| TO DO |
| CL |
Mar 11 (14) |
Stove needs to be pushed back into place once electrical outlet has been complete completed |
|
|
|
| UPGRADES |
| |
|
Painted Stairs to Bedroom Level
|
|
| |
|
Eggshell Paint
|
|
|
| CRITICAL PATH |
|
|
|
Privacy Divider / Fence (0) * |
|
|
|
|
|
Sod / Seed / Landscaping (0) |
|
|
|
|
|
House Numbers (0) |
|
|
|
Wed
|
Mar 25
|
Paint 2 (3) |
In process 3/25 |
|
|
Mon
|
Mar 30
|
Shelving, Door Knobs, Fire Extinguisher (1) * |
Holes appear to have been pre-drilled for some shelving to be installed |
|
|
|
|
Install Coded Lockbox (add extra keys) (0) |
|
|
|
Tue
|
Mar 31
|
Electric Trim Out (3) * |
|
|
|
|
|
Ceiling Fans (0) |
|
|
|
Fri
|
Apr 3
|
HVAC Trim Out (1) * |
Heat pump set 3/11 |
|
|
Mon
|
Apr 6
|
Blower Door Test (1) |
|
|
|
Tue
|
Apr 7
|
Paint 3 (2) * |
|
|
|
|
|
Appraiser Confirms Construction Completion (0) |
|
|
|
|
|
Inspection (Final HVAC) (0) |
|
|
|
|
|
Inspection (Final Plumbing) (0) |
|
|
|
|
|
Inspection (Final Electric) (0) |
|
|
|
Thu
|
Apr 9
|
Inspection (Final Building) (4) * |
|
|
|
|
|
Pre Walk Through (0) |
|
|
|
Wed
|
Apr 15
|
Stain Hardwood Stairs (1) * |
|
|
|
Thu
|
Apr 16
|
Cleaning (1) |
|
|
|
Fri
|
Apr 17
|
Certificate of Occupancy (1) * |
|
|
|
|
|
C.O. to Lender (0) |
|
|
|
|
|
Schedule Closing (0) |
|
|
|
Mon
|
Apr 20
|
Buyer Walk Through (1) * |
|
|
|
|
|
Payment for Upgrades (0) |
|
|
|
|
|
Keys to Settlement Agent (0) |
|
|
|
|
|
Review Settlement Statement (0) |
|
|
|
|
|
Jerry Signs Closing Documents (0) |
|
|
|
|
|
Request Trash Tote From POA Manager (0) |
|
|
|
Tue
|
Apr 21
|
Closing (1) |
Brittany @ West View Title |
|
|
|
|
Remove Coded Lockbox (0) |
|
|
|
| TO DO - COMPLETED OR DELETED |
|
|
Black spray paint dormer windows |
|
|
| CL |
Mar 4 (21) |
I think the ceilings are going to need to be painted where the drywall repairs were made |
Jesus |
|
| CL |
Feb 28 (25) |
The drywall repairs here look to have been sanded and ready for another coat of paint |
|
|
| LR |
Feb 6 (47) |
Trim needed by pantry door |
|
|
| CL |
Feb 18 (35) |
Top step leading to main level of the home has a large crack running through it |
Tom |
|
| CL |
Feb 22 (31) |
All appliances are sitting in the kitchen 2/22 |
|
|
| LR |
Feb 25 (28) |
Top step leading to main level of home has been fixed and needs to be painted |
Jesus |
|
| CL |
Feb 28 (25) |
Hall bathroom needs overflow and bottom, silver bath fixture |
|
|
|
|
Broken front window |
Tom, front left bedroom looking out |
|
| CL |
Jan 7 (77) |
Primary bathroom countertop needed |
Tom, In kitchen 1/24 |
|
| CL |
Jan 31 (53) |
Side splsh needed on primary bathroom |
|
|
| CL |
Feb 18 (35) |
Primary bathroom faucets need to be installed |
Plumber |
|
|
| UPGRADES - COMPLETED |
| |
|
Expanded Driveway
|
|
| |
|
LVP in Upstairs Hallway and Bedrooms
|
|
| |
|
Amendment to increase price by $6,020
|
|
|
| CRITICAL PATH - COMPLETED |
| -- |
-- |
Ratified Contract? (0) 07.21.2025 |
|
|
| -- |
-- |
$2500 Deposit Received (0) 07.29.2025 |
|
|
| -- |
-- |
Association Packet Requested (0) 07.21.2025 |
|
|
| -- |
-- |
Association Packet Received (0) 07.29.2025 |
|
|
| -- |
-- |
Selections Meeting (0) 08.21.2025 |
|
|
| -- |
-- |
Selections Sheet Signed (0) 08.21.2025 |
|
|
| -- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 08.29.2025 |
|
|
| -- |
-- |
Deposit For Upgrades Received (0) 08.29.2025 |
|
|
| -- |
-- |
Building Permit (30) * 05.24.2025 |
|
|
| -- |
-- |
Order Roof & Floor Trusses (1) 09.15.2025 |
|
|
| -- |
-- |
Order Windows & Doors (0) 10.09.2025 |
|
|
| -- |
-- |
Stake Out Home (1) 05.29.2025 |
|
|
| -- |
-- |
Excavate (2) 05.29.2025 |
|
|
| -- |
-- |
Inspection (Footers) (1) 06.02.2025 |
|
|
| -- |
-- |
Inspection (Concrete Wall) (1) 07.31.2025 |
|
|
| -- |
-- |
Pour Footers (1) * 06.02.2025 |
