CONGERS-2 - 101  ::  1270 Constitution Court #101
[ BUILD: 1805-0140 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
--   --   Discuss Existing Conduit Layout
--   --   Shingle color? Same?
--   --   Shingle color? Same?
--   --  
--   --   Busted back pillar 6/24 Wrap with white PVC board
--   --   Photo of framed opening: https://bit.ly/2PojUVs
--   --   Electric trim out before remaining drywall goes up 8/19
--   --   Kate - Can the buyer pick the LVP color?
--   --   Kate - Can the buyer extend LBP to the bedrooms?
--   --   Kate - The buyer is ready to pick the granite color.
--   --   Bathroom floors-arriving 10/29 Eric to install 11/6in process 11/7
--   --   CODED LOCKBOX 0101
--   --   Anchor dishwasher 11/29
--   --   Drywall repairs needed
--   --   Door lock broken 12/16
--   --   Door lock broken 12/16
--   --  
--   --   Window framing repairs needed in MB 1/3 Painter
--   --   Light bulbs needed throughout 1/6 Greg to order and put in GWB
--   --   Paint touch up needed throughout
--   --   Transition strip to laundry needed 1/20 Greg to get from lowes 1/21 Eric to install
--   --   Microwave needed Maybe on order?
--   --   Cabinet trim needed in hallway bath 2/3
--   --   Clean again is it going to need it again?? 2/14
--   --   Paint door trim 2/6 Needs completing 2/24
--   --   Door handle to patio door needed 2/6
--   --   Bathroom outlet covers needed 2/10 after paint touch up 2/14
--   --   Check deadbolt Broken 2/17
--   --   Landscaping repairs 3/3 Tom scheduling landscaping 3/18
--   --   Loose door handle Kate talked to Ron-
--   --   Deadbolt is difficult to operate WD40-worked better 3/31
--   --   Touch up paint
--   --   Paint front door
--   --   Pressure wash siding
--   --   Finish cable panel Tom will take a look
--   --   Final clean
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)       Jan 6 or 7
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)       in process 2/8
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *        Roof in process 3/29
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)       in process 4/4
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       in process 4/29
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       Almost complete 6/14
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       Doors ordered. Trim to be ordered 9/28 GWB
-- -- Drywall (Hang) (4) *        Almost complete 9/2
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 9/19- almost completed
-- -- Paint 1 (1)       Set to start 9/22 GWB
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        Thursday, 11/11
-- -- Interior Trim - Install (3) *        in process 10/14
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        Waiting on arrival date for that flooring.
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Galindez on site 11/5 should be finished
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       In process 11/7
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       In process 1/3
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)      
-- -- Install Appliances (0) *        CJ to install pending date
-- -- Paint 3 (2) *       
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *       
-- -- Pre Walk Through (0)       1.22 GWB
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Tuesday, 4/20 at 11AM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)       Wed, 4/21 at 4:00 PM
-- -- Closing (1)       Wed, 4/21 at 4:30 PM
-- -- Remove Coded Lockbox (0)