Wed | Nov 27 | Inspection (Concrete Wall) (1) | ||
Thu | Nov 28 | Inspection (Conduit Under Slab) (1) | ||
Fri | Nov 29 | Inspection (Drain Tile) (0) | ||
Fri | Nov 29 | Inspection (Rough In Plumbing) (1) | ||
Mon | Dec 2 | Inspection (Rough In Electric) (1) | ||
Tue | Dec 3 | Inspection (Deck Piers) (0) | ||
Tue | Dec 3 | Inspection (Framing) (1) | ||
Wed | Dec 4 | Inspection (Main Water Line) (0) | ||
Wed | Dec 4 | Inspection (Final HVAC) (1) | ||
Thu | Dec 5 | Inspection (Final Plumbing) (1) | ||
Fri | Dec 6 | Inspection (Final Electric) (1) | ||
-- | -- | Inspection (Footers) (1) | ||
-- | -- | Inspection (Plumbing Under Slab) (1) | ||
-- | -- | Inspection (Slab) (1) | ||
-- | -- | Inspection (Rough In HVAC) (1) | Reinspect 5/12 | |
-- | -- | Inspection (Insulation) (1) | today 5/18 | |
-- | -- | Inspection (Electric Service) (0) | ||
-- | -- | Inspection (Main Sewer Line) (0) | Working on it 7/29 | |
-- | -- | Inspection (Final Building) (2) * | Re-inspection Friday, August 21 | |