CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (Mar 25)    show all photos
TO DO
CL Mar 11 (14) Stove needs to be pushed back into place once electrical outlet has been complete completed
UPGRADES
    Painted Stairs to Bedroom Level  
    Eggshell Paint  
CRITICAL PATH
    Privacy Divider / Fence (0) *       
    Sod / Seed / Landscaping (0)      
    House Numbers (0)      
Wed    Mar 25      Paint 2 (3)       In process 3/25
Mon    Mar 30      Shelving, Door Knobs, Fire Extinguisher (1) *        Holes appear to have been pre-drilled for some shelving to be installed
    Install Coded Lockbox (add extra keys) (0)      
Tue    Mar 31      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Fri    Apr 3      HVAC Trim Out (1) *        Heat pump set 3/11
Mon    Apr 6      Blower Door Test (1)      
Tue    Apr 7      Paint 3 (2) *       
    Appraiser Confirms Construction Completion (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Thu    Apr 9      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Wed    Apr 15      Stain Hardwood Stairs (1) *       
Thu    Apr 16      Cleaning (1)      
Fri    Apr 17      Certificate of Occupancy (1) *       
    C.O. to Lender (0)      
    Schedule Closing (0)      
Mon    Apr 20      Buyer Walk Through (1) *       
    Payment for Upgrades (0)      
    Keys to Settlement Agent (0)      
    Review Settlement Statement (0)      
    Jerry Signs Closing Documents (0)      
    Request Trash Tote From POA Manager (0)      
Tue    Apr 21      Closing (1)       Brittany @ West View Title
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
Black spray paint dormer windows
CL Mar 4 (21) I think the ceilings are going to need to be painted where the drywall repairs were made Jesus
CL Feb 28 (25) The drywall repairs here look to have been sanded and ready for another coat of paint
LR Feb 6 (47) Trim needed by pantry door
CL Feb 18 (35) Top step leading to main level of the home has a large crack running through it Tom
CL Feb 22 (31) All appliances are sitting in the kitchen 2/22
LR Feb 25 (28) Top step leading to main level of home has been fixed and needs to be painted Jesus
CL Feb 28 (25) Hall bathroom needs overflow and bottom, silver bath fixture
Broken front window Tom, front left bedroom looking out
CL Jan 7 (77) Primary bathroom countertop needed Tom, In kitchen 1/24
CL Jan 31 (53) Side splsh needed on primary bathroom
CL Feb 18 (35) Primary bathroom faucets need to be installed Plumber
UPGRADES - COMPLETED
    Expanded Driveway  
    LVP in Upstairs Hallway and Bedrooms  
    Amendment to increase price by $6,020  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  07.21.2025    
-- -- $2500 Deposit Received (0)  07.29.2025    
-- -- Association Packet Requested (0)  07.21.2025    
-- -- Association Packet Received (0)  07.29.2025    
-- -- Selections Meeting (0)  08.21.2025    
-- -- Selections Sheet Signed (0)  08.21.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.29.2025    
-- -- Deposit For Upgrades Received (0)  08.29.2025    
-- -- Building Permit (30) *   05.24.2025    
-- -- Order Roof & Floor Trusses (1)  09.15.2025    
-- -- Order Windows & Doors (0)  10.09.2025    
-- -- Stake Out Home (1)  05.29.2025    
-- -- Excavate (2)  05.29.2025    
-- -- Inspection (Footers) (1)  06.02.2025    
-- -- Inspection (Concrete Wall) (1)  07.31.2025    
