CONGERS-3 - 30  ::  1416 Derby Drive
[ BUILD: 20250228 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
Install patio screen doors Tom - on order
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
the dormer window needs to be moved to unit 31
Move tub in bonus bath
Expanded Driveway! Can it be added?
Amendment for upgraded driveway
Upper dormer windows need installed
Front dormer windows that need to be installed are in this bonus room
All bathtubs need to have plumbing rough in completed
Buyer will be doing a home inspection
Install side splash in the primary bathroom
Drywall needed on primary bedroom door
Primary door framing issue bedroom Jesus
Cover carpet
Cover carpet upstairs
Shoe molding Is needed in the bonus bathroom Jorge
Quite a bit of paint needs to be cleaned off the basement bonus bathroom vanity Jesus
Full set of appliances in this kitchen
Paint 2 does still need to be completed in the hallway
Home Inspection - Tuesday, Dec 16 at 1PM
Bonus room light fixture is broken Electrician. New one on floor. 12/13
Brown receptacles needed in kitchen island Jill
Granite soda stain Jill. I think gone? Jill’s magic.
Light bulbs needed in a few places, cable covers need to be installed?
Lots of white scuffing around the corner of the kitchen island. Perhaps it will come off with cleaning? Jill
Light fixtures in hallway are upside down Electrician
Significant coffee staining on the upstairs banister. Hoping painters can repair?
Trying to close on Dec 19 at 9AM
Repair rear exterior vent outlet (protruding) Greg, Jill
Install missing interior door knobs
Add PVC board under rear deck exterior door
Install door stop on front exterior door
Repair drywall behind door
Replace damaged wood on rear deck Tom
Install handle and latch at kitchen pantry pocket door
Turn on and test refrigerator ice maker
Secure loose toilet in bonus room bathroom
Repair hole in primary bathroom shower Jill coordinating, Wed, Dec 24
Repair broken roof trusses
Add more insulation in attic
Paint touch ups throughout A lot of blue tape still remains 12/24
Install cabinet shelf that sitting on the top of the cabinets Jill
Few bath accessories are missing. Lynn said, shoving folks said they would be going in tomorrow.
CODED LOCKBOX 3030
Straighten chandelier Electrician
Clean out garage Just needs to have a small dust pile cleaned up, Jill
Secure tub faucet to wall in bonus bathroom Munzure
Clean paint off of LVP at landing Jesus
Caulk at pedestal sink in half bathroom
Paint touch up throughout
Clean off scuffs on kitchen cabinets Jill
Remove gum (?) from upstairs hallway carpet Jill, Eric, Denny
Whiteboard needed off of patio door Tom
All these driveways really need to be pressure washed or at least swept Tom
Please turn off lights when leaving property as utilities are now in buyer’s name
Repairs needed to hallway, bathroom light fixture?
Second coat of paint needed on this front door
Adjust front door to close more easily Tom
SR Jan 15 (19) Can we swap out the bathroom fans for flush mount fans? Jill will ask Mast & Brunk
SR Jan 13 (21) Patch, sand and paint at hall bathroom light fixture Jesus
UPGRADES - COMPLETED
    Finished Bonus Room  
    Finished Bonus Bathroom  
    Microwave vented to Exterior  
    Expanded Driveway  
    Amendment to increase price by $18,170  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  02.12.2025    
-- -- $2500 Deposit Received (0)  02.15.2025    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  02.15.2025    
-- -- Selections Meeting (0)  03.28.2025     10:30 AM 11/27
-- -- Selections Sheet Signed (0)  04.04.2025     3/27: sent to Luke
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.18.2025     9/15: sent updated version to Luke
-- -- Deposit For Upgrades Received (0)  04.08.2025    
-- -- Building Permit (30) *   01.31.2025    
-- -- Order Roof & Floor Trusses (1)  08.04.2025    
-- -- Order Windows & Doors (0)  08.04.2025    
-- -- Stake Out Home (1)  03.29.2025    
-- -- Excavate (2)  03.29.2025    
-- -- Inspection (Footers) (1)  04.07.2025    
-- -- Inspection (Concrete Wall) (1)  05.15.2025    
-- -- Pour Footers (1) *   04.07.2025    
-- -- Set Forms (2)  05.15.2025    
-- -- Pour Foundation Walls (1)  05.15.2025    
-- -- Plumb Slab (2)  05.15.2025    
-- -- Inspection (Plumbing Under Slab) (1)  06.05.2025    
-- -- Inspection (Conduit Under Slab) (1)  06.05.2025    
-- -- Prepare Slab (1)  06.05.2025    
-- -- Inspection (Slab) (1)  07.31.2025    
-- -- Inspection (Drain Tile) (0)  07.22.2025    
-- -- Pour Slab (1) *   06.08.2025    
