37 ADDR
CONGERS-2 - 40  ::  1647 Bald Eagle Circle
[ BUILD: 1907-0001 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
Tue    Dec 30      Request Trash Tote From POA Manager (0)      
--   --   On Site Meeting Wed, Sep 25 @ 4PM;
--   --   Window in basement crooked?
--   --   BUYERS EAGER TO CLOSE BY 1/20
--   --   Buyers want to seal garage floor and all unfinished concrete before closing- doable? cost? Tom
--   --   Do not need toilet paper holders installed in any bathroom Kate to communicate with Ron
--   --   ring towel holders at all bathroom sinks
--   --   Hooks instead of rods
--   --   Kate to schedule meetign with Ron for placement of all bath accessories
--   --   Please add hand held to shower head for Martins- Kate to get options from Ferguson
--   --   Buyer would like diagonal bar in shower
--   --   Second Floor Drain
--   --   2 lights by front door/2 on garage fyi for ordering 11/23 see additional pic 12/1
--   --   Expanded patio off basement?
--   --   Trim Out Isaac
--   --   FENCO- cultured marble tops to include an added up hall bath at 31"
--   --   Pratt and Lambert - shell white
--   --   Would like to increase concrete pad Tom & Kate working on it 1/2
--   --   Tile in basement bath covered but not grouted 1/5
--   --   Floor into office cracks/pops loudly 1/8 Tom
--   --  
--   --   Cabinet hardware Jan 9
--   --   Keep Derik Trissel updated on timing
--   --   Garage door molding 1/11
--   --   Molding on kitchen cabinets 1/22 Red knows 2/5
--   --   Silt fence needs repairs in a few sections 1/11
--   --   Confirm mailbox will not be crooked 1/15
--   --  
--   --   Cultured marble Master bath - Thu, Jan 23
--   --   Few missing pieces cabinet molding 1/19
--   --   Staining of steps only 1/2 completed 1/19?
--   --   CODED LOCKBOX 4040
--   --  
--   --  
--   --  
--   --   Attic cover needed in garage 1/26
--   --   Aiming to close on February 11
--   --  
--   --   Fire extinguisher?
--   --   Dents in wood near fridge 2/1 Tom
--   --   Paint 3 is not done 2/1 Isaac
--   --   Cabinet door needs installed sitting in kitchen 2/1 Red
--   --   Kit island molding needed 2/1 Red - in process 2/5
--   --   MB light fixture crooked 2/1 Looks better-2/8
--   --  
--   --   Shutters
--   --   Cabinet hardware in laundry room
--   --   Red needs 3 pulls for cabinets in MB Get Monday from Classic Kitchens
--   --   End of driveway repairs 2/5 Spring
--   --   Ceiling touch up basement room 2/5 ISAAC
--   --  
--   --   tighten hinges on cabinets in kitchen next to laundry door and cabinet in master bathroom RED-I think completed 2/8
--   --   fix stair issue- needs poly ISSAC
--   --   Red to hang curtain rods RED
--   --   loose damaged gusset bottom of attic truss- per reccomendations RED
--   --   Have heat pump examined by Excel EXCEL
--   --   Fix insulation in attic GREG
--   --   Floor drain in basement to be uncovered RED
--   --   Fix insulation in basement GREG
--   --   fasteners to be added to deck railing at rear and at decking board at outside edge RED
--   --   Lightbulb needed downstairs bathroom vanity light
--   --   Power wash concrete patio
--   --   Cut back rubber flashing
--   --   Patch cement patio - Red or JB
--   --   Silver blades need to be added to living room ceiling fan
--   --   Stopper hinge on cabinet to the left of cabinet. Kate emailed Kimberly for hinges 2/7 - Red or JB
--   --   Power wash deck
--   --   Top drawer left of oven is crooked
--   --   Far left island door needs replacement On site, waiting to install - Red or JB
--   --   Right sink door needs replacement On site, waiting to install - Red or JB
--   --  
--   --   Exterior garage door key pad need a to be installed
--   --  
--   --  
--   --  
--   --   Repaint garage? Touch up paint throughout 2/8
--   --   Comcast needs to run a line
--   --   Replace drawer front that was mis-drilled On site, waiting to install - Red or JB
--   --   Replace garage door weather stripping Greg S
--   --   Dan Martin = 540-820-5471
--   --   Install numbers on mailbox
--   --   Red left a bucket with things in it at the house
--   --   Cracked window frame 11/16 - John Weeks to fix 12/5 (Saturday)