|
|
| -- |
-- |
Set Forms (2) 06.05.2025 |
|
|
| -- |
-- |
Pour Foundation Walls (1) 07.31.2025 |
|
|
| -- |
-- |
Plumb Slab (2) 07.31.2025 |
|
|
| -- |
-- |
Inspection (Plumbing Under Slab) (1) 08.25.2025 |
|
|
| -- |
-- |
Inspection (Conduit Under Slab) (1) 08.25.2025 |
|
|
| -- |
-- |
Prepare Slab (1) 08.07.2025 |
|
|
| -- |
-- |
Inspection (Slab) (1) 08.25.2025 |
|
|
| -- |
-- |
Inspection (Drain Tile) (0) 08.25.2025 |
|
|
| -- |
-- |
Pour Slab (1) * 09.04.2025 |
|
|
| -- |
-- |
Settlement Agent Confirmed (0) 10.25.2025 |
|
|
| -- |
-- |
Framing I (9) 09.15.2025 |
|
|
| -- |
-- |
Order Steps (0) 10.09.2025 |
|
|
| -- |
-- |
Order Tubs / Showers (0) 10.09.2025 |
|
|
| -- |
-- |
Framing II (8) 09.17.2025 |
|
|
| -- |
-- |
Framing III (8) * 10.09.2025 |
|
|
| -- |
-- |
Verify Window & Roof Structure (0) 10.09.2025 |
|
|
| -- |
-- |
Install Stairs (0) * 10.15.2025 |
|
|
| -- |
-- |
Windows & Doors (0) * 10.15.2025 |
|
|
| -- |
-- |
House Number and Status in Window (0) 10.22.2025 |
|
|
| -- |
-- |
Roofing (0) * 10.15.2025 |
|
|
| -- |
-- |
Order Cabinets (0) 10.25.2025 |
|
|
| -- |
-- |
Order Appliances (0) 12.22.2025 |
|
|
| -- |
-- |
Deck (0) 01.04.2026 |
|
|
| -- |
-- |
Gutters (0) 02.04.2026 |
|
|
| -- |
-- |
Driveway (0) * 03.21.2026 |
|
|
| -- |
-- |
Patio (0) 01.07.2026 |
Framed 12/20 |
|
| -- |
-- |
HVAC Rough In (4) 10.15.2025 |
|
|
| -- |
-- |
Rough In Microwave Vent (0) 10.15.2025 |
|
|
| -- |
-- |
Plumbing Rough In (4) 11.05.2025 |
In process 10/29 |
|
| -- |
-- |
Electric Rough In (4) 11.10.2025 |
In process 11/8 |
|
| -- |
-- |
Inspection (Rough In HVAC) (1) 11.19.2025 |
|
|
| -- |
-- |
Inspection (Rough In Plumbing) (1) 11.19.2025 |
|
|
| -- |
-- |
Inspection (Rough In Electric) (1) 11.19.2025 |
|
|
| -- |
-- |
Inspection (Framing) (1) * 11.19.2025 |
|
|
| -- |
-- |
Inspection (Deck Piers) (0) 01.04.2026 |
|
|
| -- |
-- |
Exterior Vinyl (0) * 02.04.2026 |
In process 1/14 |
|
| -- |
-- |
Exterior Stone (0) 01.10.2026 |
|
|
| -- |
-- |
Insulation (2) * 11.19.2025 |
|
|
| -- |
-- |
Inspection (Insulation) (1) 11.28.2025 |
|
|
| -- |
-- |
Inspection (Electric Service) (0) 12.06.2025 |
|
|
| -- |
-- |
Set Electric Meter (0) * 01.07.2026 |
|
|
| -- |
-- |
Inspection (Main Sewer Line) (0) 08.18.2025 |
|
|
| -- |
-- |
Inspection (Main Water Line) (0) 08.18.2025 |
|
|
| -- |
-- |
Order Interior Doors & Trim (0) 01.04.2026 |
|
|
| -- |
-- |
Drywall (Hang) (4) * 12.03.2025 |
Stocked 11/22 |
|
| -- |
-- |
Loan Approval (0) 01.10.2026 |
Cash |
|
| -- |
-- |
Deed Preparation (0) 01.08.2026 |
|
|
| -- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 12.20.2025 |
In process 12/6 |
|
| -- |
-- |
Paint 1 (1) 01.04.2026 |
|
|
| -- |
-- |
Garage Door (0) 01.17.2026 |
|
|
| -- |
-- |
Mailbox (0) 03.14.2026 |
|
|
| -- |
-- |
Cabinet Installation (2) * 12.29.2025 |
Cabinets on site 12/20 |
|
| -- |
-- |
Granite Installation (1) * 01.07.2026 |
|
|
| -- |
-- |
Interior Trim - Install (3) * 02.06.2026 |
Doors and door trim needed. Partial paint8ng com0lete 1/24 |
|
| -- |
-- |
Order Plumbing / Lighting Fixtures (0) 01.12.2026 |
|
|
| -- |
-- |
Interior Trim - Paint (1) 02.22.2026 |
Doors need to be painted 2/11 |
|
| -- |
-- |
Luxury Vinyl Plank (3) * 01.24.2026 |
In process 1/21 |
|
| -- |
-- |
Luxury Vinyl Tile (0) 01.24.2026 |
In process 1/21 |
|
| -- |
-- |
Cover Floors (0) 03.18.2026 |
|
|
| -- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 01.26.2026 |
|
|
| -- |
-- |
Shoe Moulding (0) 02.14.2026 |
In process 2/11 |
|
| -- |
-- |
Pay Water / Sewer Taps (0) 03.19.2026 |
|
|
| -- |
-- |
Set Water Meter (1) * 03.25.2026 |
|
|
| -- |
-- |
Plumbing Trim Out (2) * 02.18.2026 |
|
|
| -- |
-- |
Install Appliances (0) * 03.11.2026 |
All appliances on site 2/22 |
|
| -- |
-- |
Carpet (2) 02.07.2026 |
|
|