--   --   Replace damaged soffit (small hole) at front of townhouse by gutter Jeremy
--   --   Caulk where front door frame meets metal threshold? Jesus
--   --   Buyers Number- 757-353-9528 HER name is Charlie
--   --   Buyers plan to do a pre-drywall inspection Pause construction after insulation
--   --   PAUSE CONSTRUCTION AFTER INSULATION
--   --   Install bonus bathtub
--   --   Pre Drywall Inspection Wed, Jul 30 at 9AM
--   --   One piece of drywall missing in bonus room
--   --   Patio under deck needs to be expanded In process 8/20
--   --   Vanity hardware needed in the bonus bathroom
--   --   All cabinet hardware needed Fred, QI
--   --   Upstairs hall bathroom vanity is not here In hallway 9/1, Kenny
--   --   Farmhouse sink trim needed White - Jorge
--   --   Courtney owes Jerry $5
--   --   Hardware still needed on vanities Fred
--   --   Cover carpets
--   --   Hall vanity needs a countertop And handles. Countertop is on that needs to be secured.
--   --   Two farmhouse sinks are in this garage
--   --   Few pieces of trim needed near pantry
--   --   Dishwasher needs installed in oven needs to be hooked up to a plug
--   --   Side/needed on hall vanity Tom
--   --   Patch hole in bonus room Jesus
--   --   Bonus fan needs moved from living room to bonus room Electrician
--   --   Raise dining area light by about 18 inches Tom. Swag it.
--   --   Buyer will be doing a home inspection Thu, Oct 16
--   --   Leave ceiling fan in living room Electrician
--   --   Add ceiling fan in bonus room Electrician
--   --   Powder bath mirror needed Paul
--   --   Few lightbulbs needed throughout Electrician
--   --   Large scratches on hall bath vanity On order, Fred
--   --   Put ceiling fan for bonus room light has been installed.
--   --   The farmhouse trim done by Jorge looks really good!
--   --   Clean up the drywall mud or caulk on the exterior of the shower door Lynn
--   --   Towel bar over bonus toilet is crooked Paul
--   --   Look at Kate’s pics of shower door installation Tom - PVC board
--   --   Clean out garage Jill, Lynn
--   --   CODED LOCKBOX 1919
--   --   Some of the steps leading to the upper level, have a really dark stain on the left hand side. Maybe an additional coat of stain will help to cover it? C blue taped
--   --   Caulk in hall side splash Jesus
--   --   Remove paint off luxury vinyl plank Jesus
--   --   Check from buyers for fan $260.00
--   --   Paint front door again Jesus
--   --   I think these steps are gonna need another coat of white paint on the risers Jesus
--   --   Put splash blocks in place
--   --   Adjust deadbolt to lock properly Rear patio, Paul
--   --   Install missing corner pads at front door to limit air infiltration Where door meets jamb, at the bottom
--   --   Secure loose joist fasteners under deck Tom
--   --   Install white PVC board under patio door to deck
--   --   Adjust shingles so that lower flange of vent boot is on top of shingles
--   --   Install filter in air handler
--   --   Secure loose piece of laminate flooring on ground level near stairs Denny
--   --   Tap down hinge pins on interior doors
--   --   Install screens
--   --   Caulk at sink to wall intersection in half bathroom
--   --   Ensure water dispenser and ice maker are working
--   --   Secure loose toilets (two upstairs, main level)
--   --   Caulk where shower meets drywall at upstairs hall bathroom
