| TO DO |
|
|
CODED LOCKBOX 3131 |
|
|
| SR |
Jan 5 (29) |
Install patio door screens |
Tom (on order) |
|
|
| UPGRADES |
| --- |
|
| CRITICAL PATH |
| --- |
|
| TO DO - COMPLETED OR DELETED |
|
|
Selections sheet says gardenia LVT but it’s STANDARD |
Please install standard |
|
|
|
POTENTIALLY - NO EXPANDED DRIVEWAY |
Ask Scott for details |
|
|
|
POTENTIALLY - NO VENTED MICROWAVE |
Ask Scott for details |
|
|
|
It appears that the Ruffin microwave vent and the plumbing pipes, may have a situation |
|
|
|
|
Install top dormer windows |
|
|
|
|
Cabinets are on site but drywall has not been sanded |
|
|
|
|
This house appears to have a free three drawer stack as well, but one of the drawers does not function properly |
Fred |
|
|
|
Primary door framing issue |
Jorge looking for drywall |
|
|
|
Spraying doors/trim 10/29 |
|
|
|
|
Granite stain |
|
|
|
|
Cover carpet 11/12 |
|
|
|
|
Full set of appliances in the kitchen |
|
|
|
|
Some doors may need to be trimmed now that carpet is installed |
Jorge |
|
|
|
She molding is still needed in the primary bathroom |
Jorge |
|
|
|
One small plumbing, trim out piece needed in the hall bathroom over the drain |
Overflow - plumber |
|
|
|
Quite a few middle door hinges need to be put back on |
Jesus |
|
|
|
Is there always this much cord behind the pedestal sink? |
Plumber |
|
|
|
Lid to the hall bathroom toilet is needed |
Plumber |
|
|
|
Closet doors in bedroom need hardware at the top |
Joe, Paul |
|
|
|
Whiteboard needed on back deck and patio |
Tom. Just patio 12/20 |
|
|
|
Weatherstripping needed on front door |
Jill |
|
|
|
White electrical outlets need to be switched out with brown |
kitchen island |
|
|
|
Extra ceiling fan and the floor of the primary bedroom |
|
|
|
|
My fire alarm over slightly to cover hole on main level |
|
|
|
|
Scuffing on vinyl near front door |
Jill |
|
|
|
Remove broken patio doors from garage and possibly broken ceiling fan? |
Jill |
|
|
|
Install primary bathroom shower bar that is in closet |
Joe, Paul |
|
|
|
Move fire alarm over slightly to cover hole on main level |
|
|
|
|
Patch drywall at main level smoke detector |
Jesus |
|
|
|
Light fixture in main level bathroom has exposed screws and holes |
Final paint touchup. Powder bath |
|
|
|
Main level bathroom missing mirror |
|
|
|
|
Second coat of paint is also needed on this front door |
|
|
|
|
Touchup paint still needed |
|
|
|
|
All mirrors and shelving still needed |
|
|
| SR |
Jan 5 (29) |
Paint touch up |
Jesus |
|
| SR |
Jan 5 (29) |
Sand and paint tray ceiling |
Jesus |
|
| SR |
Jan 5 (29) |
Secure handrail going to third floor |
Jorge |
|
| SR |
Jan 5 (29) |
Repaint handrails and banisters |
Jesus |
|
| SR |
Jan 5 (29) |
First floor closet needs another coat of paint |
Jesus |
|
| CL |
Jan 7 (27) |
Clean marks near the front door on vinyl |
|
|
| CL |
Jan 7 (27) |
Few paint touchups needed |
Jesus |
|
| SR |
Jan 5 (29) |
Clean garage floor |
Jill |
|
| LR |
Jan 14 (20) |
Remove nail from ceiling by closet |
|
|
| LR |
Jan 14 (20) |
Remove nail from ceiling by closet & touchup paint |
Touch up paint - Jesus |
|
| SR |
Jan 5 (29) |
Clean mud off of carpet |
Jill (stairs) |
|
| SR |
Jan 5 (29) |
Touch up stair risers |
Jesus |
|
| SR |
Jan 5 (29) |
Caulk around dryer vent at wall in laundry room |
Jesus |
|
|
| UPGRADES - COMPLETED |
