| TO DO |
|
|
Paint around window repairs |
|
|
|
|
Fix, bonus room window |
On order |
|
|
| UPGRADES |
| --- |
|
| CRITICAL PATH |
|
|
|
Remove Coded Lockbox (0) |
|
|
|
| TO DO - COMPLETED OR DELETED |
|
|
Hoping to close by July 11 |
|
|
|
|
The top section of all the main level stairs is missing |
37/26 only |
|
|
|
Farm Sink arriving Thursday 5/22. |
|
|
|
|
Termite treatement, documents |
|
|
|
|
Are these houses getting a patio or a deck on lower level |
|
|
|
|
Are these houses getting a patio or a deck on lower level |
|
|
|
|
Spice rack is installed, but needs adjustments to open and close easily |
Fred |
|
|
|
Door frame needs to be repaired in closet under stairs in foyer level |
Jesus |
|
|
|
Sand and paint behind trim on inside of upstairs hallway bathroom door |
Jesus |
|
|
|
Master vanity countertop needed |
|
|
|
|
Privacy divider needed |
|
|
|
|
I’m assuming all the patios are going to get steps to the backyard? |
|
|
|
|
Cover quartz countertops |
|
|
|
|
Clean off master marble countertop from previous installation |
Jill |
|
|
|
Side splash Needed for master countertop |
Tom. I think matches correctly...thoughts? |
|
|
|
Powder bath needs mirror installed |
Paul |
|
|
|
Kitchen island needs electrical outlets |
Electrician |
|
|
|
Make sure correct thermostat has been ordered as other thermostats are install installed in other units |
Tom to take it down from the trailer |
|
|
|
Globe needed on light and foyer. Space |
In foyer, Electrician |
|
|
|
HVAC vent at the top of the stairs needs to be installed |
|
|
|
|
Install the shower walls |
|
|
|
|
Install ceiling fan cover, an exterior front light |
Electrician |
|
|
|
Is the lock supposed to be gold on the black keypad? |
|
|
|
|
Gutters need to be reworked with the addition of the step to the patio |
|
|
|
|
CODED LOCKBOX 3737 |
|
|
|
|
Not correct thermostat! |
|
|
|
|
Shower door needed |
Mon, Aug 18 |
|
|
|
Repaint front door second coat |
Jesus |
|
|
|
Install back patio screen |
|
|
|
|
Remove extra mirror from bonus room closet |
Paul |
|
|
|
Install ceiling fan in living room |
Electrician |
|
|
|
Install cable cover |
Jill |
|
|
|
Fix drywall in smaller bedroom |
Jesus |
|
|
|
Sand down a bit on ceiling in master bedroom |
Jesus - tray ceiling |
|
|
|
Caulk needed on side shower walls |
Jesus |
|
|
|
Sand joint under stairs on first floor |
Jesus |
|
|
|
Without drywall corners, Tracy ceiling primary bedroom |
|
|
|
|
Major issues shower walls |
|
|
|
|
Adjust primary ceiling fan control handler so the remote can go all the way down |
|
|
|
|
Swap out bathroom top of water tank |
|
|
|
|
Restain steps |
|
|
|
|
Board to be attached y see patio door |
|
|
|
|
Attach board under patio door |
|
|
|
|
Adjust 9” spice drawer |
Fred |
|
|
|
Secure show at island evenly and fill and paint nail holes |
|
|
|
|
Scrape garage floor |
Jill |
|
|
|
