| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| Sat | Aug 22 | Inspection (Concrete Wall) (1) | ||
| Mon | Aug 24 | Inspection (Plumbing Under Slab) (1) | ||
| Tue | Aug 25 | Inspection (Conduit Under Slab) (1) | ||
| Wed | Aug 26 | Inspection (Slab) (1) | ||
| Inspection (Drain Tile) (0) | ||||
| Thu | Aug 27 | Inspection (Rough In HVAC) (1) | ||
| Fri | Aug 28 | Inspection (Rough In Plumbing) (1) | ||
| Mon | Aug 31 | Inspection (Rough In Electric) (1) | ||
| Tue | Sep 1 | Inspection (Framing) (1) * | ||
| Inspection (Deck Piers) (0) | ||||
| Wed | Sep 2 | Inspection (Insulation) (1) | ||
| Inspection (Electric Service) (0) | ||||
| Inspection (Main Sewer Line) (0) | ||||
| Inspection (Main Water Line) (0) | ||||
| Inspection (Final HVAC) (0) | ||||
| Inspection (Final Plumbing) (0) | ||||
| Inspection (Final Electric) (0) | ||||
| Thu | Sep 3 | Inspection (Final Building) (4) * | ||
| TO DO - COMPLETED OR DELETED | ||||
| --- | ||||
| UPGRADES - COMPLETED | ||||
| --- | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 08.19.2026 | ||