CONGERS-3 - 37  ::  1450 Derby Drive
[ BUILD: 20242192 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
Paint around window repairs
Fix, bonus room window On order
UPGRADES
---
CRITICAL PATH
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
Hoping to close by July 11
The top section of all the main level stairs is missing 37/26 only
Farm Sink arriving Thursday 5/22.
Termite treatement, documents
Are these houses getting a patio or a deck on lower level
Are these houses getting a patio or a deck on lower level
Spice rack is installed, but needs adjustments to open and close easily Fred
Door frame needs to be repaired in closet under stairs in foyer level Jesus
Sand and paint behind trim on inside of upstairs hallway bathroom door Jesus
Master vanity countertop needed
Privacy divider needed
I’m assuming all the patios are going to get steps to the backyard?
Cover quartz countertops
Clean off master marble countertop from previous installation Jill
Side splash Needed for master countertop Tom. I think matches correctly...thoughts?
Powder bath needs mirror installed Paul
Kitchen island needs electrical outlets Electrician
Make sure correct thermostat has been ordered as other thermostats are install installed in other units Tom to take it down from the trailer
Globe needed on light and foyer. Space In foyer, Electrician
HVAC vent at the top of the stairs needs to be installed
Install the shower walls
Install ceiling fan cover, an exterior front light Electrician
Is the lock supposed to be gold on the black keypad?
Gutters need to be reworked with the addition of the step to the patio
CODED LOCKBOX 3737
Not correct thermostat!
Shower door needed Mon, Aug 18
Repaint front door second coat Jesus
Install back patio screen
Remove extra mirror from bonus room closet Paul
Install ceiling fan in living room Electrician
Install cable cover Jill
Fix drywall in smaller bedroom Jesus
Sand down a bit on ceiling in master bedroom Jesus - tray ceiling
Caulk needed on side shower walls Jesus
Sand joint under stairs on first floor Jesus
Without drywall corners, Tracy ceiling primary bedroom
Major issues shower walls
Adjust primary ceiling fan control handler so the remote can go all the way down
Swap out bathroom top of water tank
Restain steps
Board to be attached y see patio door
Attach board under patio door
Adjust 9” spice drawer Fred
Secure show at island evenly and fill and paint nail holes
Scrape garage floor Jill
Remote control holder in primary bedroom needs to be adjusted so the remote can slide all the way down Buddy
Secure the shoe molding at the island fill and paint nail holes Luke will check
Fill and paint nail holes at shoe, all vanities Jill
Jesus to leave extra paint Luke will ask
Shelf needed for Upper cabinet to the right of the microwave Kate has ordered from Fred. Swapped with another shelf
Exterior of kitchen window chipped on the upper right corner On order
Power wash front and back Jill
Trim at front of farmhouse sink Fred
Scratch on front of refrigerator Door on order
Screens Jill
Replace shower panels New corner piece - Jason
Luke Rogers, 540-830-5097
Final paint touch up Bathroom wall, etc. - Jesus
Extra Paint Needed (Chantilly Lace & Interior Closet Color) Jesus
Test 3
SR Test 4
SR Dec 29 (36) Test 5
SR Dec 30 (35) Testing New To Do
LR Dec 31 (34) Extra Paint Needed (Chantilly Lace & Interior Closet Color)
UPGRADES - COMPLETED
    Credit towards upgrades per Jerry  
    Finished Bonus Room  
    Finished Bonus Bathroom  
    Expanded Driveway  
    White Upgraded Kitchen Cabinetry  
    White Upgraded Bathroom Cabinetry  
    Level 3 Quartz Kitchen Countertops  
    White Farmhouse Sink  
    French Model Refrigerator  
    Cabinet Crown Moulding  
    Double Pull Out Waste Basket in Island  
    2 Roll Out Trays in Lower 36"  
    Spice Rack in B9" cabinet  
    Microwave vented to exterior  
    White Subway Tile Shower Walls  
    Heavy Bi-Pass Shower Door with Black Trim  
    Stained Hardwood Treads to bedroom level  
    Additional Ceiling Fan in Living Room  
    Digital Deadbolt  
    EcoBee 3 Lite Smart WiFi enabled Thermostat  
    Garage Door Opener Keypad (no charge)  
    Amendment to increase price by $23,475  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  12.17.2024    
-- -- $2500 Deposit Received (0)  12.21.2024    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  12.20.2024    
-- -- Selections Meeting (0)  12.31.2024    
-- -- Selections Sheet Signed (0)  01.02.2025     1/1: sent to Luke for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  01.12.2025     1/11: sent to Jerry to sign
-- -- Deposit For Upgrades Received (0)  01.11.2025    
-- -- Building Permit (30) *   11.22.2024    
-- -- Order Roof & Floor Trusses (1)  02.20.2025    
-- -- Order Windows & Doors (0)  12.30.2024    
-- -- Stake Out Home (1)  12.02.2024    
-- -- Excavate (2)  12.02.2024    
-- -- Inspection (Footers) (1)  12.02.2024    
-- -- Inspection (Concrete Wall) (1)  12.02.2024    