Remote control holder in primary bedroom needs to be adjusted so the remote can slide all the way down |
Buddy |
|
|
|
Secure the shoe molding at the island fill and paint nail holes |
Luke will check |
|
|
|
Fill and paint nail holes at shoe, all vanities |
Jill |
|
|
|
Jesus to leave extra paint |
Luke will ask |
|
|
|
Shelf needed for Upper cabinet to the right of the microwave |
Kate has ordered from Fred. Swapped with another shelf |
|
|
|
Exterior of kitchen window chipped on the upper right corner |
On order |
|
|
|
Power wash front and back |
Jill |
|
|
|
Trim at front of farmhouse sink |
Fred |
|
|
|
Scratch on front of refrigerator |
Door on order |
|
|
|
Screens |
Jill |
|
|
|
Replace shower panels |
New corner piece - Jason |
|
|
|
Luke Rogers, 540-830-5097 |
|
|
|
|
Final paint touch up |
Bathroom wall, etc. - Jesus |
|
|
|
Extra Paint Needed (Chantilly Lace & Interior Closet Color) |
Jesus |
|
|
|
Test 3 |
|
|
| SR |
|
Test 4 |
|
|
| SR |
Dec 29 (36) |
Test 5 |
|
|
| SR |
Dec 30 (35) |
Testing New To Do |
|
|
| LR |
Dec 31 (34) |
Extra Paint Needed (Chantilly Lace & Interior Closet Color) |
|
|
|
| UPGRADES - COMPLETED |
| |
|
Credit towards upgrades per Jerry
|
|
| |
|
Finished Bonus Room
|
|
| |
|
Finished Bonus Bathroom
|
|
| |
|
Expanded Driveway
|
|
| |
|
White Upgraded Kitchen Cabinetry
|
|
| |
|
White Upgraded Bathroom Cabinetry
|
|
| |
|
Level 3 Quartz Kitchen Countertops
|
|
| |
|
White Farmhouse Sink
|
|
| |
|
French Model Refrigerator
|
|
| |
|
Cabinet Crown Moulding
|
|
| |
|
Double Pull Out Waste Basket in Island
|
|
| |
|
2 Roll Out Trays in Lower 36"
|
|
| |
|
Spice Rack in B9" cabinet
|
|
| |
|
Microwave vented to exterior
|
|
| |
|
White Subway Tile Shower Walls
|
|
| |
|
Heavy Bi-Pass Shower Door with Black Trim
|
|
| |
|
Stained Hardwood Treads to bedroom level
|
|
| |
|
Additional Ceiling Fan in Living Room
|
|
| |
|
Digital Deadbolt
|
|
| |
|
EcoBee 3 Lite Smart WiFi enabled Thermostat
|
|
| |
|
Garage Door Opener Keypad (no charge)
|
|
| |
|
Amendment to increase price by $23,475
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Ratified Contract? (0) 12.17.2024 |
|
|
| -- |
-- |
$2500 Deposit Received (0) 12.21.2024 |
|
|
| -- |
-- |
Association Packet Requested (0) 06.30.2025 |
|
|
| -- |
-- |
Association Packet Received (0) 12.20.2024 |
|
|
| -- |
-- |
Selections Meeting (0) 12.31.2024 |
|
|
| -- |
-- |
Selections Sheet Signed (0) 01.02.2025 |
1/1: sent to Luke for signatures |
|
| -- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 01.12.2025 |
1/11: sent to Jerry to sign |
|
| -- |
-- |
Deposit For Upgrades Received (0) 01.11.2025 |
|
|
| -- |
-- |
Building Permit (30) * 11.22.2024 |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) 02.20.2025 |
|
|
| -- |
-- |
Order Windows & Doors (0) 12.30.2024 |
|
|
| -- |
-- |
Stake Out Home (1) 12.02.2024 |
|
|
| -- |
-- |
Excavate (2) 12.02.2024 |
|
|
| -- |
-- |
