CONGERS-2 - 1  ::  1790 Heritage Estates Circle
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Saturday (Nov 23)    show all photos
--   --   Refrigerator door replacement After Closing
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Order Tubs / Showers (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Install Stairs (0)      
Mon    Dec 2      House Number and Status in Window (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Garage Door (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Order Plumbing / Lighting Fixtures (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Cover Floors (1)      
Mon    Dec 9      Deliver Plumbing / Lighting Fixtures (0)      
Mon    Dec 9      Shoe Moulding (0)      
Mon    Dec 9      Set Water Meter (0)      
Mon    Dec 9      Ceiling Fans (0)      
Mon    Dec 9      Blower Door Test (1)      
Tue    Dec 10      Paint 3 (2) *       
Thu    Dec 12      Appraiser Confirms Construction Completion (0)      
Thu    Dec 12      Inspection (Final HVAC) (1)      
Fri    Dec 13      Inspection (Final Plumbing) (1)      
Mon    Dec 16      Inspection (Final Electric) (1)      
Tue    Dec 17      Stain Hardwood Stairs (1)      
Wed    Dec 18      C.O. to Lender (0)      
Wed    Dec 18      Schedule Closing (0)      
Wed    Dec 18      Payment for Upgrades (0)      
Wed    Dec 18      Keys to Settlement Agent (0)      
Wed    Dec 18      Review Settlement Statement (0)      
Wed    Dec 18      Jerry Signs Closing Documents (0)      
Wed    Dec 18      Request Trash Tote From POA Manager (0)      
Wed    Dec 18      Remove Coded Lockbox (0)      
--   --   Replace front of freezer (ding) Kate to call back service center with serial number
--   --   Resolve basement shower issue
--   --   When will we install ceramic back splash buyer would like to be present Needs thinset
--   --   Butler's pantry Del Jan 23, Install Jan 24-26
--   --   Basement vanity Timing TBD
--   --   Light fixture outside sliding door on main level
--   --   Install shower door After Closing
--   --   Remove granite backsplash
--   --   Install ceramic tile backsplash February 3rd
--   --   Install cedar siding in closet Tom to call- Mitch install Saturday
--   --   Touch up ceiling paint very splotchy Thursday, Feb 16
--   --   Downstairs Shower? 1/26 late in day
--   --   Vinyl Tues, Feb 7
--   --   Backing in shower- tom to install grab bar, or Ron? Brushed nickel- get Ron to do
--   --   Hardwood flooring issues upstairs
--   --   Remove master closet shelving
--   --   Install hardware on screen door JB
--   --   Keypad at garage door Greg
--   --   Install pull down stairs in garage
--   --   Install light above butler's pantry
--   --   Install missing under cabinet light under cabinet to left of refrigerator
--   --   Under cabinet light in Butler cabinet
--   --   TOM- PLEASE COVER RANGE TO PROTECT FROM TILE BACK SPLASH
--   --   Install grab bar (VA Installation) Ron
--   --   Mitch change out bathroom doors 2'6- put up oak handrail Change order fees.
--   --   Ceramic back splash
--   --   Fireplace in basement?
--   --   Anchor bolt in storage room wall JB
--   --   Thresholds at carpet- bedroom and office
--   --   LED lights purchased by Tom
--   --   Adding snap light over ceiling Added recently
--   --   LED lights in master bathroom?
--   --   Install and stain oak handrail Stained, just install
--   --   Install keypad for garage door Greg
--   --   Cleaning Cheryl
--   --   Basement tub repair Friday, Feb 17
--   --   Stone and caulk repairs Friday, Feb 17
--   --   Mailbox repair Thursday, Feb 16
--   --   Replace kitchen cabinet fronts
--   --   Replace damaged kitchen cabinet fronts
--   --   HVAC cleaning TBD game plan
--   --   Air handler cleaning
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        Materials have been ordered;
-- -- Windows & Doors (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0)      
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)       Tuesday morning 1/17
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)       Tuesday morning 1/17
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Tuesday afternoon 1/17
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process- complete by Monday afternoon the 23rd
-- -- Paint 1 (1)       Tuesday 1/24
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Del- Wed 2/1; Install Thursday the 2nd; Granite install 2/6
-- -- Granite Installation (1) *       
-- -- Interior Trim - Install (3)       Mitch, Wed 1/25- through Friday 1/27
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Saturday 28th and Sunday 29th
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Needs to be finished
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Electric Trim Out (3)       Now
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *       
-- -- Carpet (2)       Carpet and Vinyl- Friday the 3rd
-- -- Inspection (Final Building) (2) *        Tues, Feb 7
-- -- Pre Walk Through (0)       Tuesday 2/7
-- -- Cleaning (1)       Wed, Feb 8 - start upstairs
-- -- Certificate of Occupancy (1) *       
-- -- Buyer Walk Through (1)      
-- -- Closing (1)