CONGERS-3 - 30  ::  1416 Derby Drive
[ BUILD: 20250228 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Friday (Oct 31)    show all photos
--   --   Primary door framing issue bedroom
    Microwave vented to Exterior  
Sun    Nov 2      Patio (0)       Standard
Sun    Nov 2      Privacy Divider / Fence (0) *       
Sun    Nov 2      Sod / Seed / Landscaping (0)      
Sun    Nov 2      Inspection (Deck Piers) (0)      
Sun    Nov 2      Loan Approval (0)  03.05.2025     JoDee @ United (80% Conventional)
Sun    Nov 2      Deed Preparation (0)      
Sun    Nov 2      House Numbers (0)      
Sun    Nov 2      Mailbox (0)      
Sun    Nov 2      Interior Trim - Install (3) *   10.31.2025     In process 10/31
Wed    Nov 5      Interior Trim - Paint (1)      
Thu    Nov 6      Luxury Vinyl Plank (3) *       
Tue    Nov 11      Luxury Vinyl Tile (0)      
Tue    Nov 11      Paint 2 (3)      
Fri    Nov 14      Cover Floors (1)      
Mon    Nov 17      Shoe Moulding (0)      
Mon    Nov 17      Shelving, Door Knobs, Fire Extinguisher (0) *       
Mon    Nov 17      Install Coded Lockbox (add extra keys) (0)      
Mon    Nov 17      Pay Water / Sewer Taps (0)      
Mon    Nov 17      Set Water Meter (0) *       
Mon    Nov 17      Electric Trim Out (3) *       
Thu    Nov 20      Ceiling Fans (0)      
Thu    Nov 20      HVAC Trim Out (1) *       
Fri    Nov 21      Blower Door Test (1)      
Mon    Nov 24      Plumbing Trim Out (2) *       
Wed    Nov 26      Install Appliances (0) *        Delivery set for 11/20
Wed    Nov 26      Paint 3 (2) *       
Fri    Nov 28      Carpet (2)      
Tue    Dec 2      Appraiser Confirms Construction Completion (0)      
Tue    Dec 2      Inspection (Final HVAC) (1)      
Wed    Dec 3      Inspection (Final Plumbing) (1)      
Thu    Dec 4      Inspection (Final Electric) (1)      
Fri    Dec 5      Inspection (Final Building) (2) *       
Tue    Dec 9      Pre Walk Through (0)      
Tue    Dec 9      Stain Hardwood Stairs (1) *       
Wed    Dec 10      Cleaning (1)      
Thu    Dec 11      Certificate of Occupancy (1) *       
Fri    Dec 12      C.O. to Lender (0)      
Fri    Dec 12      Schedule Closing (0)      
Fri    Dec 12      Buyer Walk Through (1) *       
Mon    Dec 15      Payment for Upgrades (0)      
Mon    Dec 15      Keys to Settlement Agent (0)      
Mon    Dec 15      Review Settlement Statement (0)      
Mon    Dec 15      Request Trash Tote From POA Manager (0)      
Mon    Dec 15      Closing (1)      
Tue    Dec 16      Remove Coded Lockbox (0)      
--   --   the dormer window needs to be moved to unit 31
--   --   Move tub in bonus bath
--   --   Expanded Driveway! Can it be added?
