| TO DO |
| CL |
Jan 28 (6) |
Lots of painting of doors needed |
Jesus |
|
| LR |
Jan 20 (14) |
Patch and paint bonus room window trim |
Jesus |
|
| CL |
Jan 24 (10) |
Bonus room bathroom door needs to be painted |
Jesus |
|
| CL |
Jan 28 (6) |
Large drywall, crack in bonus room ceiling |
Jesus |
|
| CL |
Jan 28 (6) |
Side gutter dented pretty bad |
Davenport - downspout |
|
| SR |
Feb 2 (1) |
Add trim to exterior of bonus room window |
Tom |
|
| CL |
Jan 14 (20) |
Closet and door at the top of the staircase need to be painted |
Jesus |
|
| CL |
Jan 31 (3) |
Paint and patch door and trim of laundry room |
Jesus |
|
|
| UPGRADES |
| |
|
Microwave vented to exterior
|
|
| |
|
Painted Carpet Grade Steps
|
|
|
| CRITICAL PATH |
|
|
|
Privacy Divider / Fence (0) * |
|
|
|
|
|
Sod / Seed / Landscaping (0) |
All completed except side yard |
|
|
|
|
Loan Approval (0) |
Scott @ BOTJ (75% Conventional) |
|
|
|
|
House Numbers (0) |
|
|
|
|
|
Mailbox (0) |
|
|
|
Tue
|
Feb 3
|
Paint 2 (3) |
In process 1/28 |
|
|
|
|
Cover Floors (0) |
|
|
|
Fri
|
Feb 6
|
Shelving, Door Knobs, Fire Extinguisher (1) * |
|
|
|
|
|
Install Coded Lockbox (add extra keys) (0) |
|
|
|
Mon
|
Feb 9
|
Electric Trim Out (3) * |
|
|
|
|
|
Ceiling Fans (0) |
|
|
|
Thu
|
Feb 12
|
Blower Door Test (1) |
|
|
|
Fri
|
Feb 13
|
Plumbing Trim Out (2) * |
Started 1/31 |
|
|
|
|
Install Appliances (0) * |
Need to be delivered |
|
|
Tue
|
Feb 17
|
Paint 3 (2) * |
|
|
|
|
|
Appraiser Confirms Construction Completion (0) |
|
|
|
|
|
Inspection (Final HVAC) (0) |
|
|
|
|
|
Inspection (Final Plumbing) (0) |
|
|
|
|
|
Inspection (Final Electric) (0) |
|
|
|
Thu
|
Feb 19
|
Inspection (Final Building) (4) * |
|
|
|
|
|
Pre Walk Through (0) |
|
|
|
Wed
|
Feb 25
|
Stain Hardwood Stairs (1) * |
|
|
|
Thu
|
Feb 26
|
Cleaning (1) |
|
|
|
Fri
|
Feb 27
|
Certificate of Occupancy (1) * |
|
|
|
|
|
C.O. to Lender (0) |
|
|
|
|
|
Schedule Closing (0) |
|
|
|
Mon
|
Mar 2
|
Buyer Walk Through (1) * |
|
|
|
|
|
Payment for Upgrades (0) |
|
|
|
|
|
Keys to Settlement Agent (0) |
|
|
|
|
|
Review Settlement Statement (0) |
|
|
|
|
|
Jerry Signs Closing Documents (0) |
|
|
|
Tue
|
Mar 3
|
Closing (1) |
Brittany @ West View Title |
|
|
|
|
Remove Coded Lockbox (0) |
|
|
|
| TO DO - COMPLETED OR DELETED |
|
|
Second deposit was $50 short (adjust at closing) |
Scott will tell WVT |
|
|
|
Walk in fiberglass shower in bonus room |
|
|
|
|
10 has a dormer window-that ok? |
|
|
|
|
I think one of the tubs in the garage of nine goes in the basement of 12 |
|
|
|
|
Looks like one fan box is needed in the living room |
|
|
|
|
Size splash Needed on master bathroom vanity |
Also needed at hall bathroom |
|
|
|
Vanity not on bonus bathroom vanity |
Countertop needs to be secured |
|
|
|
Vanity top needed for bonus vanity |
|
|
|
|
Ceiling and primary bedroom still needs to be completed? Then painted? |
|
|
| CL |
Jan 14 (20) |
HVAC fan covers needed in all bathrooms |
Mast & Brunk |
|
| CL |
Jan 7 (27) |
Side splash Needed on bonus room vanity |
Tom, Jesus |
|
| CL |
Jan 7 (27) |
Trim needed on bonus room window |
Jesus - patch and paint |
|
| SR |
Jan 12 (22) |