--   --   Replace dead shrub
--   --   Re-seed trouble spots in yard Tom told Roger about it
--   --   Peeling paint on the garage Isaac
--   --   Resurfacing of concrete patio Red
--   --   Landscaping at back corner of the lot Pettit knows and will fix when they do other landscaping at HE29
--   --   Issues with concrete patio under deck Coating discolors when wet - Tom will call Scott at Superior
-- -- Building Permit (30) *        Plans sent to printer on June 17
    CREDIT- NO DINING CHANDELIER  
    Paint upgrade- Third coat of Second selection paint in specified areas  
    Custom Closet Shelving Difference  
    Sod yard upgrade  
    LED undercabinet light upgrade  
-- -- Order Roof & Floor Trusses (1)      
    Addressing deck railing and boards. Make even fill holes  
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
    Convert Crawlspace to Unfinished Basement  
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *        7/29 starting
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)       Alex
-- -- Inspection (Plumbing Under Slab) (1)       Fri, Aug 30
-- -- Prepare Slab (1)       Tues, Sep 3
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Wed, Sep 4
-- -- Framing I (9)       Starting Sep 9
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
    Bedroom, Hallway, Full Bathroom in Basement  
    Expanded Kitchen Area  
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
    Fake Fireplace  
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        90% done 10/30
-- -- Order Cabinets (0)      
    Island set of 2 roll out trays- (total of four)  
    Lazy Susans in both the upper and base corner cabinet  
    Spice Pull Out in W1242 to the right of microwave  
    3 drawer configuartion to the right of the fridge (instead of base cabinet)  
    Tray Dividers base cabinet left of fridge and above fridge  
-- -- Order Appliances (0)      
-- -- Deck (0)       being installed 1/8
    Decks per Plans  
    Side Deck changes  
-- -- Gutters (0)      
-- -- Driveway (0) *        To be formed on Fri, Jan 24
    Expanded Concrete Pad Outside of Basement Door  
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       Plumbing inspection 10/30
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Mon, Nov 4
-- -- Exterior Vinyl (0) *        Stone 95% complete 1/5
-- -- Insulation (2) *        Mon, Nov 4
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Pipe is in
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 11/9
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        All taped/needs sanding 12/7
-- -- Paint 1 (1)       Wed, Dec 11
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Installing hardware 1/8
    Laundry Room cabinets  
-- -- Granite Installation (1) *        Thurs, Jan 16
-- -- Interior Trim - Install (3) *        Let MRTINS KNOW WHEN TRIM COMPLETE FOR WINDOW MEASUREMENTS/in process 12/28
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Just needs grout in shower 1/19
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       Jan 23
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In process 1/29
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *        Fri, Jan 24
-- -- Electric Trim Out (3) *        In process 1/15
-- -- HVAC Trim Out (1) *        Heat pump set 1/11
-- -- Plumbing Trim Out (2) *        In process 1/29
-- -- Install Appliances (0) *        Wed, Jan 29
    Whirpool fingerprint resistant SS Appliance Package Upgrade  
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Needed on second floor
    8 lb carpet pad throughout  
    Upgrading to a runner on stained pine steps (includes cost to sand and stain steps) cost absed on standard carpet selection- price would increase based on carpet selection.  
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Fri, Jan 31 or Mon, Feb 3 (reinspect Mon Feb 3)
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Finish cleaning over weekend
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Friday at 9:30
-- -- Payment for Upgrades (0)       $8,665
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title, Mon, Feb 10 at 10:00 AM
-- -- Remove Coded Lockbox (0)