--   --   Amendment for upgraded driveway
--   --   Upper dormer windows need installed
--   --   Front dormer windows that need to be installed are in this bonus room
--   --   All bathtubs need to have plumbing rough in completed
--   --   Buyer will be doing a home inspection
--   --   Install side splash in the primary bathroom
--   --   Drywall needed on primary bedroom door
-- -- Ratified Contract? (0)  02.12.2025    
    Finished Bonus Room  
    Finished Bonus Bathroom  
    Expanded Driveway  
    Amendment to increase price by $18,170  
-- -- $2500 Deposit Received (0)  02.15.2025    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  02.15.2025    
-- -- Selections Meeting (0)  03.28.2025     10:30 AM 11/27
-- -- Selections Sheet Signed (0)  04.04.2025     3/27: sent to Luke
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.18.2025     9/15: sent updated version to Luke
-- -- Deposit For Upgrades Received (0)  04.08.2025    
-- -- Building Permit (30) *   01.31.2025    
-- -- Order Roof & Floor Trusses (1)  08.04.2025    
-- -- Order Windows & Doors (0)  08.04.2025    
-- -- Stake Out Home (1)  03.29.2025    
-- -- Excavate (2)  03.29.2025    
-- -- Inspection (Footers) (1)  04.07.2025    
-- -- Inspection (Concrete Wall) (1)  05.15.2025    
-- -- Pour Footers (1) *   04.07.2025    
-- -- Set Forms (2)  05.15.2025    
-- -- Pour Foundation Walls (1)  05.15.2025    
-- -- Plumb Slab (2)  05.15.2025    
-- -- Inspection (Plumbing Under Slab) (1)  06.05.2025    
-- -- Inspection (Conduit Under Slab) (1)  06.05.2025    
-- -- Prepare Slab (1)  06.05.2025    
-- -- Inspection (Slab) (1)  07.31.2025    
-- -- Inspection (Drain Tile) (0)  07.22.2025    
-- -- Pour Slab (1) *   06.08.2025    
-- -- Settlement Agent Confirmed (0)  04.16.2025     4/9: sent to Brittany
-- -- Framing I (9)  07.31.2025    
-- -- Order Steps (0)  08.04.2025    
-- -- Order Tubs / Showers (0)  08.14.2025    
-- -- Framing II (8)  08.07.2025    
-- -- Framing III (8) *   08.11.2025    
-- -- Verify Window & Roof Structure (0)  08.14.2025    
-- -- Install Stairs (0) *   08.18.2025    
-- -- Windows & Doors (0) *   08.25.2025    
-- -- House Number and Status in Window (0)  09.04.2025    
-- -- Roofing (0) *   08.25.2025    
-- -- Order Cabinets (0)  08.19.2025    
-- -- Order Appliances (0)  10.27.2025    
-- -- Deck (0)  10.04.2025     Standard
-- -- Gutters (0)  10.20.2025    
-- -- Driveway (0) *   09.03.2025    
-- -- HVAC Rough In (4)  08.23.2025    
-- -- Rough In Microwave Vent (0)  09.01.2025    
-- -- Plumbing Rough In (4)  09.17.2025     In process 9/3
-- -- Electric Rough In (4)  09.13.2025     In process 9/10
-- -- Inspection (Rough In HVAC) (1)  09.18.2025    
-- -- Inspection (Rough In Plumbing) (1)  09.18.2025    
-- -- Inspection (Rough In Electric) (1)  09.18.2025    
-- -- Inspection (Framing) (1) *   09.18.2025    
-- -- Exterior Vinyl (0) *   10.19.2025    
-- -- Exterior Stone (0)  09.08.2025    
-- -- Insulation (2) *   09.20.2025    
-- -- Inspection (Insulation) (1)  09.25.2025    
-- -- Inspection (Electric Service) (0)  10.06.2025    
-- -- Set Electric Meter (0) *   10.27.2025    
-- -- Inspection (Main Sewer Line) (0)  08.14.2025    
-- -- Inspection (Main Water Line) (0)  08.14.2025    
-- -- Order Interior Doors & Trim (0)  10.23.2025    
-- -- Drywall (Hang) (4) *   10.04.2025     In process 9/26
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   10.11.2025     In process 10/8. Final sanding.
-- -- Paint 1 (1)  10.15.2025     In process 10/11
-- -- Garage Door (0)  10.15.2025    
-- -- Cabinet Installation (2) *   10.15.2025     Oct 15
-- -- Granite Installation (1) *   10.25.2025     Fri, Oct 24
-- -- Order Plumbing / Lighting Fixtures (0)  10.16.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  10.27.2025    
-- -- Jerry Signs Closing Documents (0)  08.27.2025