PLUMBING TRIM OUT
hide completed
 
Lot       Buyer       Status    Projected    Notes   
000  
40 Daniel Spears 03/27/2025 Completed except master bath
37 Luke Rogers & Scott Rogers 08/19/2025 Bonus bathroom vanity needs trimmed out. Primary shower and pedestal sink too.
20 Salah Abdallah 10/02/2025 In process 9/20
13 Shelby Knoche 11/11/2025
32 Meng Qi Wu 12/09/2025 Almost completed. One fixture missing in the primary bathroom and one fixture missing in the hall bath.
31 Jawad Ahmed & Zainab Ahmed 12/10/2025
30 Dong Dong (Johnny) 12/16/2025 Completed except for small fixture on hall bathroom. And the completion of installing the dishwasher.
29 Zeng Liang Chen 12/23/2025 In process 12/3
28 Ali Anwar 12/23/2025 In process 12/6
12 Austin Beaghan 01/21/2026 In process 1/10 - waiting on farmhouse plumbing
11 Lauren & Jackson Roper 01/21/2026 In process 1/10
10 Jacob Brazelton & Virginia Nordeng 02/06/2026 In process. Toilets installs 1/17
9 Luis Blandon 02/13/2026 Started 1/31
5 Ronnie & Sue Sours 02/23/2026
6 Ronnie & Sue Sours 02/23/2026
7 Ronnie & Sue Sours 02/26/2026
8 Caridad Del Toro 03/03/2026
1 Nara Yoon 02/27/2026
2 Ronnie & Sue Sours 02/27/2026
3 Ronnie & Sue Sours 02/27/2026
4 Fadi Majdoub 02/27/2026