INTERIOR TRIM - INSTALL
hide completed
 
Lot       Buyer       Status    Projected    Notes   
000  
37 Luke Rogers & Scott Rogers 07/03/2025 In process 6/25
31 Jawad Ahmed & Zainab Ahmed 10/28/2025 In process 10/22
5 Ronnie & Sue Sours 02/11/2026 Doors and trim needed. Partially painted. 1/17
6 Ronnie & Sue Sours 02/06/2026 Doors and door trim needed. Partial paint8ng com0lete 1/24
7 Ronnie & Sue Sours 02/06/2026 Doors and door trim needed to complete 2/4
2 Ronnie & Sue Sours 02/23/2026 In process 2/14
3 Ronnie & Sue Sours 02/26/2026 In process 2/22
4 Fadi Majdoub 03/04/2026 In process 2/28