Repair drywall cracks in bonus room ceiling |
Drywaller |
|
| CL |
Jan 28 (6) |
Garage interior door is opening wrong direction |
Maybe a different townhouse |
|
| CL |
Jan 31 (3) |
The countertop in the bonus bathroom is definitely an older, creamier color than the rest of the house. Maybe no one will notice? |
|
|
| CL |
Jan 31 (3) |
Exterior trim is needed on bonus room window |
|
|
|
|
Ecobee 3 ordered 11/3 |
|
|
| CL |
Jan 10 (24) |
I think the upgraded thermostat may be for 12 and not 9? |
|
|
| CL |
Jan 14 (20) |
Drywall repair needed on the corner near the kitchen and the staircase |
Drywaller |
|
| CL |
Jan 14 (20) |
HVAC register covers are installed except for the large ones on the main level and on the staircase at the upper level of the house |
Mast & Brunk |
|
| CL |
Jan 21 (13) |
Pretty significant drywall repair needed at the landing between the main level and upper level of the home |
Drywaller |
|
| CL |
Jan 21 (13) |
Clarity white paint in kitchen |
Clarify location |
|
| CL |
Jan 10 (24) |
Trim and door missing from laundry room. It looks like they were installed at some point? |
Jorge - arriving Jan 23 |
|
| CL |
Jan 21 (13) |
Long pipe and laundry room likely needs to be trimmed down |
Plumber |
|
|
| UPGRADES - COMPLETED |
| |
|
LVP in Upstairs Hallway and Bedrooms
|
|
| |
|
Upgraded LVT in Up Baths, Bonus Bath and Laundry
|
|
| |
|
Expanded Driveway
|
|
| |
|
Garage Door Opener Keypad
|
|
| |
|
EcoBee 3 lite smart Wifi Enabled Thermostat
|
|
| |
|
Egress Window in Bonus Room
|
|
| |
|
Finished Bonus Room
|
|
| |
|
Finish Bonus Bath
|
|
| |
|
Eggshell Paint for Chantily White Only
|
|
| |
|
LVP in Bonus Room
|
|
| |
|
Amendment to increase price by $25,905
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Ratified Contract? (0) 03.05.2025 |
|
|
| -- |
-- |
$2500 Deposit Received (0) 03.06.2025 |
|
|
| -- |
-- |
Association Packet Requested (0) 06.30.2025 |
|
|
| -- |
-- |
Association Packet Received (0) 03.07.2025 |
|
|
| -- |
-- |
Selections Meeting (0) 04.08.2025 |
|
|
| -- |
-- |
Selections Sheet Signed (0) 06.13.2025 |
5/30: sent to David |
|
| -- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 06.19.2025 |
6/13: sent to David |
|
| -- |
-- |
Deposit For Upgrades Received (0) 06.19.2025 |
|
|
| -- |
-- |
Building Permit (30) * 04.11.2025 |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) 08.04.2025 |
|
|
| -- |
-- |
Order Windows & Doors (0) 09.15.2025 |
|
|
| -- |
-- |
Stake Out Home (1) 05.27.2025 |
|
|
| -- |
-- |
Excavate (2) 05.27.2025 |
|
|
| -- |
-- |
Inspection (Footers) (1) 05.27.2025 |
|
|
| -- |
-- |
Inspection (Concrete Wall) (1) 05.27.2025 |
|
|
| -- |
-- |
Pour Footers (1) * 06.02.2025 |
|
|
| -- |
-- |
Set Forms (2) 05.27.2025 |
|
|
| -- |
-- |
Pour Foundation Walls (1) 05.27.2025 |
|
|
| -- |
-- |
Plumb Slab (2) 07.31.2025 |
|
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) 07.31.2025 |
|
|
| -- |
-- |
Inspection (Conduit Under Slab) (1) 07.31.2025 |
|
|
| -- |
-- |
Prepare Slab (1) 07.31.2025 |
|
|
| -- |
-- |
Inspection (Slab) (1) 07.31.2025 |
|
|
| -- |
-- |
Inspection (Drain Tile) (0) 09.28.2025 |
|
|
| -- |
-- |
Pour Slab (1) * 07.31.2025 |
