Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Schedule Closing (0)      
Fri    Dec 13      Keys to Settlement Agent (0)      
Fri    Dec 13      Review Settlement Statement (0)      
Fri    Dec 13      Jerry Signs Closing Documents (0)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
Fri    Dec 13      Remove Coded Lockbox (0)      
--   --   Install the last few windows and doors;
--   --   Plumb gas line for stove
--   --   Plumb gas line for fireplace
--   --   Darker Shutters EXACTLY LIKE LOT 32
--   --   No hardwood in alcoves by front door. See note in changes. Please change as soon as possible
--   --   Deck Rail and Steps
--   --   Please cover granite!!! K: 7/25: cover island please
--   --   Basement bath closet flooring? Ceramic tile
--   --   Buyer wants mulch NOT rock
--   --   Drywall arhes
--   --   Drywall arches
--   --   Deck
--   --   Hardwood laminate at the bottom of the steps
--   --   Living room floor vent cut wider
--   --   Bottom trim on shelf at arches?
--   --   Touch up grout in several placesn master bath
--   --   Touch up paint
--   --   Fix baseboard in master linen closet
--   --   Finish trim/ shoe old in downstairs bath closet
--   --   Touch up paint
--   --   Touch up cleaning
--   --   Poly steps and paint risers
--   --   Touch up grout in master bath
--   --   One window on the side of the house is missing shutters Tom
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       4/11: Setting roof trusses;
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)       Remainder will arrive May 10;
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)       Shingles going on now;
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)       In process
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tuesday, May 17
-- -- Plumbing Rough In (4)       Plumbing gas line;
-- -- Electric Rough In (4)       Nearly done;
-- -- Exterior Vinyl (0) *        K: 6/20 nearly complete
-- -- Insulation (2)       Wednesday, May 18
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Meter base to be set May 16
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *       
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        K: in process
-- -- Paint 1 (1)       Primed on June 10;
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivery June 16; Install June 20;
-- -- Granite Installation (1) *        July 5
-- -- Interior Trim - Install (3)       K: 6/20 nearly complete
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       7/25 K: Everything complete except shower
-- -- Paint 2 (3)       7/25: K: finishing 7/27
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       July 25
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       8/1 almost complete
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Friday, July 29
-- -- Install Appliances (0) *        July 25
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Mon, Aug 1
-- -- Pre Walk Through (0)       Mon, Aug 1
-- -- Cleaning (1)       July 30 (Cheryl)
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Buyer Walk Through (1)       8/3 at 11:00
-- -- Payment for Upgrades (0)      
-- -- Closing (1)