-- -- Settlement Agent Confirmed (0)  04.16.2025     4/9: sent to Brittany
-- -- Framing I (9)  07.31.2025    
-- -- Order Steps (0)  08.04.2025    
-- -- Order Tubs / Showers (0)  08.14.2025    
-- -- Framing II (8)  08.07.2025    
-- -- Framing III (8) *   08.11.2025    
-- -- Verify Window & Roof Structure (0)  08.14.2025    
-- -- Install Stairs (0) *   08.18.2025    
-- -- Windows & Doors (0) *   08.25.2025    
-- -- House Number and Status in Window (0)  09.04.2025    
-- -- Roofing (0) *   08.25.2025    
-- -- Order Cabinets (0)  08.19.2025    
-- -- Order Appliances (0)  10.27.2025    
-- -- Deck (0)  10.04.2025     Standard
-- -- Gutters (0)  10.20.2025    
-- -- Driveway (0) *   09.03.2025    
-- -- Patio (0)  11.15.2025     Standard
-- -- Privacy Divider / Fence (0) *   12.10.2025    
-- -- Sod / Seed / Landscaping (0)  12.24.2025    
-- -- HVAC Rough In (4)  08.23.2025    
-- -- Rough In Microwave Vent (0)  09.01.2025    
-- -- Plumbing Rough In (4)  09.17.2025     In process 9/3
-- -- Electric Rough In (4)  09.13.2025     In process 9/10
-- -- Inspection (Rough In HVAC) (1)  09.18.2025    
-- -- Inspection (Rough In Plumbing) (1)  09.18.2025    
-- -- Inspection (Rough In Electric) (1)  09.18.2025    
-- -- Inspection (Framing) (1) *   09.18.2025    
-- -- Inspection (Deck Piers) (0)  11.10.2025    
-- -- Exterior Vinyl (0) *   10.19.2025    
-- -- Exterior Stone (0)  09.08.2025    
-- -- Insulation (2) *   09.20.2025    
-- -- Inspection (Insulation) (1)  09.25.2025    
-- -- Inspection (Electric Service) (0)  10.06.2025    
-- -- Set Electric Meter (0) *   10.27.2025    
-- -- Inspection (Main Sewer Line) (0)  08.14.2025    
-- -- Inspection (Main Water Line) (0)  08.14.2025    
-- -- Order Interior Doors & Trim (0)  10.23.2025    
-- -- Drywall (Hang) (4) *   10.04.2025     In process 9/26
-- -- Loan Approval (0)  12.15.2025     JoDee @ United (80% Conventional)
-- -- Deed Preparation (0)  11.18.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   10.11.2025     In process 10/8. Final sanding.
-- -- Paint 1 (1)  10.15.2025     In process 10/11
-- -- Garage Door (0)  10.15.2025    
-- -- House Numbers (0)  11.15.2025    
-- -- Mailbox (0)  11.24.2025    
-- -- Cabinet Installation (2) *   10.15.2025     Oct 15
-- -- Granite Installation (1) *   10.25.2025     Fri, Oct 24
-- -- Interior Trim - Install (3) *   11.05.2025     In process 10/31
-- -- Order Plumbing / Lighting Fixtures (0)  10.16.2025    
-- -- Interior Trim - Paint (1)  11.08.2025     Painting 11/5
-- -- Luxury Vinyl Plank (3) *   11.12.2025    
-- -- Luxury Vinyl Tile (0)  11.12.2025    
-- -- Paint 2 (3)  11.22.2025    
-- -- Cover Floors (0)  11.22.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  10.27.2025    
-- -- Shoe Moulding (0)  11.22.2025     In process 11/19
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   12.20.2025    
-- -- Install Coded Lockbox (add extra keys) (0)  12.17.2025    
-- -- Pay Water / Sewer Taps (0)  11.10.2025    
-- -- Set Water Meter (1) *   12.01.2025    
-- -- Electric Trim Out (3) *   12.13.2025     In process 12/10
-- -- Ceiling Fans (0)  12.13.2025    
-- -- HVAC Trim Out (1) *   11.22.2025    
-- -- Blower Door Test (1)  12.16.2025    
-- -- Plumbing Trim Out (2) *   12.10.2025     Completed except for small fixture on hall bathroom. And the completion of installing the dishwasher.
-- -- Install Appliances (0) *   12.16.2025     Delivery set for 11/20. Full set of appliances are in the kitchen.
-- -- Paint 3 (2) *   12.16.2025    
-- -- Carpet (2)  11.15.2025     In process 11/12
-- -- Appraiser Confirms Construction Completion (0)  12.19.2025    
-- -- Inspection (Final HVAC) (0)  12.16.2025    
-- -- Inspection (Final Plumbing) (0)  12.16.2025    
-- -- Inspection (Final Electric) (0)  12.16.2025    
-- -- Inspection (Final Building) (4) *   12.16.2025    
-- -- Pre Walk Through (0)  12.18.2025    
-- -- Stain Hardwood Stairs (1) *   12.17.2025    
-- -- Cleaning (1)  12.20.2025    
-- -- Certificate of Occupancy (1) *   12.18.2025    
-- -- C.O. to Lender (0)  12.18.2025    
-- -- Schedule Closing (0)  12.18.2025    
-- -- Buyer Walk Through (1) *   12.19.2025    
-- -- Payment for Upgrades (0)  12.15.2025    
-- -- Keys to Settlement Agent (0)  12.15.2025    
-- -- Review Settlement Statement (0)  12.17.2025    
-- -- Jerry Signs Closing Documents (0)  08.27.2025    
-- -- Request Trash Tote From POA Manager (0)  12.16.2025    
-- -- Closing (1)  12.20.2025     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  01.08.2026