CONGERS-3 - 39  ::  1623 Palomino Trail
[ BUILD: 20241830 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Closing complete on house to be sold? scheduled to close Nov 30
--   --   Must close by 1031 deadline!
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Order Windows & Doors (0)      
Thu    Nov 28      Settlement Agent Confirmed (0)      
Thu    Nov 28      Order Steps (0)      
Thu    Nov 28      Order Tubs / Showers (0)      
Thu    Nov 28      Framing II (8)      
Tue    Dec 10      Framing III (8) *       
Fri    Dec 20      Verify Window & Roof Structure (0)      
Fri    Dec 20      Install Stairs (0)      
Fri    Dec 20      Windows & Doors (0)      
Fri    Dec 20      House Number and Status in Window (0)      
Fri    Dec 20      Roofing (0)      
Fri    Dec 20      Order Cabinets (0)      
Fri    Dec 20      Order Appliances (0)      
Fri    Dec 20      Deck (0)      
Fri    Dec 20      Gutters (0)      
Fri    Dec 20      Driveway (0)      
Fri    Dec 20      Patio (0)      
Fri    Dec 20      Privacy Divider / Fence (0)      
Fri    Dec 20      Sod / Seed / Landscaping (0)      
Fri    Dec 20      HVAC Rough In (4)      
Thu    Dec 26      Inspection (Rough In HVAC) (1)      
Fri    Dec 27      Rough In Microwave Vent (0)      
Fri    Dec 27      Plumbing Rough In (4)      
Thu    Jan 2      Inspection (Rough In Plumbing) (1)      
Fri    Jan 3      Electric Rough In (4)      
Thu    Jan 9      Inspection (Rough In Electric) (1)      
Fri    Jan 10      Inspection (Deck Piers) (0)      
Fri    Jan 10      Inspection (Framing) (1)      
Mon    Jan 13      Exterior Vinyl (0) *       
Mon    Jan 13      Exterior Stone (0)      
Mon    Jan 13      Insulation (2)      
Wed    Jan 15      Inspection (Insulation) (1)      
Thu    Jan 16      Inspection (Electric Service) (0)      
Thu    Jan 16      Set Electric Meter (0)      
Thu    Jan 16      Inspection (Main Sewer Line) (0)      
Thu    Jan 16      Inspection (Main Water Line) (0)      
Thu    Jan 16      Order Interior Doors & Trim (0)      
Thu    Jan 16      Drywall (Hang) (4) *       
Wed    Jan 22      Loan Approval (0)      
Wed    Jan 22      Deed Preparation (0)      
Wed    Jan 22      Drywall (Tape, Block, Skim, Sand) (6) *       
Thu    Jan 30      Paint 1 (1)      
Fri    Jan 31      Garage Door (0)      
Fri    Jan 31      House Numbers (0)      
Fri    Jan 31      Mailbox (0)      
Fri    Jan 31      Cabinet Installation (2) *       
Tue    Feb 4      Granite Installation (1) *       
Wed    Feb 5      Interior Trim - Install (3)      
Mon    Feb 10      Order Plumbing / Lighting Fixtures (0)      
Mon    Feb 10      Interior Trim - Paint (1)      
Tue    Feb 11      Luxury Vinyl Plank (3) *       
Fri    Feb 14      Luxury Vinyl Tile (0)      
Fri    Feb 14      Paint 2 (3)      
Wed    Feb 19      Cover Floors (1)      
Thu    Feb 20      Deliver Plumbing / Lighting Fixtures (0)      
Thu    Feb 20      Shoe Moulding (0)      
Thu    Feb 20      Shelving, Door Knobs, Fire Extinguisher (0)      
Thu    Feb 20      Install Coded Lockbox (add extra keys) (0)      
Thu    Feb 20      Pay Water / Sewer Taps (0)      
Thu    Feb 20      Set Water Meter (0)      
Thu    Feb 20      Electric Trim Out (3)      
Tue    Feb 25      Ceiling Fans (0)      
Tue    Feb 25      HVAC Trim Out (1)      
Wed    Feb 26      Blower Door Test (1)      
Thu    Feb 27      Plumbing Trim Out (2)      
Mon    Mar 3      Install Appliances (0) *       
Mon    Mar 3      Paint 3 (2) *       
Wed    Mar 5      Carpet (2)      
Fri    Mar 7      Appraiser Confirms Construction Completion (0)      
Fri    Mar 7      Inspection (Final HVAC) (1)      
Mon    Mar 10      Inspection (Final Plumbing) (1)      
Tue    Mar 11      Inspection (Final Electric) (1)      
Wed    Mar 12      Inspection (Final Building) (2) *       
Fri    Mar 14      Pre Walk Through (0)      
Fri    Mar 14      Stain Hardwood Stairs (1)      
Mon    Mar 17      Cleaning (1)      
Tue    Mar 18      Certificate of Occupancy (1) *       
Wed    Mar 19      C.O. to Lender (0)      
Wed    Mar 19      Schedule Closing (0)      
Wed    Mar 19      Buyer Walk Through (1)      
Thu    Mar 20      Payment for Upgrades (0)      
Thu    Mar 20      Keys to Settlement Agent (0)      
Thu    Mar 20      Review Settlement Statement (0)      
Thu    Mar 20      Jerry Signs Closing Documents (0)      
Thu    Mar 20      Request Trash Tote From POA Manager (0)      
Thu    Mar 20      Closing (1)      
Fri    Mar 21      Remove Coded Lockbox (0)      
-- -- Ratified Contract? (0)  11.02.2024    
-- -- $2500 Deposit Received (0)  11.02.2024    
-- -- Association Packet Requested (0)  11.02.2024    
-- -- Association Packet Received (0)  11.08.2024    
-- -- Building Permit (30)  10.07.2024    
-- -- Order Roof & Floor Trusses (1)  10.17.2024    
-- -- Stake Out Home (1)  10.14.2024    
-- -- Excavate (2)  10.21.2024    
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Pour Footers (1)  10.21.2024    
-- -- Set Forms (2)  11.13.2024    
-- -- Pour Foundation Walls (1)  11.13.2024    
-- -- Plumb Slab (2)  11.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.13.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.13.2024    
-- -- Prepare Slab (1)  11.13.2024    
-- -- Inspection (Slab) (1)  11.13.2024    
-- -- Inspection (Drain Tile) (0)  11.13.2024    
-- -- Pour Slab (1) *   11.13.2024    
-- -- Framing I (9)  11.24.2024