- 3  ::  1260 Cottage Lane
[ BUILD: 0273 ]       [ ELEC: 95996 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Wed    Nov 27      Ratified Contract? (0)      
Wed    Nov 27      $2500 Deposit Received (0)      
Wed    Nov 27      Association Packet Requested (0)      
Wed    Nov 27      Association Packet Received (0)      
Wed    Nov 27      Selections Meeting (0)      
Wed    Nov 27      Selections Sheet Signed (0)      
Wed    Nov 27      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Wed    Nov 27      Deposit For Upgrades Received (0)      
Wed    Nov 27      Inspection (Concrete Wall) (1)      
Thu    Nov 28      Inspection (Conduit Under Slab) (1)      
Fri    Nov 29      Inspection (Drain Tile) (0)      
Fri    Nov 29      Settlement Agent Confirmed (0)      
Fri    Nov 29      Verify Window & Roof Structure (0)      
Fri    Nov 29      Order Appliances (0)      
Fri    Nov 29      Patio (0)      
Fri    Nov 29      Rough In Microwave Vent (0)      
Fri    Nov 29      Inspection (Rough In Plumbing) (1)      
Mon    Dec 2      Inspection (Rough In Electric) (1)      
Tue    Dec 3      Inspection (Deck Piers) (0)      
Tue    Dec 3      Inspection (Framing) (1)      
Wed    Dec 4      Exterior Stone (0)      
Wed    Dec 4      Set Electric Meter (0)      
Wed    Dec 4      Inspection (Main Water Line) (0)      
Wed    Dec 4      Loan Approval (0)      
Wed    Dec 4      Deed Preparation (0)      
Wed    Dec 4      Mailbox (0)      
Wed    Dec 4      Order Plumbing / Lighting Fixtures (0)      
Wed    Dec 4      Interior Trim - Paint (1)      
Thu    Dec 5      Ceiling Fans (0)      
Thu    Dec 5      Blower Door Test (1)      
Fri    Dec 6      Inspection (Final HVAC) (1)      
Mon    Dec 9      Inspection (Final Plumbing) (1)      
Tue    Dec 10      Inspection (Final Electric) (1)      
Wed    Dec 11      Stain Hardwood Stairs (1)      
Thu    Dec 12      Schedule Closing (0)      
Thu    Dec 12      Keys to Settlement Agent (0)      
Thu    Dec 12      Review Settlement Statement (0)      
Thu    Dec 12      Jerry Signs Closing Documents (0)      
Thu    Dec 12      Request Trash Tote From POA Manager (0)      
Thu    Dec 12      Remove Coded Lockbox (0)      
--   --   Install Steps
--   --   Order four foot corner tub from Lowe's Kate has ordered
--   --   Add missing windows and doors
--   --   Tile above corner tub Need to grout
--   --   Trim around arched window
--   --   Hardwood laminate and front two bedrooms incorrect. Cane Hickory. See selection sheet. Kate will talk to buyers; Eric offering $300 credit.
--   --   Six crown in kitchen
--   --   Fix cabinet crown in kitchen Hopefully tomorrow
--   --   Select and paint front door
--   --   Is master bath backsplash seaside beige? Looks darker than floor tile
--   --   Finish grouting tile backsplash in master bathroom
--   --   Paint touch up
--   --   Tom thank you for covering granite
--   --   Half the lights don't work. Call Harry
--   --   Electrical trim out
--   --   Touch up paint
--   --   Final cleaning....touch up
--   --   Bonus room vent cover
--   --   Address white trim boards above windows on first floor
--   --   Landscape?
--   --   Replace front door Osbaldo
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)       Happening April 11;
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)       Waiting on dry weather
-- -- Pour Footers (1)      
-- -- Set Forms (2)       Pin footers May 24;
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       Gravel May 26, plumbing May 27
-- -- Inspection (Plumbing Under Slab) (1)       June 1
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)       June 6
-- -- Pour Slab (1) *        June 10
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       August 8
-- -- Plumbing Rough In (4)       Install tub
-- -- Electric Rough In (4)       Starting July 27
-- -- Exterior Vinyl (0) *        K: in process
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Soon
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *       
-- -- Paint 1 (1)       Start painting Aug 25
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Deliver 9/5, install 9/5
-- -- Granite Installation (1) *        9/23
-- -- Interior Trim - Install (3)       In process
-- -- Luxury Vinyl Plank (3) *        Sept 27
-- -- Luxury Vinyl Tile (0)       In progress (Marcus)
-- -- Paint 2 (3)       In process complete by 9/17
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Almost complete- pantry.
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       Nearly complete
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *        Set Friday morning
-- -- Paint 3 (2) *       
-- -- Carpet (2)       September 26
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Tom to call today to schedule for Tuesday
-- -- Pre Walk Through (0)       Monday 10/10 at 4:00
-- -- Cleaning (1)       Kelly this weekend
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       Monday at four
-- -- Payment for Upgrades (0)      
-- -- Closing (1)