000 40 37 20 13 32 31 30 29 28 12 11 10 9 5 6 7 8 1 2 3 4 ADDR
CONGERS-3 - 41  ::  1615 Palomino Trail
[ BUILD: 20241827 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Install tub in bonus bath
PAUL- have you ordered shower door with black trim?
Missing section of insulation outside of bonus bathtub
Crown Molding Questions (pantry/closet) where does it end?
Few pieces of trim missing in small bedroom
Vinyl strip missing on front of house
Piece of shoe molding missing in upper stairwell
Remove tree behind townhoues
Remove tree behind townhouse
Powder bath light fixture needed Electrician. Bonus bath also.
Needs thermostat
Thermostat needed
Install side splash on hall bathroom countertop. Side splash is sitting on the kitchen counter. Tom
Home Inspection - April 22, 1pm Benjamin
Drywall patching needed in living room Jesus. In process 4/16
All mirrors still needed Paul
Install dishwasher
Paint front door Jesus. Final coat will be completed before final walk-through.
Remove gravel from rear of house
CODED LOCKBOX 4141
Where is the back piece of the basement toilet Jill
Is the mirror too low or the powder bath light fixture too high?
Wrap up final paint touchup before cleaning
Do we need brown electrical covers on the kitchen island?
Hall vanity side splash has been installed so there is an extra one sitting in the kitchen Courtney
Paint frame of exterior doors. Specifically off the patio. Jesus
Pressure wash front and rear of home Buddy said he plans to do this tomorrow 4/29
Snap lights are not soft white but daylight bulbs Electrician
Push refrigerator into place
Few spots of glue in the master shower Lynn - maybe
Push refrigerator into place and hook up water Mazur
Remove large trash cans from in front of 38 to 41 units
Gutter guards needed
bonus bathroom door rubs at the frame Jorge
make sure all interior door edges have been painted Courtney notifed painter
Move dumpster Courtney will call Contain It
Splash blocks needed Front one was in place. One in the back needs an extension, and the one on the side may need a piece of sod cut out? Or maybe an extension and not an actual/block. I will talk to Buddy.
Chip in bathtub Courtney has requested the repair
Transition strip needed from foyer to main level Thu, May 8
Sweep out garage
Screens
clean up debris in rear of the house from tree cutting Buddy knows- he/Jason are doing this week
Replant sod near front of driveway Bob is adding soil in today, and Petit is bringing sod on Wednesday
Fill holes in garage trim near house numbers Marked for Jesus who was coming this evening 4/28
Remove small concrete spots from flashing around garage door These will come off with a pressure washer. Buddy is aware and will do when he was pressuring washing the house. 4/9
Patch and paint blemishes in foyer Blue taped. Jesus completing 4/28
Remove small concrete spots from exterior of rear lower level door Buddy - pressure washer
Adjust screen at basement right side window (or frame?) Courtney, Buddy
Replace door sweep on bottom of door between garage and hallway Jorge completed 4/28
Paint touch up on ceiling when coming own stairs to front door Jesus completing 4/28. I marked with blue tape.
Can the stain on the steps be evened out at all? Jesus says this will be fixed. I will go by in the morning 4/29
Touch up cabinet door to right of oven Courtney- I did this 4/28
Connect water to refrigerator Mazur connected 4/28
Adjust door from dining area to deck so that it is straight and deadbolt will lock Jorge fixed 4/28
Add a screw at the outlet cover that is not attached Courtney fixed it. 4/28
Paint touch up at ceiling over top stairs Jesus- marked with blue tape 4/28
Paint touch up at guest bedroom ceiling Jesus-marked with blue tape
Adjust left master bedroom window so that it will lock Courtney-I need to look at this 4/29
Small drywall spot in smaller bedroom
Small drywall spot in smaller bedroom
Tire tracks in yard Tom-backyard needs more repairs since drain installation
Mop floors
Does the HOA know to mow in 38 to 41? The grass is getting very long.