| |
|
Expanded Driveway
|
|
| |
|
Microwave vented to exterior
|
|
| |
|
Amendment to increase price by $1,890
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Ratified Contract? (0) 02.12.2025 |
|
|
| -- |
-- |
$2500 Deposit Received (0) 02.21.2025 |
|
|
| -- |
-- |
Association Packet Requested (0) 06.30.2025 |
|
|
| -- |
-- |
Association Packet Received (0) 02.15.2025 |
|
|
| -- |
-- |
Selections Meeting (0) 05.20.2025 |
waiting on buyer- father just passed away |
|
| -- |
-- |
Selections Sheet Signed (0) 05.29.2025 |
5/19: sent to Kozhin |
|
| -- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 07.28.2025 |
7/27: sent to Jerry |
|
| -- |
-- |
Deposit For Upgrades Received (0) 05.29.2025 |
|
|
| -- |
-- |
Building Permit (30) * 01.31.2025 |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) 08.04.2025 |
|
|
| -- |
-- |
Order Windows & Doors (0) 08.04.2025 |
|
|
| -- |
-- |
Stake Out Home (1) 03.29.2025 |
|
|
| -- |
-- |
Excavate (2) 03.29.2025 |
|
|
| -- |
-- |
Inspection (Footers) (1) 04.07.2025 |
|
|
| -- |
-- |
Inspection (Concrete Wall) (1) 05.15.2025 |
|
|
| -- |
-- |
Pour Footers (1) * 04.07.2025 |
|
|
| -- |
-- |
Set Forms (2) 05.15.2025 |
|
|
| -- |
-- |
Pour Foundation Walls (1) 05.15.2025 |
|
|
| -- |
-- |
Plumb Slab (2) 05.15.2025 |
|
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) 06.08.2025 |
|
|
| -- |
-- |
Inspection (Conduit Under Slab) (1) 06.08.2025 |
|
|
| -- |
-- |
Prepare Slab (1) 06.08.2025 |
|
|
| -- |
-- |
Inspection (Slab) (1) 07.31.2025 |
|
|
| -- |
-- |
Inspection (Drain Tile) (0) 07.22.2025 |
|
|
| -- |
-- |
Pour Slab (1) * 06.08.2025 |
|
|
| -- |
-- |
Settlement Agent Confirmed (0) 07.29.2025 |
7/28: sent to WVT |
|
| -- |
-- |
Framing I (9) 07.31.2025 |
|
|
| -- |
-- |
Order Steps (0) 08.04.2025 |
|
|
| -- |
-- |
Order Tubs / Showers (0) 08.14.2025 |
|
|
| -- |
-- |
Framing II (8) 08.07.2025 |
|
|
| -- |
-- |
Framing III (8) * 08.11.2025 |
|
|
| -- |
-- |
Verify Window & Roof Structure (0) 08.14.2025 |
|
|
| -- |
-- |
Install Stairs (0) * 08.18.2025 |
|
|
| -- |
-- |
Windows & Doors (0) * 08.25.2025 |
|
|
| -- |
-- |
House Number and Status in Window (0) 09.04.2025 |
|
|
| -- |
-- |
Roofing (0) * 08.25.2025 |
|
|
| -- |
-- |
Order Cabinets (0) 08.19.2025 |
|
|
| -- |
-- |
Order Appliances (0) 10.27.2025 |
|
|
| -- |
-- |
Deck (0) 09.26.2025 |
|
|
| -- |
-- |
Gutters (0) 10.20.2025 |
|
|
| -- |
-- |
Driveway (0) * 09.03.2025 |
|
|
| -- |
-- |
Patio (0) 11.15.2025 |
|
|
| -- |
-- |
Privacy Divider / Fence (0) * 12.10.2025 |
|
|
| -- |
-- |
Sod / Seed / Landscaping (0) 12.24.2025 |
|
|
| -- |
-- |
HVAC Rough In (4) 09.03.2025 |
In process 8/27 |
|
| -- |
-- |
Rough In Microwave Vent (0) 09.03.2025 |
|
|
| -- |
-- |
Plumbing Rough In (4) 09.06.2025 |
in process 8/27 |
|
| -- |
-- |
Electric Rough In (4) 09.13.2025 |
In process 9/10 |
|
| -- |
-- |
Inspection (Rough In HVAC) (1) 09.13.2025 |
|
|
| -- |
-- |
Inspection (Rough In Plumbing) (1) 09.13.2025 |
|
|
| -- |
-- |
Inspection (Rough In Electric) (1) 09.13.2025 |
|
|
| -- |
-- |
Inspection (Framing) (1) * 09.13.2025 |
|
|
| -- |
-- |
Inspection (Deck Piers) (0) 11.10.2025 |
|
|
| -- |
-- |
Exterior Vinyl (0) * 10.19.2025 |
|
|
| -- |
-- |
Exterior Stone (0) 09.08.2025 |
|
|
| -- |
-- |
Insulation (2) * 09.17.2025 |
In process 9/13 |
|
| -- |
-- |
Inspection (Insulation) (1) 09.18.2025 |
