| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| --- | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 12.02.2024 | ||
| -- | -- | Inspection (Concrete Wall) (1) 12.02.2024 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 12.28.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 12.28.2024 | ||
| -- | -- | Inspection (Slab) (1) 12.28.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 02.20.2025 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 04.06.2025 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 04.06.2025 | ||
| -- | -- | Inspection (Rough In Electric) (1) 04.06.2025 | ||
| -- | -- | Inspection (Framing) (1) * 04.06.2025 | ||
| -- | -- | Inspection (Deck Piers) (0) 04.06.2025 | ||
| -- | -- | Inspection (Insulation) (1) 04.14.2025 | 4/10 | |
| -- | -- | Inspection (Electric Service) (0) 04.14.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 04.14.2025 | ||
| -- | -- | Inspection (Main Water Line) (0) 04.14.2025 | ||
| -- | -- | Inspection (Final HVAC) (0) 06.30.2025 | ||
| -- | -- | Inspection (Final Plumbing) (0) 06.30.2025 | ||
| -- | -- | Inspection (Final Electric) (0) 06.30.2025 | ||
| -- | -- | Inspection (Final Building) (4) * 06.30.2025 | Wed, Jun 25 | |