CONGERS-3 - 15  ::  1389 Derby Drive
[ BUILD: 20250703 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Friday (Oct 31)    show all photos
--   --   Farmhouse trim is going to be needed around sink Burlap - Jorge
--   --   Piece of backsplash is missing on kitchen countertops Fenco
--   --   Dent in the fridge door near the handle Kate is working on a replacement
--   --   Few painting repairs needed in back bonus room
--   --   Brown electrical outlets needed for kitchen is Island
--   --   Trim basement doors that rub carpet
--   --   Drywall in garage
--   --   Bonus bath light fixture still needed. Bonus room light is not working.
--   --   Holes will need patched on the side of the shower walls where it meets the molding
--   --   CODED LOCKBOX 1515
    Microwave vented to Exterior  
    Shower Door in Master Bathroom  
    Stained Hardwood Treads to Bedroom Level  
Sun    Nov 2      Sod / Seed / Landscaping (0)      
Sun    Nov 2      Loan Approval (0)  02.27.2025     JoDee @ United (95% Conventional)
Sun    Nov 2      Garage Door (0)      
Sun    Nov 2      House Numbers (0)      
Sun    Nov 2      Mailbox (0)      
Sun    Nov 2      Cover Floors (1)      
Mon    Nov 3      Electric Trim Out (3) *        In process 10/31
Thu    Nov 6      HVAC Trim Out (1) *       
Fri    Nov 7      Blower Door Test (1)      
Mon    Nov 10      Install Appliances (0) *        Appliances on site 10/22
Mon    Nov 10      Appraiser Confirms Construction Completion (0)      
Mon    Nov 10      Inspection (Final HVAC) (1)      
Tue    Nov 11      Inspection (Final Plumbing) (1)      
Wed    Nov 12      Inspection (Final Electric) (1)      
Thu    Nov 13      Inspection (Final Building) (2) *       
Mon    Nov 17      Pre Walk Through (0)      
Mon    Nov 17      Stain Hardwood Stairs (1) *       
Tue    Nov 18      Cleaning (1)      
Wed    Nov 19      Certificate of Occupancy (1) *       
Thu    Nov 20      C.O. to Lender (0)      
Thu    Nov 20      Schedule Closing (0)      
Thu    Nov 20      Buyer Walk Through (1) *       
Fri    Nov 21      Payment for Upgrades (0)      
Fri    Nov 21      Keys to Settlement Agent (0)      
Fri    Nov 21      Review Settlement Statement (0)      
Fri    Nov 21      Jerry Signs Closing Documents (0)      
Fri    Nov 21      Request Trash Tote From POA Manager (0)      
Fri    Nov 21      Closing (1)       Brittany @ West View Title
Mon    Nov 24      Remove Coded Lockbox (0)      
--   --   Pre drywall inspection Friday, Aug 29 at 1PM, Benjamin Meredith
--   --   12x18 deck possible?
--   --   Make sure correct primary bathtub gets installed Shower pan is in the bonus room. The bathtub in the master needs to be moved to the bonus bathroom.
--   --   Add insulation at front first floor exterior wall
--   --   Add insulation at half bathroom wall
--   --   Add insulation at the wall adjacent to the front exterior door
--   --   Add insulation at the wall adjacent the 2nd floor stairwell
--   --   Install air barrier behind exterior tub wall
--   --   Install air barrier at exterior wall adjacent to primary bathroom shower stall
--   --   Repair damaged truss plates at left side gable end attic truss
--   --   Repair floor truss adjacent to top of basement stairs
--   --   Last bit of bonus room drywall needs to be installed. I think after the deck is built.
--   --   I do not see the panels for this primary shower on site In primary bedroom, just need to be installed
--   --   Garage drywall is going to need to be finished Drywaller
--   --   Install farmhouse sink that is sitting on the floor of the kitchen
--   --   Repair drywall around primary bedroom door Drywaller
--   --   Wrong bathroom countertops? Waiting on Fenco
--   --   Remove culture marble countertops from primary bathroom and install quartz. I do not see a side splash on site for the quartz countertops.