--   --   Seal around bath and shower fixtures where they meet fiberglass Jesus
--   --   Void in fire wall system at west side wall? Tom
--   --   Adjust cardboard baffles in attic near eaves so that insulation is not blocking soffit ventilation Davenport
--   --   Screens needed
--   --   Paint touchup throughout
--   --   Address hole in coffee cabinet
--   --   Straighten towel bar in master bath Paul
--   --   repair in soffit needed
-- -- Ratified Contract? (0)  01.15.2025    
    Finish Bonus Room  
    Finish Bonus Bath  
    Expanded Patio Under Deck  
    Expanded Driveway  
    White Kitchen Cabinetry  
    Banquette Seating in white with under cabinets  
    Coffee Bar with glass shelving and crown moulding- white paint  
    Farmhouse Sink- white  
    Oak Stairs to Bedroom Level  
    Upgraded Carpet Pad in all carpeted areas  
    Garage Door Opener Keypad  
    Added 3 Ceiling fans- Bonus and Up Bedrooms  
    Eggshell Paint  
    LVP in upstairs hallway  
    Shower Door in Master Bathroom  
    Amendment to increase price by $33,850  
    Add ceiling fan in living room  
-- -- $2500 Deposit Received (0)  03.06.2025    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  01.17.2025    
-- -- Selections Meeting (0)  02.26.2025    
-- -- Selections Sheet Signed (0)  03.05.2025     2/26: sent to Carson
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  03.12.2025     3/11: sent to Jerry
-- -- Deposit For Upgrades Received (0)  03.11.2025    
-- -- Building Permit (30) *   01.25.2025    
-- -- Order Roof & Floor Trusses (1)  04.03.2025    
-- -- Order Windows & Doors (0)  06.16.2025    
-- -- Stake Out Home (1)  03.29.2025    
-- -- Excavate (2)  03.29.2025    
-- -- Inspection (Footers) (1)  03.29.2025    
-- -- Inspection (Concrete Wall) (1)  03.29.2025    
-- -- Pour Footers (1) *   03.29.2025    
-- -- Set Forms (2)  03.29.2025    
-- -- Pour Foundation Walls (1)  03.29.2025    
-- -- Plumb Slab (2)  04.24.2025    
-- -- Inspection (Plumbing Under Slab) (1)  04.24.2025    
-- -- Inspection (Conduit Under Slab) (1)  05.01.2025    
-- -- Prepare Slab (1)  05.01.2025    
-- -- Inspection (Slab) (1)  05.12.2025    
-- -- Inspection (Drain Tile) (0)  05.12.2025    
-- -- Pour Slab (1) *   05.01.2025    
-- -- Settlement Agent Confirmed (0)  03.13.2025     3/11: sent to Brittany
-- -- Framing I (9)  05.27.2025    
-- -- Order Steps (0)  06.16.2025    
-- -- Order Tubs / Showers (0)  06.16.2025    
-- -- Framing II (8)  06.15.2025    
-- -- Framing III (8) *   06.30.2025    
-- -- Verify Window & Roof Structure (0)  07.03.2025    
-- -- Install Stairs (0) *   06.30.2025    
-- -- Windows & Doors (0) *   07.14.2025    
-- -- House Number and Status in Window (0)  07.17.2025    
-- -- Roofing (0) *   07.10.2025    
-- -- Order Cabinets (0)  07.28.2025    
-- -- Order Appliances (0)  08.18.2025    
-- -- Deck (0)  08.06.2025     Standard
-- -- Gutters (0)  09.17.2025    
-- -- Driveway (0) *   09.24.2025    
-- -- Patio (0)  08.23.2025     Expanded 10 x 10
-- -- Privacy Divider / Fence (0) *   09.20.2025     in process 9/17
-- -- Sod / Seed / Landscaping (0)  10.23.2025    
-- -- HVAC Rough In (4)  07.02.2025    
-- -- Rough In Microwave Vent (0)  07.02.2025    
-- -- Plumbing Rough In (4)  07.28.2025     In process 7/16
-- -- Electric Rough In (4)  07.28.2025    
-- -- Inspection (Rough In HVAC) (1)  07.28.2025    
