Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
ALL CABINETRY IS BURLAP_ CORRECTION FROM SELECTION SHEET |
|
|
-- |
-- |
Are the cabinets the correct color? |
Cabinets removed and in kitchen 7/16 |
|
-- |
-- |
Vanity tops needed 7/12 |
In living room 7/16 |
|
-- |
-- |
Odd drywall hole in garage |
Add bisquit - Tom. Finishing 8/23 |
|
-- |
-- |
Drywall repair from master bath closet move |
Drywaller |
|
-- |
-- |
Repair drywall, hole, in kitchen ceiling |
Drywaller |
|
-- |
-- |
Is there a need to patch the concrete hole in the utility room? |
Tom |
|
-- |
-- |
Needs transition strips at all plank flooring areas |
Denny |
|
-- |
-- |
Needs thermostat |
HVAC |
|
-- |
-- |
Buyer out of the country Aug 23 - Sep 17 |
|
|
-- |
-- |
Farm sink installed backwards |
|
|
-- |
-- |
Cabinet hardware is different-I think Kate mentioned it may be? |
|
|
-- |
-- |
Master bathroom vanity needs installed |
And bonus |
|
-- |
-- |
Toilet seat lid/top needed in bonus bath |
Mazur |
|
-- |
-- |
Master bath, vanity missing bottom trim |
George |
|
-- |
-- |
Master bathroom needs floor trim |
George |
|
-- |
-- |
Whiteboards needed below all back patio doors |
Tom |
|
-- |
-- |
Paint, exposed concrete on all town houses |
Painter |
|
-- |
-- |
Vent cover, needed in front rock on 35 and 37 |
Davenport |
|
-- |
-- |
Electric cover needed on kitchen island |
Electrician |
|
-- |
-- |
Smoke detector needed in living room |
Electrician |
|
-- |
-- |
Second coated steps is going to be needed on painted stairs |
Painter |
|
-- |
-- |
Shoe molding needed master bath |
|
|
-- |
-- |
I am bothered the heat pumps have plastic where a brand sticker/logo should be with no logo there. |
|
|
-- |
-- |
Trim needed in all garages |
George |
|
-- |
-- |
Vanity light needed in bonus that |
Bath |
|
-- |
-- |
Powder bath needs light |
Electrician |
|
-- |
-- |
Mirrors needed in all but bonus bath |
|
|
-- |
-- |
Brand stickers needed on heat pumps |
|
|
-- |
-- |
Oil spill in garage |
Jill |
|
-- |
-- |
CODEDLOCKBOX 3535 |
|
|
-- |
-- |
Black shower drain needed |
Plumber |
|
-- |
-- |
Air vent needed on outside of utility room |
|
|
-- |
-- |
Few more screws needed in cable box cover |
Tom |
|
-- |
-- |
Remove white glue from stair transition strip |
Denny |
|
-- |
-- |
Remove glue from bathtub |
Jill |
|
-- |
-- |
Chunk of trim, missing at back patio door |
Painter |
|
-- |
-- |
Clean window sill, bonus room |
Lynn |
|
-- |
-- |
Clean off glue residue, bonus room transition strip |
Denny |
|
-- |
-- |
Drywall, patch, bonus room, vanity light |
Painter |
|
-- |
-- |
Second coat of paint on stairs to bedroom level |
Painter |
|
-- |
-- |
Nail pop between pedestal sink and mirror |
Painter |
|
-- |
-- |
Adjust pantry pocket door |
George |
|
-- |
-- |
Clean glue residue off transition strip at top of stairs |
|
|
-- |
-- |
Install a window screens |
|
|
-- |
-- |
Install a window screens |
Jill |
|
-- |
-- |
Clean out garage |
Jill |
|
-- |
-- |
Complete sos |
|
|
-- |
-- |
Pressure wash front after sos complete |
Jill |
|
-- |
-- |
Clean off back patio |
Jill |
|
-- |
-- |
Fill nail holes, master vanity, trim |
Painter |
|
-- |
-- |
Replace light receptacle in master bathroom |
Switch plate cover - Electrician |
|
-- |
-- |
Adjust temperature, hot water heater |
Tom |
|
-- |
-- |
Adjust cap next hot cold water in laundry |
Tom |
|
-- |
-- |
Nail pop below banister from main level |
Painter |
|
-- |
-- |
Sod |
Pettit |
|
-- |
-- |
Few screens needed |
Jill |
|
-- |
-- |
Remop floors |
Lynn |
|
-- |
-- |
A/C broken |
Jason |
|
-- |
-- |
Remove blue tape |
Jill - from front porch overhang |
|
-- |
-- |
Ratified Contract? (0) 02.11.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 02.16.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 02.11.2023 |
|
|
-- |
-- |
Association Packet Received (0) 02.14.2023 |
|
|
-- |
-- |
Selections Meeting (0) 03.10.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0) 03.22.2023 |
3/10: Sent to Matt for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 03.31.2023 |
3/29: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 03.29.2023 |
|
|
-- |
-- |
Building Permit (30) 11.07.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 05.01.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 05.01.2023 |
|
|
-- |
-- |
Stake Out Home (1) 01.02.2023 |
|
|
-- |
-- |
Excavate (2) 01.02.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 01.02.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 01.31.2023 |
|
|
-- |
-- |
Pour Footers (1) 01.02.2023 |
|
|
-- |
-- |
Set Forms (2) 01.31.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 01.31.2023 |
|
|
-- |
-- |
Plumb Slab (2) 03.23.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 03.23.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 03.23.2023 |
|
|
-- |
-- |