|
|
| -- |
-- |
Settlement Agent Confirmed (0) 12.29.2025 |
12/5: sent to Brittany |
|
| -- |
-- |
Framing I (9) 09.04.2025 |
|
|
| -- |
-- |
Order Steps (0) 09.15.2025 |
|
|
| -- |
-- |
Order Tubs / Showers (0) 09.28.2025 |
|
|
| -- |
-- |
Framing II (8) 09.17.2025 |
|
|
| -- |
-- |
Framing III (8) * 09.25.2025 |
|
|
| -- |
-- |
Verify Window & Roof Structure (0) 09.28.2025 |
|
|
| -- |
-- |
Install Stairs (0) * 09.28.2025 |
|
|
| -- |
-- |
Windows & Doors (0) * 09.28.2025 |
|
|
| -- |
-- |
House Number and Status in Window (0) 10.15.2025 |
|
|
| -- |
-- |
Roofing (0) * 09.28.2025 |
|
|
| -- |
-- |
Order Cabinets (0) 10.16.2025 |
|
|
| -- |
-- |
Order Appliances (0) 10.24.2025 |
Kate will order 11/15 for 12/15 install |
|
| -- |
-- |
Deck (0) 11.05.2025 |
None |
|
| -- |
-- |
Gutters (0) 12.06.2025 |
|
|
| -- |
-- |
Driveway (0) * 11.19.2025 |
|
|
| -- |
-- |
Patio (0) 01.10.2026 |
Standard |
|
| -- |
-- |
HVAC Rough In (4) 09.28.2025 |
|
|
| -- |
-- |
Rough In Microwave Vent (0) 09.28.2025 |
|
|
| -- |
-- |
Plumbing Rough In (4) 10.19.2025 |
hook up bathtubs 10/8 |
|
| -- |
-- |
Electric Rough In (4) 10.22.2025 |
In process 10/19 |
|
| -- |
-- |
Inspection (Rough In HVAC) (1) 10.31.2025 |
|
|
| -- |
-- |
Inspection (Rough In Plumbing) (1) 10.31.2025 |
|
|
| -- |
-- |
Inspection (Rough In Electric) (1) 10.31.2025 |
|
|
| -- |
-- |
Inspection (Framing) (1) * 10.31.2025 |
|
|
| -- |
-- |
Inspection (Deck Piers) (0) 12.22.2025 |
|
|
| -- |
-- |
Exterior Vinyl (0) * 12.04.2025 |
In process 11/28 |
|
| -- |
-- |
Exterior Stone (0) 12.17.2025 |
in process 12/3 |
|
| -- |
-- |
Insulation (2) * 10.31.2025 |
|
|
| -- |
-- |
Inspection (Insulation) (1) 11.06.2025 |
|
|
| -- |
-- |
Inspection (Electric Service) (0) 10.30.2025 |
|
|
| -- |
-- |
Set Electric Meter (0) * 12.01.2025 |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) 10.30.2025 |
|
|
| -- |
-- |
Inspection (Main Water Line) (0) 10.30.2025 |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) 12.01.2025 |
|
|
| -- |
-- |
Drywall (Hang) (4) * 11.12.2025 |
Stocked 11/8 |
|
| -- |
-- |
Deed Preparation (0) 01.08.2026 |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 12.13.2025 |
In process 12/10. Cabinets going in now. |
|
| -- |
-- |
Paint 1 (1) 12.13.2025 |
|
|
| -- |
-- |
Garage Door (0) 12.17.2025 |
|
|
| -- |
-- |
Cabinet Installation (2) * 12.13.2025 |
In process 12/10 |
|
| -- |
-- |
Granite Installation (1) * 12.20.2025 |
|
|
| -- |
-- |
Interior Trim - Install (3) * 01.04.2026 |
In process 12/20 |
|
| -- |
-- |
Order Plumbing / Lighting Fixtures (0) 12.22.2025 |
|
|
| -- |
-- |
Interior Trim - Paint (1) 01.07.2026 |
|
|
| -- |
-- |
Luxury Vinyl Plank (3) * 01.17.2026 |
In process 1/14 |
|
| -- |
-- |
Luxury Vinyl Tile (0) 01.10.2026 |
|
|
| -- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 12.22.2025 |
|
|
| -- |
-- |
Shoe Moulding (0) 01.24.2026 |
|
|
| -- |
-- |
Pay Water / Sewer Taps (0) 01.11.2026 |
|
|
| -- |
-- |
Set Water Meter (1) * 01.12.2026 |
|
|
| -- |
-- |
HVAC Trim Out (1) * 01.14.2026 |
|
|
| -- |
-- |
Carpet (2) 01.14.2026 |
|
|
| -- |
-- |
Request Trash Tote From POA Manager (0) 01.27.2026 |
|
|