--   --   Cover carpet in bonus room
--   --   Install countertop and bonus bathroom Fenco
--   --   Install countertop in primary bathroom Fenco
-- -- Ratified Contract? (0)  02.13.2025    
    Finished Bonus Room  
    Finished Bonus Bathroom  
    Expanded Driveway  
    White perimeter kitchen cabinets  
    Level 0 Quartz Countertops Carrara Trigato  
    Farmhouse Sink  
    Double Pull Out Waste Basket in Island  
    Spice Rack Cabinet  
    French Style Refrigerator  
    Level 0 quartz in all bathrooms  
    LVP in Upstairs Hallway  
    8 lb pad upstairs carpet  
    8 lb pad in Bonus Room  
    Living Room ceiling fan  
    Digital Deadbolt front door  
    White Subway Tile Shower Walls  
    Expanded 10 x 18 Deck  
    Amendment to increase price by $34,690  
-- -- $2500 Deposit Received (0)  02.17.2025    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  02.15.2025    
-- -- Selections Meeting (0)  03.28.2025     11:00 AM 3/26
-- -- Selections Sheet Signed (0)  03.30.2025     3/27: sent to Luke
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.02.2025     7/29: sent to Luke
-- -- Deposit For Upgrades Received (0)  04.08.2025    
-- -- Building Permit (30) *   04.11.2025    
-- -- Order Roof & Floor Trusses (1)  07.31.2025    
-- -- Order Windows & Doors (0)  07.31.2025    
-- -- Stake Out Home (1)  05.27.2025    
-- -- Excavate (2)  05.27.2025    
-- -- Inspection (Footers) (1)  06.30.2025    
-- -- Inspection (Concrete Wall) (1)  05.27.2025    
-- -- Pour Footers (1) *   06.19.2025    
-- -- Set Forms (2)  05.27.2025    
-- -- Pour Foundation Walls (1)  05.27.2025    
-- -- Plumb Slab (2)  06.19.2025    
-- -- Inspection (Plumbing Under Slab) (1)  06.30.2025    
-- -- Inspection (Conduit Under Slab) (1)  06.30.2025    
-- -- Prepare Slab (1)  06.30.2025    
-- -- Inspection (Slab) (1)  07.19.2025    
-- -- Inspection (Drain Tile) (0)  07.19.2025    
-- -- Pour Slab (1) *   06.30.2025    
-- -- Settlement Agent Confirmed (0)  04.16.2025    
-- -- Framing I (9)  07.19.2025    
-- -- Order Steps (0)  07.31.2025    
-- -- Order Tubs / Showers (0)  08.03.2025    
-- -- Framing II (8)  07.19.2025    
-- -- Framing III (8) *   07.31.2025    
-- -- Verify Window & Roof Structure (0)  07.31.2025    
-- -- Install Stairs (0) *   08.03.2025    
-- -- Windows & Doors (0) *   08.03.2025    
-- -- House Number and Status in Window (0)  09.06.2025    
-- -- Roofing (0) *   08.06.2025    
-- -- Order Cabinets (0)  08.28.2025    
-- -- Order Appliances (0)  10.02.2025    
-- -- Deck (0)  09.17.2025     Standard
-- -- Gutters (0)  10.18.2025    
-- -- Driveway (0) *   10.31.2025    
-- -- Patio (0)  09.17.2025     Standard
-- -- Privacy Divider / Fence (0) *   09.17.2025    
-- -- HVAC Rough In (4)  08.03.2025    
-- -- Rough In Microwave Vent (0)  08.03.2025    
-- -- Plumbing Rough In (4)  08.18.2025     In process 8/13
-- -- Electric Rough In (4)  08.26.2025    
-- -- Inspection (Rough In HVAC) (1)  08.26.2025    
-- -- Inspection (Rough In Plumbing) (1)  08.26.2025    
-- -- Inspection (Rough In Electric) (1)  08.26.2025    
-- -- Inspection (Framing) (1) *   08.26.2025    
-- -- Inspection (Deck Piers) (0)  09.11.2025    
-- -- Exterior Vinyl (0) *   10.08.2025     In process 10/1
-- -- Exterior Stone (0)  10.15.2025    
-- -- Insulation (2) *   08.27.2025    
-- -- Inspection (Insulation) (1)  09.04.2025    
-- -- Inspection (Electric Service) (0)  10.10.2025    
-- -- Set Electric Meter (0) *   10.23.2025    
-- -- Inspection (Main Sewer Line) (0)  08.21.2025    
-- -- Inspection (Main Water Line) (0)  08.21.2025    
-- -- Order Interior Doors & Trim (0)  09.11.2025    
-- -- Drywall (Hang) (4) *   09.06.2025    
-- -- Deed Preparation (0)  10.23.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   09.17.2025    
-- -- Paint 1 (1)  09.17.2025    
-- -- Cabinet Installation (2) *   09.22.2025     Delivered Sep 17, Installed Sep 18
-- -- Granite Installation (1) *   10.18.2025    
-- -- Interior Trim - Install (3) *   10.01.2025     In process 9/24
-- -- Order Plumbing / Lighting Fixtures (0)  10.02.2025    
-- -- Interior Trim - Paint (1)  10.01.2025    
-- -- Luxury Vinyl Plank (3) *   10.11.2025     In process 10/8
-- -- Luxury Vinyl Tile (0)  10.11.2025     In process 10/8
-- -- Paint 2 (3)  10.15.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  10.13.2025    
-- -- Shoe Moulding (0)  10.25.2025     In process 10/11
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   10.29.2025    
-- -- Install Coded Lockbox (add extra keys) (0)  10.31.2025    
-- -- Pay Water / Sewer Taps (0)  10.23.2025    
-- -- Set Water Meter (0) *   10.30.2025    
-- -- Ceiling Fans (0)  10.29.2025    
-- -- Plumbing Trim Out (2) *   10.29.2025     Plumbing in process
-- -- Paint 3 (2) *   10.22.2025    
-- -- Carpet (2)  10.11.2025