Prepare Slab (1) 03.23.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 03.23.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 04.17.2023 |
|
|
-- |
-- |
Pour Slab (1) * 03.23.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 06.15.2023 |
|
|
-- |
-- |
Framing I (9) 04.27.2023 |
|
|
-- |
-- |
Order Steps (0) 05.01.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 05.28.2023 |
|
|
-- |
-- |
Framing II (8) 04.27.2023 |
|
|
-- |
-- |
Framing III (8) * 05.11.2023 |
|
|
-- |
-- |
Install Stairs (0) 05.17.2023 |
|
|
-- |
-- |
Windows & Doors (0) 05.28.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 06.15.2023 |
|
|
-- |
-- |
Roofing (0) 05.28.2023 |
|
|
-- |
-- |
Order Cabinets (0) 06.06.2023 |
|
|
-- |
-- |
Order Appliances (0) 07.27.2023 |
|
|
-- |
-- |
Deck (0) 06.12.2023 |
|
|
-- |
-- |
Gutters (0) 08.02.2023 |
|
|
-- |
-- |
Driveway (0) 08.19.2023 |
|
|
-- |
-- |
Patio (0) 08.02.2023 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 09.10.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 09.27.2023 |
Front needed 9/16 |
|
-- |
-- |
HVAC Rough In (4) 05.28.2023 |
In process 5/28 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 06.12.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 05.28.2023 |
In process 5/24 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 06.12.2023 |
|
|
-- |
-- |
Electric Rough In (4) 06.03.2023 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 06.12.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 06.26.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 06.12.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 07.22.2023 |
in process 7/16 |
|
-- |
-- |
Exterior Stone (0) 07.30.2023 |
in process 7/26 |
|
-- |
-- |
Insulation (2) 06.14.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1) 06.19.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 08.21.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 09.14.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 03.20.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 03.20.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 07.27.2023 |
|
|
-- |
-- |
Drywall (Hang) (4) * 06.26.2023 |
|
|
-- |
-- |
Loan Approval (0) 09.07.2023 |
|
|
-- |
-- |
Deed Preparation (0) 08.28.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 07.09.2023 |
Appears completed just needs to be cleaned up |
|
-- |
-- |
Paint 1 (1) 07.09.2023 |
|
|
-- |
-- |
Garage Door (0) 08.23.2023 |
|
|
-- |
-- |
House Numbers (0) 08.30.2023 |
Jill |
|
-- |
-- |
Mailbox (0) 09.25.2023 |
Needed 9/16 |
|
-- |
-- |
Cabinet Installation (2) * 08.19.2023 |
Fri, Aug 18 |
|
-- |
-- |
Granite Installation (1) * 08.30.2023 |
|
|
-- |
-- |
Interior Trim - Install (3) 07.19.2023 |
In process 7/16 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 07.30.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 07.22.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 07.30.2023 |
Tom will mark off the floor |
|
-- |
-- |
Luxury Vinyl Tile (0) 07.30.2023 |
|
|
-- |
-- |
Paint 2 (3) 07.09.2023 |
|
|
-- |
-- |
Cover Floors (1) 08.02.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 08.02.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 08.23.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 09.06.2023 |
In process 8/30 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 09.10.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 08.21.2023 |
|
|
-- |
-- |
Set Water Meter (0) 08.28.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 08.26.2023 |
|
|
-- |
-- |
Ceiling Fans (0) 08.26.2023 |
Living Room |
|
-- |
-- |
HVAC Trim Out (1) 08.09.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2) 09.10.2023 |
Finish 9/7 |
|
-- |
-- |
Install Appliances (0) * 08.31.2023 |
Delivery 8/10 |
|
-- |
-- |
Paint 3 (2) * 08.09.2023 |
|
|
-- |
-- |
Carpet (2) 08.02.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 09.18.2023 |
9/15 |
|
-- |
-- |
Inspection (Final HVAC) (1) 09.16.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 09.16.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 09.16.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 09.16.2023 |
|
|
-- |
-- |
Pre Walk Through (0) 09.21.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 09.03.2023 |
In process 8/30 |
|
-- |
-- |
Cleaning (1) 09.20.2023 |
9/18 |
|
-- |
-- |
Certificate of Occupancy (1) * 09.20.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 09.20.2023 |
|
|
-- |
-- |
Schedule Closing (0) 09.27.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 09.25.2023 |
Thu, Sep 21, 11AM |
|
-- |
-- |
Payment for Upgrades (0) 09.21.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 09.21.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 09.27.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 08.16.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 09.21.2023 |
|
|
-- |
-- |
Closing (1) 10.09.2023 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 10.12.2023 |
|
|