-- -- Pour Footers (1) *   08.24.2025    
-- -- Set Forms (2)  12.19.2024    
-- -- Pour Foundation Walls (1)  12.19.2024    
-- -- Plumb Slab (2)  12.30.2024    
-- -- Inspection (Plumbing Under Slab) (1)  12.30.2024    
-- -- Inspection (Conduit Under Slab) (1)  12.30.2024    
-- -- Prepare Slab (1)  02.02.2025    
-- -- Inspection (Slab) (1)  02.20.2025    
-- -- Inspection (Drain Tile) (0)  06.09.2025    
-- -- Pour Slab (1) *   08.24.2025    
-- -- Settlement Agent Confirmed (0)  06.24.2025    
-- -- Framing I (9)  03.29.2025    
-- -- Order Steps (0)  04.03.2025    
-- -- Order Tubs / Showers (0)  04.07.2025    
-- -- Framing II (8)  03.29.2025    
-- -- Framing III (8) *   08.24.2025    
-- -- Verify Window & Roof Structure (0)  05.07.2025    
-- -- Install Stairs (0) *   05.07.2025    
-- -- Windows & Doors (0) *   08.24.2025    
-- -- House Number and Status in Window (0)  05.19.2025    
-- -- Roofing (0) *   08.24.2025    
-- -- Order Cabinets (0)  06.23.2025    
-- -- Order Appliances (0)  06.09.2025    
-- -- Deck (0)  06.15.2025     Standard
-- -- Gutters (0)  07.04.2025    
-- -- Driveway (0) *   08.24.2025    
-- -- Patio (0)  06.15.2025     Standard
-- -- Privacy Divider / Fence (0) *   08.24.2025    
-- -- Sod / Seed / Landscaping (0)  08.12.2025    
-- -- HVAC Rough In (4)  04.26.2025    
-- -- Rough In Microwave Vent (0)  04.26.2025     Vented to Exterior
-- -- Plumbing Rough In (4)  05.14.2025    
-- -- Electric Rough In (4)  05.21.2025    
-- -- Inspection (Rough In HVAC) (1)  05.21.2025    
-- -- Inspection (Rough In Plumbing) (1)  05.21.2025    
-- -- Inspection (Rough In Electric) (1)  05.21.2025    
-- -- Inspection (Framing) (1) *   08.24.2025    
-- -- Inspection (Deck Piers) (0)  06.24.2025    
-- -- Exterior Vinyl (0) *   08.24.2025    
-- -- Exterior Stone (0)  07.28.2025    
-- -- Insulation (2) *   08.24.2025    
-- -- Inspection (Insulation) (1)  05.22.2025    
-- -- Inspection (Electric Service) (0)  06.12.2025    
-- -- Set Electric Meter (0) *   08.24.2025    
-- -- Inspection (Main Sewer Line) (0)  06.09.2025    
-- -- Inspection (Main Water Line) (0)  06.09.2025    
-- -- Order Interior Doors & Trim (0)  06.24.2025    
-- -- Drywall (Hang) (4) *   08.24.2025    
-- -- Loan Approval (0)  08.15.2025     JoDee @ United Bank (80% LTV)
-- -- Deed Preparation (0)  06.24.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.24.2025     In process 6/4
-- -- Paint 1 (1)  06.15.2025    
-- -- Garage Door (0)  08.03.2025    
-- -- House Numbers (0)  07.14.2025    
-- -- Mailbox (0)  07.03.2025    
-- -- Cabinet Installation (2) *   08.24.2025     In process 6/18
-- -- Granite Installation (1) *   08.24.2025    
-- -- Interior Trim - Install (3) *   08.24.2025     In process 6/25
-- -- Order Plumbing / Lighting Fixtures (0)  06.12.2025    
-- -- Interior Trim - Paint (1)  07.02.2025    
-- -- Luxury Vinyl Plank (3) *   08.24.2025     In process 7/9
-- -- Luxury Vinyl Tile (0)  07.12.2025    
-- -- Paint 2 (3)  07.18.2025     In process 7/16
-- -- Cover Floors (0)  07.30.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  06.19.2025    
-- -- Shoe Moulding (0)  07.16.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   08.24.2025    
-- -- Install Coded Lockbox (add extra keys) (0)  08.13.2025    
-- -- Pay Water / Sewer Taps (0)  06.30.2025    
-- -- Set Water Meter (1) *   08.24.2025    
-- -- Electric Trim Out (3) *   08.03.2025     Ceiling fans and a few electrical outlet covers and smoke alarms needed. Powder bath needs light fixture as well.
-- -- Ceiling Fans (0)  08.21.2025     Still need ceiling fan in living room
-- -- HVAC Trim Out (1) *   08.24.2025     HVAC trimout is completed except thermostat
-- -- Blower Door Test (1)  08.15.2025    
-- -- Plumbing Trim Out (2) *   08.24.2025     Bonus bathroom vanity needs trimmed out. Primary shower and pedestal sink too.
-- -- Install Appliances (0) *   08.24.2025     French/ Current Date: 7/7. On site 6/27
-- -- Paint 3 (2) *   08.24.2025    
-- -- Carpet (2)  07.18.2025    
-- -- Appraiser Confirms Construction Completion (0)  08.19.2025    
-- -- Inspection (Final HVAC) (0)  08.15.2025     Scheduled for Friday 8/15
-- -- Inspection (Final Plumbing) (0)  08.15.2025    
-- -- Inspection (Final Electric) (0)  08.15.2025    
-- -- Inspection (Final Building) (4) *   08.24.2025    
-- -- Pre Walk Through (0)  08.18.2025    
-- -- Stain Hardwood Stairs (1) *   08.24.2025    
-- -- Cleaning (1)  08.20.2025     in process 8/16
-- -- Certificate of Occupancy (1) *   08.24.2025    
-- -- C.O. to Lender (0)  08.19.2025    
-- -- Schedule Closing (0)  08.19.2025    
-- -- Buyer Walk Through (1) *   08.24.2025    
-- -- Payment for Upgrades (0)  08.15.2025    
-- -- Keys to Settlement Agent (0)  08.15.2025    
-- -- Review Settlement Statement (0)  08.19.2025    
-- -- Jerry Signs Closing Documents (0)  08.20.2025    
-- -- Request Trash Tote From POA Manager (0)  12.30.2025    
-- -- Closing (1)  08.21.2025     Brittany @ West View Title