Inspection (Footers) (1) 12.02.2024 |
|
|
| -- |
-- |
Inspection (Concrete Wall) (1) 12.02.2024 |
|
|
| -- |
-- |
Pour Footers (1) * 08.24.2025 |
|
|
| -- |
-- |
Set Forms (2) 12.19.2024 |
|
|
| -- |
-- |
Pour Foundation Walls (1) 12.19.2024 |
|
|
| -- |
-- |
Plumb Slab (2) 12.30.2024 |
|
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) 12.30.2024 |
|
|
| -- |
-- |
Inspection (Conduit Under Slab) (1) 12.30.2024 |
|
|
| -- |
-- |
Prepare Slab (1) 02.02.2025 |
|
|
| -- |
-- |
Inspection (Slab) (1) 02.20.2025 |
|
|
| -- |
-- |
Inspection (Drain Tile) (0) 06.09.2025 |
|
|
| -- |
-- |
Pour Slab (1) * 08.24.2025 |
|
|
| -- |
-- |
Settlement Agent Confirmed (0) 06.24.2025 |
|
|
| -- |
-- |
Framing I (9) 03.29.2025 |
|
|
| -- |
-- |
Order Steps (0) 04.03.2025 |
|
|
| -- |
-- |
Order Tubs / Showers (0) 04.07.2025 |
|
|
| -- |
-- |
Framing II (8) 03.29.2025 |
|
|
| -- |
-- |
Framing III (8) * 08.24.2025 |
|
|
| -- |
-- |
Verify Window & Roof Structure (0) 05.07.2025 |
|
|
| -- |
-- |
Install Stairs (0) * 05.07.2025 |
|
|
| -- |
-- |
Windows & Doors (0) * 08.24.2025 |
|
|
| -- |
-- |
House Number and Status in Window (0) 05.19.2025 |
|
|
| -- |
-- |
Roofing (0) * 08.24.2025 |
|
|
| -- |
-- |
Order Cabinets (0) 06.23.2025 |
|
|
| -- |
-- |
Order Appliances (0) 06.09.2025 |
|
|
| -- |
-- |
Deck (0) 06.15.2025 |
Standard |
|
| -- |
-- |
Gutters (0) 07.04.2025 |
|
|
| -- |
-- |
Driveway (0) * 08.24.2025 |
|
|
| -- |
-- |
Patio (0) 06.15.2025 |
Standard |
|
| -- |
-- |
Privacy Divider / Fence (0) * 08.24.2025 |
|
|
| -- |
-- |
Sod / Seed / Landscaping (0) 08.12.2025 |
|
|
| -- |
-- |
HVAC Rough In (4) 04.26.2025 |
|
|
| -- |
-- |
Rough In Microwave Vent (0) 04.26.2025 |
Vented to Exterior |
|
| -- |
-- |
Plumbing Rough In (4) 05.14.2025 |
|
|
| -- |
-- |
Electric Rough In (4) 05.21.2025 |
|
|
| -- |
-- |
Inspection (Rough In HVAC) (1) 05.21.2025 |
|
|
| -- |
-- |
Inspection (Rough In Plumbing) (1) 05.21.2025 |
|
|
| -- |
-- |
Inspection (Rough In Electric) (1) 05.21.2025 |
|
|
| -- |
-- |
Inspection (Framing) (1) * 08.24.2025 |
|
|
| -- |
-- |
Inspection (Deck Piers) (0) 06.24.2025 |
|
|
| -- |
-- |
Exterior Vinyl (0) * 08.24.2025 |
|
|
| -- |
-- |
Exterior Stone (0) 07.28.2025 |
|
|
| -- |
-- |
Insulation (2) * 08.24.2025 |
|
|
| -- |
-- |
Inspection (Insulation) (1) 05.22.2025 |
|
|
| -- |
-- |
Inspection (Electric Service) (0) 06.12.2025 |
|
|
| -- |
-- |
Set Electric Meter (0) * 08.24.2025 |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) 06.09.2025 |
|
|
| -- |
-- |
Inspection (Main Water Line) (0) 06.09.2025 |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) 06.24.2025 |
|
|
| -- |
-- |
Drywall (Hang) (4) * 08.24.2025 |
|
|
| -- |
-- |
Loan Approval (0) 08.15.2025 |
JoDee @ United Bank (80% LTV) |
|
| -- |
-- |
Deed Preparation (0) 06.24.2025 |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 08.24.2025 |
In process 6/4 |
|
| -- |
