -- House Number and Status in Window (0)  08.28.2025    
-- -- Roofing (0) *   09.22.2025    
-- -- Order Cabinets (0)  10.16.2025    
-- -- Order Appliances (0)  10.27.2025    
-- -- Deck (0)  03.23.2026    
-- -- Gutters (0)  03.23.2026    
-- -- Driveway (0) *   02.19.2026    
-- -- Patio (0)  05.13.2026    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- Sod / Seed / Landscaping (0)  06.12.2026    
-- -- HVAC Rough In (4)  10.02.2025    
-- -- Rough In Microwave Vent (0)  10.09.2025    
-- -- Plumbing Rough In (4)  11.20.2025    
-- -- Electric Rough In (4)  01.11.2026     in process 12/3- almost completed
-- -- Inspection (Rough In HVAC) (1)  01.22.2026    
-- -- Inspection (Rough In Plumbing) (1)  02.02.2026    
-- -- Inspection (Rough In Electric) (1)  01.22.2026    
-- -- Inspection (Framing) (1) *   02.19.2026    
-- -- Inspection (Deck Piers) (0)  01.22.2026    
-- -- Exterior Vinyl (0) *   02.02.2026    
-- -- Exterior Stone (0)  02.02.2026    
-- -- Insulation (2) *   02.19.2026    
-- -- Inspection (Insulation) (1)  02.19.2026    
-- -- Inspection (Electric Service) (0)  01.15.2026    
-- -- Set Electric Meter (0) *   04.06.2026    
-- -- Inspection (Main Sewer Line) (0)  06.11.2026    
-- -- Inspection (Main Water Line) (0)  04.14.2026    
-- -- Order Interior Doors & Trim (0)  03.30.2026    
-- -- Drywall (Hang) (4) *   03.05.2026    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   03.16.2026     In process 3/7
-- -- Paint 1 (1)  03.16.2026    
-- -- Garage Door (0)  09.25.2025    
-- -- House Numbers (0)  05.27.2026    
-- -- Mailbox (0)  06.01.2026    
-- -- Cabinet Installation (2) *   03.23.2026    
-- -- Granite Installation (1) *   04.23.2026     Apr 20 - all six apartments
-- -- Interior Trim - Install (3) *   04.06.2026    
-- -- Order Plumbing / Lighting Fixtures (0)  04.09.2026    
-- -- Interior Trim - Paint (1)  04.09.2026    
-- -- Luxury Vinyl Plank (3) *   04.13.2026    
-- -- Luxury Vinyl Tile (0)  04.13.2026    
-- -- Paint 2 (3)  05.13.2026    
-- -- Cover Floors (0)  05.27.2026    
-- -- Deliver Plumbing / Lighting Fixtures (0)  05.07.2026    
-- -- Shoe Moulding (0)  05.06.2026    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   05.27.2026     Needs bathroom accessories & front door lock
-- -- Install Coded Lockbox (add extra keys) (0)  06.03.2026    
-- -- Pay Water / Sewer Taps (0)  06.11.2026    
-- -- Set Water Meter (1) *   06.15.2026    
-- -- Electric Trim Out (3) *   05.27.2026    
-- -- Ceiling Fans (0)  06.03.2026    
-- -- HVAC Trim Out (1) *   05.14.2026    
-- -- Blower Door Test (1)  06.25.2026    
-- -- Plumbing Trim Out (2) *   05.02.2026     In process 4/25
-- -- Install Appliances (0) *   06.21.2026     All but stove 6/3
-- -- Paint 3 (2) *   06.21.2026     In process, ceiling needs to be painted
-- -- Carpet (2)  05.18.2026    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- Inspection (Final HVAC) (0)  06.25.2026    
-- -- Inspection (Final Plumbing) (0)  06.25.2026    
-- -- Inspection (Final Electric) (0)  06.25.2026    
-- -- Pre Walk Through (0)  06.25.2026    
-- -- Stain Hardwood Stairs (1) *   06.04.2026    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Keys to Settlement Agent (0)  06.25.2026    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025    
-- -- Request Trash Tote From POA Manager (0)  06.25.2026    
-- -- Closing (1)  06.25.2026    
-- -- Remove Coded Lockbox (0)  06.25.2026