UPGRADES - COMPLETED
    Finished Bonus Room  
    Finished Bonus Bathroom  
    Expanded Deck- 10 x 18  
    Expanded Patio  
    Expanded Driveway  
    White painted Kitchen Cabinets  
    Level 3 Quartz Kitchen Countertops  
    Microwave vented to exterior  
    Cabinet Crown Moulding  
    Three Drawer Stack in place of B 36"  
    Double Waste Basket in Island  
    White painted cabinets in Bathrooms (includes Bonus)  
    Gardenia LVT in all baths and laundry  
    Oak Treads to Bedroom Level  
    LVP in Bonus Room  
    LVP in Upstairs Hallway  
    Shower Door with black trim in master bath  
    4" Crown moulding on Main Level  
    Amendment to increase price by $35,310  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  10.07.2024    
-- -- $2500 Deposit Received (0)  10.10.2024    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  10.11.2024    
-- -- Selections Meeting (0)  10.14.2024     Requested for week of 10/14
-- -- Selections Sheet Signed (0)  11.05.2024     11/3: sent updated version to Matt
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.07.2024     11/5: sent to Jerry
-- -- Deposit For Upgrades Received (0)  11.06.2024    
-- -- Building Permit (30) *   10.07.2024    
-- -- Order Roof & Floor Trusses (1)  10.17.2024    
-- -- Order Windows & Doors (0)  12.02.2024    
-- -- Stake Out Home (1)  10.14.2024    
-- -- Excavate (2)  10.21.2024    
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Pour Footers (1) *   10.21.2024    
-- -- Set Forms (2)  11.13.2024    
-- -- Pour Foundation Walls (1)  11.13.2024    
-- -- Plumb Slab (2)  11.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.13.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.13.2024    
-- -- Prepare Slab (1)  11.13.2024    
-- -- Inspection (Slab) (1)  11.13.2024    
-- -- Inspection (Drain Tile) (0)  12.02.2024    
-- -- Pour Slab (1) *   11.13.2024    
-- -- Settlement Agent Confirmed (0)  11.09.2024    
-- -- Framing I (9)  11.24.2024    
-- -- Order Steps (0)  12.09.2024    
-- -- Order Tubs / Showers (0)  12.23.2024    
-- -- Framing II (8)  12.02.2024    
-- -- Framing III (8) *   12.19.2024    
-- -- Verify Window & Roof Structure (0)  12.19.2024    
-- -- Install Stairs (0) *   12.23.2024    
-- -- Windows & Doors (0) *   01.05.2025    
-- -- House Number and Status in Window (0)  01.16.2025    
-- -- Roofing (0) *   01.05.2025    
-- -- Order Cabinets (0)  12.31.2024    
-- -- Order Appliances (0)  02.20.2025     order # 200509352240380141
-- -- Deck (0)  03.01.2025     In process 2/26
-- -- Gutters (0)  02.16.2025    
-- -- Driveway (0) *   03.26.2025    
-- -- Patio (0)  03.15.2025    
-- -- Privacy Divider / Fence (0) *   03.15.2025    
-- -- Sod / Seed / Landscaping (0)  04.23.2025     in process 4/19
-- -- HVAC Rough In (4)  01.23.2025     in process 1/15
-- -- Rough In Microwave Vent (0)  01.08.2025    
-- -- Plumbing Rough In (4)  01.30.2025     in process 1/22
-- -- Electric Rough In (4)  02.01.2025    
-- -- Inspection (Rough In HVAC) (1)  02.05.2025    
-- -- Inspection (Rough In Plumbing) (1)  02.05.2025    
-- -- Inspection (Rough In Electric) (1)  02.05.2025    
-- -- Inspection (Framing) (1) *   02.05.2025    