|
|
| -- |
-- |
Inspection (Electric Service) (0) 10.06.2025 |
|
|
| -- |
-- |
Set Electric Meter (0) * 10.27.2025 |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) 08.14.2025 |
|
|
| -- |
-- |
Inspection (Main Water Line) (0) 08.14.2025 |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) 10.23.2025 |
|
|
| -- |
-- |
Drywall (Hang) (4) * 09.20.2025 |
Stocked 9/17 |
|
| -- |
-- |
Loan Approval (0) 12.23.2025 |
Kozhin @ Nexa (85% Conventional) |
|
| -- |
-- |
Deed Preparation (0) 10.23.2025 |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.08.2025 |
In process 10/4 |
|
| -- |
-- |
Paint 1 (1) 10.08.2025 |
|
|
| -- |
-- |
Garage Door (0) 10.15.2025 |
|
|
| -- |
-- |
House Numbers (0) 11.17.2025 |
|
|
| -- |
-- |
Mailbox (0) 11.23.2025 |
|
|
| -- |
-- |
Cabinet Installation (2) * 10.11.2025 |
Tue, Oct 7 |
|
| -- |
-- |
Granite Installation (1) * 10.25.2025 |
Fri, Oct 24 |
|
| -- |
-- |
Interior Trim - Install (3) * 10.25.2025 |
In process 10/22 |
|
| -- |
-- |
Order Plumbing / Lighting Fixtures (0) 10.16.2025 |
|
|
| -- |
-- |
Interior Trim - Paint (1) 10.31.2025 |
In process 10/29 |
|
| -- |
-- |
Luxury Vinyl Plank (3) * 11.12.2025 |
|
|
| -- |
-- |
Luxury Vinyl Tile (0) 11.08.2025 |
|
|
| -- |
-- |
Paint 2 (3) 11.28.2025 |
|
|
| -- |
-- |
Cover Floors (0) 11.23.2025 |
|
|
| -- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 10.27.2025 |
|
|
| -- |
-- |
Shoe Moulding (0) 11.23.2025 |
|
|
| -- |
-- |
Shelving, Door Knobs, Fire Extinguisher (1) * 01.04.2026 |
Shelving and mirrors are still needed 12/24 |
|
| -- |
-- |
Install Coded Lockbox (add extra keys) (0) 12.17.2025 |
|
|
| -- |
-- |
Pay Water / Sewer Taps (0) 11.10.2025 |
|
|
| -- |
-- |
Set Water Meter (1) * 12.01.2025 |
|
|
| -- |
-- |
Electric Trim Out (3) * 12.16.2025 |
In process 12/13 |
|
| -- |
-- |
Ceiling Fans (0) 12.17.2025 |
|
|
| -- |
-- |
HVAC Trim Out (1) * 12.11.2025 |
|
|
| -- |
-- |
Blower Door Test (1) 12.16.2025 |
|
|
| -- |
-- |
Plumbing Trim Out (2) * 11.28.2025 |
|
|
| -- |
-- |
Install Appliances (0) * 12.16.2025 |
Delivery set 11/20 |
|
| -- |
-- |
Paint 3 (2) * 12.03.2025 |
|
|
| -- |
-- |
Carpet (2) 11.12.2025 |
|
|
| -- |
-- |
Appraiser Confirms Construction Completion (0) 01.04.2026 |
|
|
| -- |
-- |
Inspection (Final HVAC) (0) 12.16.2025 |
|
|
| -- |
-- |
Inspection (Final Plumbing) (0) 12.16.2025 |
|
|
| -- |
-- |
Inspection (Final Electric) (0) 12.16.2025 |
|
|
| -- |
-- |
Inspection (Final Building) (4) * 12.16.2025 |
|
|
| -- |
-- |
Pre Walk Through (0) 01.02.2026 |
|
|
| -- |
-- |
Stain Hardwood Stairs (1) * 12.20.2025 |
|
|
| -- |
-- |
Cleaning (1) 12.24.2025 |
In process 12/20 |
|
| -- |
-- |
Certificate of Occupancy (1) * 12.19.2025 |
|
|
| -- |
-- |
C.O. to Lender (0) 12.19.2025 |
|
|
| -- |
-- |
Schedule Closing (0) 01.13.2026 |
|
|
| -- |
-- |
Buyer Walk Through (1) * 01.02.2026 |
Mon, Dec 29 at 10:30 AM |
|
| -- |
-- |
Payment for Upgrades (0) 12.23.2025 |
|
|
| -- |
-- |
Keys to Settlement Agent (0) 12.23.2025 |
|
|
| -- |
-- |
Review Settlement Statement (0) 01.07.2026 |
|
|
| -- |
-- |
Jerry Signs Closing Documents (0) 01.09.2026 |
|
|
| -- |
-- |
Request Trash Tote From POA Manager (0) 12.16.2025 |
|
|
| -- |
-- |
Closing (1) 01.19.2026 |
Brittany @ West View Title (Fri, Jan 16) |
|
| -- |
-- |
Remove Coded Lockbox (0) 01.25.2026 |
|
|