-- -- Inspection (Rough In Plumbing) (1)  07.28.2025    
-- -- Inspection (Rough In Electric) (1)  07.28.2025    
-- -- Inspection (Framing) (1) *   07.28.2025    
-- -- Inspection (Deck Piers) (0)  08.04.2025    
-- -- Exterior Vinyl (0) *   09.10.2025    
-- -- Exterior Stone (0)  09.08.2025    
-- -- Insulation (2) *   08.03.2025     In process 7/30
-- -- Inspection (Insulation) (1)  08.04.2025    
-- -- Inspection (Electric Service) (0)  08.14.2025    
-- -- Set Electric Meter (0) *   09.16.2025    
-- -- Inspection (Main Sewer Line) (0)  08.14.2025    
-- -- Inspection (Main Water Line) (0)  08.14.2025    
-- -- Order Interior Doors & Trim (0)  07.31.2025    
-- -- Drywall (Hang) (4) *   08.03.2025    
-- -- Loan Approval (0)  10.20.2025     JoDee @ United (85% Conventional)
-- -- Deed Preparation (0)  09.26.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.13.2025     In process 8/6
-- -- Paint 1 (1)  08.13.2025    
-- -- Garage Door (0)  08.20.2025    
-- -- House Numbers (0)  09.29.2025    
-- -- Mailbox (0)  09.08.2025    
-- -- Cabinet Installation (2) *   08.23.2025     Delivery 8/20, Install 8/21. In process 8/20
-- -- Granite Installation (1) *   09.13.2025     Installing Sep 9
-- -- Interior Trim - Install (3) *   08.20.2025     In process 8/16
-- -- Order Plumbing / Lighting Fixtures (0)  08.21.2025    
-- -- Interior Trim - Paint (1)  09.03.2025    
-- -- Luxury Vinyl Plank (3) *   09.06.2025    
-- -- Luxury Vinyl Tile (0)  09.03.2025    
-- -- Paint 2 (3)  09.20.2025     In process 9/17
-- -- Cover Floors (1)  09.13.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  08.28.2025    
-- -- Shoe Moulding (0)  09.13.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   10.01.2025     In process 9/24
-- -- Install Coded Lockbox (add extra keys) (0)  10.08.2025    
-- -- Pay Water / Sewer Taps (0)  09.04.2025    
-- -- Set Water Meter (0) *   10.07.2025     Mon, Oct 6 or Tue, Oct 7
-- -- Electric Trim Out (3) *   10.06.2025     In process 9/26
-- -- Ceiling Fans (0)  09.26.2025    
-- -- HVAC Trim Out (1) *   10.08.2025     Tue, Oct 7
-- -- Blower Door Test (1)  10.13.2025    
-- -- Plumbing Trim Out (2) *   09.26.2025    
-- -- Install Appliances (0) *   09.20.2025     Standard Current Date: 7/30
-- -- Paint 3 (2) *   09.26.2025    
-- -- Carpet (2)  09.13.2025    
-- -- Appraiser Confirms Construction Completion (0)  10.20.2025    
-- -- Inspection (Final HVAC) (1)  10.13.2025    
-- -- Inspection (Final Plumbing) (1)  10.13.2025    
-- -- Inspection (Final Electric) (1)  10.13.2025    
-- -- Inspection (Final Building) (2) *   10.20.2025     Thu, Oct 16
-- -- Pre Walk Through (0)  10.20.2025    
-- -- Stain Hardwood Stairs (1) *   10.13.2025     One coat still needed 10/8
-- -- Cleaning (1)  10.20.2025     In process 10/11
-- -- Certificate of Occupancy (1) *   10.22.2025    
-- -- C.O. to Lender (0)  10.22.2025    
-- -- Schedule Closing (0)  10.22.2025    
-- -- Buyer Walk Through (1) *   10.23.2025     Mon, Oct 20, 10:30 AM
-- -- Payment for Upgrades (0)  10.20.2025    
-- -- Keys to Settlement Agent (0)  10.13.2025    
-- -- Review Settlement Statement (0)  10.21.2025    
-- -- Jerry Signs Closing Documents (0)  08.27.2025    
-- -- Request Trash Tote From POA Manager (0)  10.15.2025    
-- -- Closing (1)  10.23.2025     Brittany @ West View Title (Oct 21)
-- -- Remove Coded Lockbox (0)  10.27.2025