-- -- Inspection (Deck Piers) (0)  02.20.2025    
-- -- Exterior Vinyl (0) *   02.16.2025    
-- -- Exterior Stone (0)  03.12.2025    
-- -- Insulation (2) *   02.08.2025     In process 2/5
-- -- Inspection (Insulation) (1)  02.12.2025    
-- -- Inspection (Electric Service) (0)  02.20.2025    
-- -- Set Electric Meter (0) *   04.09.2025    
-- -- Inspection (Main Sewer Line) (0)  02.20.2025    
-- -- Inspection (Main Water Line) (0)  02.20.2025    
-- -- Order Interior Doors & Trim (0)  01.27.2025     TOM- NEED CROWN MOULDING MAIN FLOOR
-- -- Drywall (Hang) (4) *   02.12.2025    
-- -- Loan Approval (0)  11.20.2024     JoDee @ United Bank (75%)
-- -- Deed Preparation (0)  03.24.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.20.2025    
-- -- Paint 1 (1)  02.26.2025    
-- -- Garage Door (0)  03.12.2025    
-- -- House Numbers (0)  03.22.2025    
-- -- Mailbox (0)  04.16.2025    
-- -- Cabinet Installation (2) *   03.05.2025     Install Tuesday, March 4
-- -- Granite Installation (1) *   03.08.2025    
-- -- Interior Trim - Install (3) *   03.08.2025     Crown Moulding. In process 3/5
-- -- Order Plumbing / Lighting Fixtures (0)  02.17.2025    
-- -- Interior Trim - Paint (1)  03.08.2025    
-- -- Luxury Vinyl Plank (3) *   03.19.2025     In process 3/15
-- -- Luxury Vinyl Tile (0)  03.19.2025     replacing color 3/17
-- -- Paint 2 (3)  03.12.2025    
-- -- Cover Floors (0)  03.19.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.20.2025    
-- -- Shoe Moulding (0)  03.19.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   04.12.2025     In process 4/9
-- -- Install Coded Lockbox (add extra keys) (0)  04.16.2025    
-- -- Pay Water / Sewer Taps (0)  03.03.2025    
-- -- Set Water Meter (1) *   04.09.2025    
-- -- Electric Trim Out (3) *   03.26.2025     In process 3/19
-- -- Ceiling Fans (0)  03.19.2025    
-- -- HVAC Trim Out (1) *   03.26.2025    
-- -- Blower Door Test (1)  04.16.2025    
-- -- Plumbing Trim Out (2) *   03.26.2025     In process 3/22
-- -- Install Appliances (0) *   04.12.2025     Standard Current Date: 3/27
-- -- Paint 3 (2) *   03.28.2025     In process 3/26
-- -- Carpet (2)  03.19.2025    
-- -- Appraiser Confirms Construction Completion (0)  04.24.2025    
-- -- Inspection (Final HVAC) (0)  04.21.2025    
-- -- Inspection (Final Plumbing) (0)  04.21.2025    
-- -- Inspection (Final Electric) (0)  04.21.2025    
-- -- Inspection (Final Building) (4) *   04.21.2025     Fri, Apr 18
-- -- Pre Walk Through (0)  04.24.2025    
-- -- Stain Hardwood Stairs (1) *   04.09.2025     In process 4/6
-- -- Cleaning (1)  04.26.2025    
-- -- Certificate of Occupancy (1) *   04.22.2025    
-- -- C.O. to Lender (0)  04.22.2025    
-- -- Schedule Closing (0)  04.26.2025    
-- -- Buyer Walk Through (1) *   04.26.2025     Thu, Apr 24 at 5PM
-- -- Payment for Upgrades (0)  04.21.2025    
-- -- Keys to Settlement Agent (0)  04.21.2025    
-- -- Review Settlement Statement (0)  04.22.2025    
-- -- Jerry Signs Closing Documents (0)  04.22.2025    
-- -- Request Trash Tote From POA Manager (0)  04.21.2025    
-- -- Closing (1)  04.30.2025     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  05.19.2025