-- |
Paint 1 (1) 06.15.2025 |
|
|
| -- |
-- |
Garage Door (0) 08.03.2025 |
|
|
| -- |
-- |
House Numbers (0) 07.14.2025 |
|
|
| -- |
-- |
Mailbox (0) 07.03.2025 |
|
|
| -- |
-- |
Cabinet Installation (2) * 08.24.2025 |
In process 6/18 |
|
| -- |
-- |
Granite Installation (1) * 08.24.2025 |
|
|
| -- |
-- |
Interior Trim - Install (3) * 08.24.2025 |
In process 6/25 |
|
| -- |
-- |
Order Plumbing / Lighting Fixtures (0) 06.12.2025 |
|
|
| -- |
-- |
Interior Trim - Paint (1) 07.02.2025 |
|
|
| -- |
-- |
Luxury Vinyl Plank (3) * 08.24.2025 |
In process 7/9 |
|
| -- |
-- |
Luxury Vinyl Tile (0) 07.12.2025 |
|
|
| -- |
-- |
Paint 2 (3) 07.18.2025 |
In process 7/16 |
|
| -- |
-- |
Cover Floors (0) 07.30.2025 |
|
|
| -- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 06.19.2025 |
|
|
| -- |
-- |
Shoe Moulding (0) 07.16.2025 |
|
|
| -- |
-- |
Shelving, Door Knobs, Fire Extinguisher (1) * 08.24.2025 |
|
|
| -- |
-- |
Install Coded Lockbox (add extra keys) (0) 08.13.2025 |
|
|
| -- |
-- |
Pay Water / Sewer Taps (0) 06.30.2025 |
|
|
| -- |
-- |
Set Water Meter (1) * 08.24.2025 |
|
|
| -- |
-- |
Electric Trim Out (3) * 08.03.2025 |
Ceiling fans and a few electrical outlet covers and smoke alarms needed. Powder bath needs light fixture as well. |
|
| -- |
-- |
Ceiling Fans (0) 08.21.2025 |
Still need ceiling fan in living room |
|
| -- |
-- |
HVAC Trim Out (1) * 08.24.2025 |
HVAC trimout is completed except thermostat |
|
| -- |
-- |
Blower Door Test (1) 08.15.2025 |
|
|
| -- |
-- |
Plumbing Trim Out (2) * 08.24.2025 |
Bonus bathroom vanity needs trimmed out. Primary shower and pedestal sink too. |
|
| -- |
-- |
Install Appliances (0) * 08.24.2025 |
French/ Current Date: 7/7. On site 6/27 |
|
| -- |
-- |
Paint 3 (2) * 08.24.2025 |
|
|
| -- |
-- |
Carpet (2) 07.18.2025 |
|
|
| -- |
-- |
Appraiser Confirms Construction Completion (0) 08.19.2025 |
|
|
| -- |
-- |
Inspection (Final HVAC) (0) 08.15.2025 |
Scheduled for Friday 8/15 |
|
| -- |
-- |
Inspection (Final Plumbing) (0) 08.15.2025 |
|
|
| -- |
-- |
Inspection (Final Electric) (0) 08.15.2025 |
|
|
| -- |
-- |
Inspection (Final Building) (4) * 08.24.2025 |
|
|
| -- |
-- |
Pre Walk Through (0) 08.18.2025 |
|
|
| -- |
-- |
Stain Hardwood Stairs (1) * 08.24.2025 |
|
|
| -- |
-- |
Cleaning (1) 08.20.2025 |
in process 8/16 |
|
| -- |
-- |
Certificate of Occupancy (1) * 08.24.2025 |
|
|
| -- |
-- |
C.O. to Lender (0) 08.19.2025 |
|
|
| -- |
-- |
Schedule Closing (0) 08.19.2025 |
|
|
| -- |
-- |
Buyer Walk Through (1) * 08.24.2025 |
|
|
| -- |
-- |
Payment for Upgrades (0) 08.15.2025 |
|
|
| -- |
-- |
Keys to Settlement Agent (0) 08.15.2025 |
|
|
| -- |
-- |
Review Settlement Statement (0) 08.19.2025 |
|
|
| -- |
-- |
Jerry Signs Closing Documents (0) 08.20.2025 |
|
|
| -- |
-- |
Request Trash Tote From POA Manager (0) 12.30.2025 |
|
|
| -- |
-- |
Closing (1) 08.21.2025 |
Brittany @ West View Title |
|