Wed |
Nov 27 |
Ratified Contract? (0) |
|
|
Wed |
Nov 27 |
$2500 Deposit Received (0) |
|
|
Wed |
Nov 27 |
Association Packet Requested (0) |
|
|
Wed |
Nov 27 |
Association Packet Received (0) |
|
|
Wed |
Nov 27 |
Selections Meeting (0) |
|
|
Wed |
Nov 27 |
Selections Sheet Signed (0) |
|
|
Wed |
Nov 27 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Wed |
Nov 27 |
Deposit For Upgrades Received (0) |
|
|
Wed |
Nov 27 |
Inspection (Concrete Wall) (1) |
|
|
Thu |
Nov 28 |
Inspection (Conduit Under Slab) (1) |
|
|
Fri |
Nov 29 |
Inspection (Drain Tile) (0) |
|
|
Fri |
Nov 29 |
Settlement Agent Confirmed (0) |
|
|
Fri |
Nov 29 |
Verify Window & Roof Structure (0) |
|
|
Fri |
Nov 29 |
Order Appliances (0) |
|
|
Fri |
Nov 29 |
Patio (0) |
|
|
Fri |
Nov 29 |
Rough In Microwave Vent (0) |
|
|
Fri |
Nov 29 |
Inspection (Rough In Plumbing) (1) |
|
|
Mon |
Dec 2 |
Inspection (Rough In Electric) (1) |
|
|
Tue |
Dec 3 |
Inspection (Deck Piers) (0) |
|
|
Tue |
Dec 3 |
Inspection (Framing) (1) |
|
|
Wed |
Dec 4 |
Exterior Stone (0) |
|
|
Wed |
Dec 4 |
Set Electric Meter (0) |
|
|
Wed |
Dec 4 |
Inspection (Main Water Line) (0) |
|
|
Wed |
Dec 4 |
Loan Approval (0) |
|
|
Wed |
Dec 4 |
Deed Preparation (0) |
|
|
Wed |
Dec 4 |
Mailbox (0) |
|
|
Wed |
Dec 4 |
Interior Trim - Paint (1) |
|
|
Thu |
Dec 5 |
Ceiling Fans (0) |
|
|
Thu |
Dec 5 |
Blower Door Test (1) |
|
|
Fri |
Dec 6 |
Inspection (Final HVAC) (1) |
|
|
Mon |
Dec 9 |
Inspection (Final Plumbing) (1) |
|
|
Tue |
Dec 10 |
Inspection (Final Electric) (1) |
|
|
Wed |
Dec 11 |
Stain Hardwood Stairs (1) |
|
|
Thu |
Dec 12 |
Request Trash Tote From POA Manager (0) |
|
|
|
-- |
-- |
Upstairs broken window (pic) |
Tom to pick up |
|
-- |
-- |
Deputy Fire Chrief- would like rock instead of mulch? |
|
|
-- |
-- |
Update on price for parking space? |
|
|
-- |
-- |
Fix Site Sign |
Blown by wind |
|
-- |
-- |
Lease terminates at the end of May |
|
|
-- |
-- |
Missing master vanity doors |
|
|
-- |
-- |
Paint attic access panel |
|
|
-- |
-- |
Paint access panels in room over garage |
|
|
-- |
-- |
Trim closet door upstairs closet outside of room over garage |
|
|
-- |
-- |
Adjust all upstairs closet doors |
Osbaldo |
|
-- |
-- |
Drywall patch is needed in upstairs hall bathroom |
|
|
-- |
-- |
Missing overflow cover in upstairs hall tub |
|
|
-- |
-- |
Finish kitchen cabinetry |
|
|
-- |
-- |
Clean out garage |
|
|
-- |
-- |
Coded Lockbox 4444 |
|
|
-- |
-- |
Dining room light correct? |
|
|
-- |
-- |
Water leak repair |
|
|
-- |
-- |
Cabinet wont close-lazy Susan |
Kyle |
|
-- |
-- |
Missing upper cabinet trim |
Kyle |
|
-- |
-- |
Install chandelier |
Harry |
|
-- |
-- |
Add smoke detector |
Harry |
|
-- |
-- |
Cleaning after drywall patch |
Kelly |
|
-- |
-- |
Drywall repair from plumbing leak |
|
|
-- |
-- |
Building Permit (30) |
Mindy will check on this; |
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
Mindy will schedule |
|
-- |
-- |
Pour Footers (1) |
|
|
-- |
-- |
Set Forms (2) |
Tues, Aug 15 |
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
Alex |
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
Tom checking |
|
-- |
-- |
Prepare Slab (1) |
Osbaldo to form |
|
-- |
-- |
Inspection (Slab) (1) |
Tom will order |
|
-- |
-- |
Pour Slab (1) * |
11/27: Will happen soon-ish |
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Order Tubs / Showers (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Install Stairs (0) |
|
|
-- |
-- |
Windows & Doors (0) |
|
|
-- |
-- |
House Number and Status in Window (0) |
|
|
-- |
-- |
Roofing (0) |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) |
Concrete done |
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
Maybe a few more items to resolve |
|
-- |
-- |
Plumbing Rough In (4) |
|
|
-- |
-- |
Electric Rough In (4) |
Finishing Feb 12 |
|
-- |
-- |
Exterior Vinyl (0) * |
In process as of Mar 18 |
|
-- |
-- |
Insulation (2) |
Feb 15 ? |
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
SVEC - soon as of Mar 18 |
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
Finishing Mar 11 |
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
In process as of Mar 14 |
|
-- |
-- |
Paint 1 (1) |
Thu, Mar 28 |
|
-- |
-- |
Garage Door (0) |
Greg will schedule - Apr 1 |
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
On site 4/17 |
|
-- |
-- |
Granite Installation (1) * |
Install 5/7 |
|
-- |
-- |
Interior Trim - Install (3) |
Started as of Apr 1/appears 95% completed 4/7 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
Installing 4/24 |
|
-- |
-- |
Paint 2 (3) |
Tom will tell Isaac to paint week of Apr 8 |
|
-- |
-- |
Cover Floors (1) |
Walking path |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) |
Checking |
|
-- |
-- |
Shoe Moulding (0) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) |
Tom will remind Ron that we are ready |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Set Water Meter (0) |
May 20 |
|
-- |
-- |
Electric Trim Out (3) |
Harry- complete on Thursday 5/16 |
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
Bobby |
|
-- |
-- |
Install Appliances (0) * |
May 20 |
|
-- |
-- |
Paint 3 (2) * |
|
|
-- |
-- |
Carpet (2) |
5/7 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
May 21 |
|
-- |
-- |
Pre Walk Through (0) |
Kate 5/14 |
|
-- |
-- |
Cleaning (1) |
|
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Schedule Closing (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Tuesday, May 21 at 3:30 PM |
|
-- |
-- |
Payment for Upgrades (0) |
$1,660 |
|
-- |
-- |
Keys to Settlement Agent (0) |
|
|
-- |
-- |
Review Settlement Statement (0) |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) |
|
|
-- |
-- |
Closing (1) |
|
|
-- |
-- |
Remove Coded Lockbox (0) |
|
|