Wed    Nov 27      Ratified Contract? (0)      
Wed    Nov 27      $2500 Deposit Received (0)      
Wed    Nov 27      Association Packet Requested (0)      
Wed    Nov 27      Association Packet Received (0)      
Wed    Nov 27      Selections Meeting (0)      
Wed    Nov 27      Selections Sheet Signed (0)      
Wed    Nov 27      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Wed    Nov 27      Deposit For Upgrades Received (0)      
Wed    Nov 27      Inspection (Concrete Wall) (1)      
Thu    Nov 28      Inspection (Conduit Under Slab) (1)      
Fri    Nov 29      Inspection (Drain Tile) (0)      
Fri    Nov 29      Settlement Agent Confirmed (0)      
Fri    Nov 29      Verify Window & Roof Structure (0)      
Fri    Nov 29      Patio (0)      
Fri    Nov 29      Rough In Microwave Vent (0)      
Fri    Nov 29      Inspection (Rough In Plumbing) (1)      
Mon    Dec 2      Inspection (Rough In Electric) (1)      
Tue    Dec 3      Inspection (Deck Piers) (0)      
Tue    Dec 3      Inspection (Framing) (1)      
Wed    Dec 4      Exterior Stone (0)      
Wed    Dec 4      Set Electric Meter (0)      
Wed    Dec 4      Inspection (Main Water Line) (0)      
Wed    Dec 4      Loan Approval (0)      
Wed    Dec 4      Deed Preparation (0)      
Wed    Dec 4      Mailbox (0)      
Wed    Dec 4      Interior Trim - Paint (1)      
Thu    Dec 5      Ceiling Fans (0)      
Thu    Dec 5      Blower Door Test (1)      
Fri    Dec 6      Inspection (Final HVAC) (1)      
Mon    Dec 9      Inspection (Final Plumbing) (1)      
Tue    Dec 10      Inspection (Final Electric) (1)      
Wed    Dec 11      Stain Hardwood Stairs (1)      
--   --   Swamp
--   --   Plan for retention pond?
--   --   Will basement walls be insulated? Tell Jared Sheets
--   --   One more window on site 3/29
--   --   Leave laundy room upstairs!
--   --   Extra set of steps?
--   --   Set and wrap porch posts
--   --   Possibly adding basement bath? 6/1 Definitely adding full bath-tub in 6/17
--   --   Tom getting price for finished basement 6/11 24,600 (no bathroom). Kate emailing agent. Maybe after closing 6/18
--   --   Steps needed to porch-before driveways? 6/24
--   --   Ceramic tile in basement bath installed 6/25
--   --   MB shower/tub? 2 shower heads??? 7/8
--   --   Home Inspection, July 30th Pushed off. Waiting to hear from inspector
--   --   Paint left side of outside basement wall 7/26 Reminded Issac. not yet painted 8/19 waiting on dry ground
--   --   Hole in garage ceiling 7/26 set to be fixed friday 7/31
--   --  
--   --   Discolored cabinets in kitchen On order - waiting on arrival date GWB-I think they have been replaced 8/15
--   --   Entry light/stair light snap lights-correct?
--   --   Home Inspection - Aug 12 @ 9AM
--   --   Fridge on back order Amana installed 8/15.
--   --   HVAC issue in garage (hole) and duct work that was moved in basement by JB for venting
--   --   CODED LOCKBOX 7777
--   --   Vanity lights needed 8/12
--   --   Actual refrigerator arrives September 8 Greg will follow up with Leisa
--   --   Railing to basement
--   --   Paint front door Galindez to paint 8/21 when the stain steps
--   --   Half bath mirror (on site)
--   --   Floor register in bedroom & Master
--   --   Patch/paint shower head hole JB patching 8/26
--   --   Fix gutter downspout near garage
--   --   Missing light bulbs?
--   --   Paint attic access 8/19 Galindez painting 8/31 GWB
--   --   Light bulb vanity upstairs bath 8/19 Greg will bring bulbs today 8/24 GWB
--   --   Home Inspection Wed - Aug 26th at 4:30pm
--   --   Molding for cabinets JB to finish - in process 8/23
--   --   911 numbers at thr lad to pass inspection
--   --   911 numbers at the road To pass inspection (note on counter from 8/21)
--   --   Paint touch up 8/26 Few spots need painting. 9/6
--   --   Cable box cover Harry to bring over GWB
--   --   Temporary water hoses? Splash blocks needed? 8/29
--   --   Electric/cable cover needed in garage 8/29
--   --   Move mulch away from siding
--   --   Pressure wash porch/garage? 9/2 JB
--   --   Paint touch up galindez going over 9/14 GWB
--   --   get paint of front patio galindez going over 9/14 GWB
--   --   touch up cabinets Greg to touch up with kit 9/14 GWB
--   --   Fan pull in living room does not work Harry back in town and will fix 9/22 GWB
--   --   master bath mirror has small crack Ron to replace mirror. Scheduling with homeowners GWB
--   --   Obed - (540) 209-5080
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)       Week of Jan 6
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       in process 2/8
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Today 2/14 GWB
-- -- Framing I (9)       in process 2/22
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       just one left to install 3/8
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)       in process 3/13
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       waiting on premier vinyl
-- -- Gutters (0)      
-- -- Driveway (0)       Asphalt-paved 8/12
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Reinspect 5/12
-- -- Plumbing Rough In (4)       Monday, April 27
-- -- Electric Rough In (4)       in process 5/9
-- -- Exterior Vinyl (0) *        All except front porch 4/12
-- -- Insulation (2)       Wed 5/13
-- -- Inspection (Insulation) (1)       today 5/18
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)       Working on it 7/29
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        IN process 5/25
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 6/17
-- -- Paint 1 (1)       Set to start 6/18 per Issac GWB
-- -- Garage Door (0)       Set to install 6/16 gwb
-- -- House Numbers (0)       House numbers up
-- -- Cabinet Installation (2) *        Sink to deliver 7/13 and David to finish 7/14 GWB
-- -- Granite Installation (1) *        Installed July 29
-- -- Interior Trim - Install (3)      
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       In process. Basement bath too 6/24
-- -- Paint 2 (3)       Trim/doors need painting 7/26 Issac guys to paint begining of next week
-- -- Cover Floors (1)       Tom to ask Jill - Wed, Jul 22
-- -- Deliver Plumbing / Lighting Fixtures (0)       Tom has them
-- -- Shoe Moulding (0)       Set to finish Friday 8/7 GWB
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       In process 8/12 set to finish 8/14 GWB
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Paid 6/3
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       In process 8/8
-- -- HVAC Trim Out (1)       HVAC on back order. set to come in next week 8/21
-- -- Plumbing Trim Out (2)       Hawkeye started 8/7 set to finish 8/10
-- -- Install Appliances (0) *        Dishwasher/micro on site 7/26
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Re-inspection Friday, August 21
-- -- Pre Walk Through (0)       Greg to walk through today 8/24
-- -- Cleaning (1)       Is Jill finishing?
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)       Set for Wed 9/16
-- -- Buyer Walk Through (1)       Tuesday, August 25?
-- -- Payment for Upgrades (0)       $5,535 Cereda has check
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Request Trash Tote From POA Manager (0)      
-- -- Closing (1)      
-- -- Remove Coded Lockbox (0)       Greg will grab today 9/22