VILLAS - 501-101  ::  501 Roman Way #101
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (Dec 17)    show all photos
Thu    Dec 18      Deck (0)      
Thu    Dec 18      Gutters (0)      
Thu    Dec 18      Driveway (0) *       
Thu    Dec 18      Patio (0)      
Thu    Dec 18      Sod / Seed / Landscaping (0)      
Thu    Dec 18      Electric Rough In (4)       in process 12/3- almost completed
Wed    Dec 24      Inspection (Rough In HVAC) (1)      
Thu    Dec 25      Inspection (Rough In Plumbing) (1)      
Fri    Dec 26      Inspection (Rough In Electric) (1)      
Mon    Dec 29      Inspection (Framing) (1) *       
Tue    Dec 30      Inspection (Deck Piers) (0)      
Tue    Dec 30      Exterior Vinyl (0) *       
Tue    Dec 30      Exterior Stone (0)      
Tue    Dec 30      Insulation (2) *       
Thu    Jan 1      Inspection (Insulation) (1)      
Fri    Jan 2      Inspection (Electric Service) (0)      
Fri    Jan 2      Set Electric Meter (0) *       
Fri    Jan 2      Inspection (Main Sewer Line) (0)      
Fri    Jan 2      Inspection (Main Water Line) (0)      
Fri    Jan 2      Order Interior Doors & Trim (0)      
Fri    Jan 2      Drywall (Hang) (4) *       
Thu    Jan 8      Drywall (Tape, Block, Skim, Sand) (6) *       
Fri    Jan 16      Paint 1 (1)      
Mon    Jan 19      House Numbers (0)      
Mon    Jan 19      Mailbox (0)      
Mon    Jan 19      Cabinet Installation (2) *       
Wed    Jan 21      Granite Installation (1) *       
Thu    Jan 22      Interior Trim - Install (3) *       
Tue    Jan 27      Order Plumbing / Lighting Fixtures (0)      
Tue    Jan 27      Interior Trim - Paint (1)      
Wed    Jan 28      Luxury Vinyl Plank (3) *       
Mon    Feb 2      Luxury Vinyl Tile (0)      
Mon    Feb 2      Paint 2 (3)      
Thu    Feb 5      Cover Floors (1)      
Fri    Feb 6      Deliver Plumbing / Lighting Fixtures (0)      
Fri    Feb 6      Shoe Moulding (0)      
Fri    Feb 6      Shelving, Door Knobs, Fire Extinguisher (0) *       
Fri    Feb 6      Install Coded Lockbox (add extra keys) (0)      
Fri    Feb 6      Pay Water / Sewer Taps (0)      
Fri    Feb 6      Set Water Meter (0) *       
Fri    Feb 6      Electric Trim Out (3) *       
Wed    Feb 11      Ceiling Fans (0)      
Wed    Feb 11      HVAC Trim Out (1) *       
Thu    Feb 12      Blower Door Test (1)      
Fri    Feb 13      Plumbing Trim Out (2) *       
Tue    Feb 17      Install Appliances (0) *       
Tue    Feb 17      Paint 3 (2) *       
Thu    Feb 19      Carpet (2)      
Mon    Feb 23      Inspection (Final HVAC) (1)      
Tue    Feb 24      Inspection (Final Plumbing) (1)      
Wed    Feb 25      Inspection (Final Electric) (1)      
Thu    Feb 26      Inspection (Final Building) (2) *       
Mon    Mar 2      Pre Walk Through (0)      
Mon    Mar 2      Stain Hardwood Stairs (1) *       
Tue    Mar 3      Cleaning (1)      
Wed    Mar 4      Certificate of Occupancy (1) *       
Thu    Mar 5      Keys to Settlement Agent (0)      
Thu    Mar 5      Request Trash Tote From POA Manager (0)      
Thu    Mar 5      Closing (1)      
Fri    Mar 6      Remove Coded Lockbox (0)      
--   --   Mud in Wilcher parking lot
--   --   Plan for mowing?
--   --   Internet plan Tom to talk to Danny Beam
--   --   ADA shower plan?
--   --   Foyer flooring plan
--   --   Set bathtub
--   --   Construction parking Remind subs not to park at 1820 CCR
--   --   Water Metering Confirm plan with third party company
-- -- Ratified Contract? (0)  05.12.2025    
-- -- $2500 Deposit Received (0)  05.12.2025    
-- -- Association Packet Requested (0)  05.12.2025    
-- -- Association Packet Received (0)  05.12.2025    
-- -- Selections Meeting (0)  05.12.2025    
-- -- Selections Sheet Signed (0)  05.12.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.12.2025    
-- -- Deposit For Upgrades Received (0)  05.12.2025    
-- -- Building Permit (30) *   08.18.2025    
-- -- Order Roof & Floor Trusses (1)  08.28.2025    
-- -- Order Windows & Doors (0)  09.15.2025     Jill will ask Tom, Colby
-- -- Stake Out Home (1)  08.18.2025    
-- -- Excavate (2)  08.18.2025    
-- -- Inspection (Footers) (1)  08.18.2025    
-- -- Inspection (Concrete Wall) (1)  08.18.2025    
-- -- Pour Footers (1) *   08.18.2025    
-- -- Set Forms (2)  08.18.2025    
-- -- Pour Foundation Walls (1)  08.18.2025    
-- -- Plumb Slab (2)  08.18.2025    
-- -- Inspection (Plumbing Under Slab) (1)  08.28.2025    
-- -- Inspection (Conduit Under Slab) (1)  08.28.2025    
-- -- Prepare Slab (1)  08.18.2025    
-- -- Inspection (Slab) (1)  08.18.2025    
-- -- Inspection (Drain Tile) (0)  08.18.2025    
-- -- Pour Slab (1) *   08.18.2025    
-- -- Settlement Agent Confirmed (0)  08.28.2025    
-- -- Framing I (9)  08.18.2025    
-- -- Order Steps (0)  09.02.2025     Jill will ask Luke
-- -- Order Tubs / Showers (0)  09.22.2025     Jill will ask Tom
-- -- Framing II (8)  09.17.2025    
-- -- Framing III (8) *   09.17.2025    
-- -- Verify Window & Roof Structure (0)  08.28.2025    
-- -- Install Stairs (0) *   10.02.2025     in process 9/20
-- -- Windows & Doors (0) *   10.27.2025    
-- -- House Number and Status in Window (0)  08.28.2025    
-- -- Roofing (0) *   09.22.2025    
-- -- Order Cabinets (0)  10.16.2025    
-- -- Order Appliances (0)  10.27.2025    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- HVAC Rough In (4)  10.02.2025    
-- -- Rough In Microwave Vent (0)  10.09.2025    
-- -- Plumbing Rough In (4)  11.20.2025    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Garage Door (0)  09.25.2025    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025