-- -- Pour Footers (1) *   06.02.2025    
-- -- Set Forms (2)  06.05.2025    
-- -- Pour Foundation Walls (1)  07.31.2025    
-- -- Plumb Slab (2)  07.31.2025    
-- -- Inspection (Plumbing Under Slab) (1)  08.25.2025    
-- -- Inspection (Conduit Under Slab) (1)  08.25.2025    
-- -- Prepare Slab (1)  08.07.2025    
-- -- Inspection (Slab) (1)  08.25.2025    
-- -- Inspection (Drain Tile) (0)  08.25.2025    
-- -- Pour Slab (1) *   09.04.2025    
-- -- Settlement Agent Confirmed (0)  10.25.2025    
-- -- Framing I (9)  09.15.2025    
-- -- Order Steps (0)  10.09.2025    
-- -- Order Tubs / Showers (0)  10.09.2025    
-- -- Framing II (8)  09.17.2025    
-- -- Framing III (8) *   10.09.2025    
-- -- Verify Window & Roof Structure (0)  10.09.2025    
-- -- Install Stairs (0) *   10.15.2025    
-- -- Windows & Doors (0) *   10.15.2025    
-- -- House Number and Status in Window (0)  10.22.2025    
-- -- Roofing (0) *   10.15.2025    
-- -- Order Cabinets (0)  10.25.2025    
-- -- Order Appliances (0)  12.22.2025    
-- -- Deck (0)  01.04.2026    
-- -- Gutters (0)  02.04.2026    
-- -- Driveway (0) *   03.21.2026    
-- -- Patio (0)  01.07.2026     Framed 12/20
-- -- HVAC Rough In (4)  10.15.2025    
-- -- Rough In Microwave Vent (0)  10.15.2025    
-- -- Plumbing Rough In (4)  11.05.2025     In process 10/29
-- -- Electric Rough In (4)  11.10.2025     In process 11/8
-- -- Inspection (Rough In HVAC) (1)  11.19.2025    
-- -- Inspection (Rough In Plumbing) (1)  11.19.2025    
-- -- Inspection (Rough In Electric) (1)  11.19.2025    
-- -- Inspection (Framing) (1) *   11.19.2025    
-- -- Inspection (Deck Piers) (0)  01.04.2026    
-- -- Exterior Vinyl (0) *   02.04.2026     In process 1/14
-- -- Exterior Stone (0)  01.10.2026    
-- -- Insulation (2) *   11.19.2025    
-- -- Inspection (Insulation) (1)  11.28.2025    
-- -- Inspection (Electric Service) (0)  12.06.2025    
-- -- Set Electric Meter (0) *   01.07.2026    
-- -- Inspection (Main Sewer Line) (0)  08.18.2025    
-- -- Inspection (Main Water Line) (0)  08.18.2025    
-- -- Order Interior Doors & Trim (0)  01.04.2026    
-- -- Drywall (Hang) (4) *   12.03.2025     Stocked 11/22
-- -- Loan Approval (0)  01.10.2026     Cash
-- -- Deed Preparation (0)  01.08.2026    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   12.20.2025     In process 12/6
-- -- Paint 1 (1)  01.04.2026    
-- -- Garage Door (0)  01.17.2026    
-- -- Mailbox (0)  03.14.2026    
-- -- Cabinet Installation (2) *   12.29.2025     Cabinets on site 12/20
-- -- Granite Installation (1) *   01.07.2026    
-- -- Interior Trim - Install (3) *   02.06.2026     Doors and door trim needed. Partial paint8ng com0lete 1/24
-- -- Order Plumbing / Lighting Fixtures (0)  01.12.2026    
-- -- Interior Trim - Paint (1)  02.22.2026     Doors need to be painted 2/11
-- -- Luxury Vinyl Plank (3) *   01.24.2026     In process 1/21
-- -- Luxury Vinyl Tile (0)  01.24.2026     In process 1/21
-- -- Cover Floors (0)  03.18.2026    
-- -- Deliver Plumbing / Lighting Fixtures (0)  01.26.2026    
-- -- Shoe Moulding (0)  02.14.2026     In process 2/11
-- -- Pay Water / Sewer Taps (0)  03.19.2026    
-- -- Set Water Meter (1) *   03.25.2026    
-- -- Plumbing Trim Out (2) *   02.18.2026    
-- -- Install Appliances (0) *   03.11.2026     All appliances on site 2/22
-- -- Carpet (2)  02.07.2026