CONGERS-2 - 1  ::  1790 Heritage Estates Circle
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (May 21)    show all photos
--   --   Refrigerator door replacement After Closing
Fri    May 23      Ratified Contract? (0)      
Fri    May 23      $2500 Deposit Received (0)      
Fri    May 23      Association Packet Requested (0)      
Fri    May 23      Association Packet Received (0)      
Fri    May 23      Selections Meeting (0)      
Fri    May 23      Selections Sheet Signed (0)      
Fri    May 23      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Fri    May 23      Deposit For Upgrades Received (0)      
Fri    May 23      Inspection (Concrete Wall) (1)      
Mon    May 26      Inspection (Conduit Under Slab) (1)      
Tue    May 27      Inspection (Drain Tile) (0)      
Tue    May 27      Settlement Agent Confirmed (0)      
Tue    May 27      Order Tubs / Showers (0)      
Tue    May 27      Verify Window & Roof Structure (0)      
Tue    May 27      Install Stairs (0)      
Tue    May 27      House Number and Status in Window (0)      
Tue    May 27      Order Appliances (0)      
Tue    May 27      Patio (0)      
Tue    May 27      Rough In Microwave Vent (0)      
Tue    May 27      Inspection (Rough In Plumbing) (1)      
Wed    May 28      Inspection (Rough In Electric) (1)      
Thu    May 29      Inspection (Deck Piers) (0)      
Thu    May 29      Inspection (Framing) (1) *       
Fri    May 30      Exterior Stone (0)      
Fri    May 30      Set Electric Meter (0) *       
Fri    May 30      Inspection (Main Water Line) (0)      
Fri    May 30      Loan Approval (0)      
Fri    May 30      Deed Preparation (0)      
Fri    May 30      Garage Door (0) *       
Fri    May 30      Mailbox (0)      
Fri    May 30      Order Plumbing / Lighting Fixtures (0)      
Fri    May 30      Interior Trim - Paint (1)      
Mon    Jun 2      Cover Floors (1)      
Tue    Jun 3      Deliver Plumbing / Lighting Fixtures (0)      
Tue    Jun 3      Shoe Moulding (0)      
Tue    Jun 3      Set Water Meter (0) *       
Tue    Jun 3      Ceiling Fans (0)      
Tue    Jun 3      Blower Door Test (1)      
Wed    Jun 4      Paint 3 (2) *       
Fri    Jun 6      Appraiser Confirms Construction Completion (0)      
Fri    Jun 6      Inspection (Final HVAC) (1)      
Mon    Jun 9      Inspection (Final Plumbing) (1)      
Tue    Jun 10      Inspection (Final Electric) (1)      
Wed    Jun 11      Stain Hardwood Stairs (1)      
Thu    Jun 12      C.O. to Lender (0)      
Thu    Jun 12      Schedule Closing (0)      
Thu    Jun 12      Payment for Upgrades (0)      
Thu    Jun 12      Keys to Settlement Agent (0)      
Thu    Jun 12      Review Settlement Statement (0)      
Thu    Jun 12      Jerry Signs Closing Documents (0)      
Thu    Jun 12      Request Trash Tote From POA Manager (0)      
Thu    Jun 12      Remove Coded Lockbox (0)      
--   --   Replace front of freezer (ding) Kate to call back service center with serial number
--   --   Resolve basement shower issue
--   --   When will we install ceramic back splash buyer would like to be present Needs thinset
--   --   Butler's pantry Del Jan 23, Install Jan 24-26
--   --   Basement vanity Timing TBD
--   --   Light fixture outside sliding door on main level
--   --   Install shower door After Closing
--   --   Remove granite backsplash
--   --   Install ceramic tile backsplash February 3rd
--   --   Install cedar siding in closet Tom to call- Mitch install Saturday
--   --   Touch up ceiling paint very splotchy Thursday, Feb 16
--   --   Downstairs Shower? 1/26 late in day
--   --   Vinyl Tues, Feb 7
--   --   Backing in shower- tom to install grab bar, or Ron? Brushed nickel- get Ron to do
--   --   Hardwood flooring issues upstairs
--   --   Remove master closet shelving
--   --   Install hardware on screen door JB
--   --   Keypad at garage door Greg
--   --   Install pull down stairs in garage
--   --   Install light above butler's pantry
--   --   Install missing under cabinet light under cabinet to left of refrigerator
--   --   Under cabinet light in Butler cabinet
--   --   TOM- PLEASE COVER RANGE TO PROTECT FROM TILE BACK SPLASH
--   --   Install grab bar (VA Installation) Ron
--   --   Mitch change out bathroom doors 2'6- put up oak handrail Change order fees.
--   --   Ceramic back splash
--   --   Fireplace in basement?
--   --   Anchor bolt in storage room wall JB
--   --   Thresholds at carpet- bedroom and office
--   --   LED lights purchased by Tom
--   --   Adding snap light over ceiling Added recently
--   --   LED lights in master bathroom?
--   --   Install and stain oak handrail Stained, just install
--   --   Install keypad for garage door Greg
--   --   Cleaning Cheryl
--   --   Basement tub repair Friday, Feb 17
--   --   Stone and caulk repairs Friday, Feb 17
--   --   Mailbox repair Thursday, Feb 16
--   --   Replace kitchen cabinet fronts
--   --   Replace damaged kitchen cabinet fronts
--   --   HVAC cleaning TBD game plan
--   --   Air handler cleaning
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        Materials have been ordered;
-- -- Windows & Doors (0) *       
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tuesday morning 1/17
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)       Tuesday morning 1/17
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Tuesday afternoon 1/17
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process- complete by Monday afternoon the 23rd
-- -- Paint 1 (1)       Tuesday 1/24
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Del- Wed 2/1; Install Thursday the 2nd; Granite install 2/6
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3) *        Mitch, Wed 1/25- through Friday 1/27
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Saturday 28th and Sunday 29th
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        Needs to be finished
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       Now
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *       
-- -- Carpet (2)       Carpet and Vinyl- Friday the 3rd
-- -- Inspection (Final Building) (2) *        Tues, Feb 7
-- -- Pre Walk Through (0)       Tuesday 2/7
-- -- Cleaning (1)       Wed, Feb 8 - start upstairs
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1)      
-- -- Closing (1)