1 14 73 65 61 62 63 ADDR
CONGERS-2 - 102  ::  1270 Constitution Court #102
[ BUILD: 1805-0142 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Building Permit (30)      
Tue    Jun 10      Inspection (Concrete Wall) (1)      
Wed    Jun 11      Inspection (Conduit Under Slab) (1)      
Thu    Jun 12      Inspection (Drain Tile) (0)      
Thu    Jun 12      Settlement Agent Confirmed (0)      
Thu    Jun 12      Verify Window & Roof Structure (0)      
Thu    Jun 12      Patio (0)      
Thu    Jun 12      Rough In Microwave Vent (0)      
Thu    Jun 12      Inspection (Rough In Plumbing) (1)      
Fri    Jun 13      Inspection (Rough In Electric) (1)      
Mon    Jun 16      Inspection (Deck Piers) (0)      
Mon    Jun 16      Inspection (Framing) (1) *       
Tue    Jun 17      Exterior Stone (0)      
Tue    Jun 17      Set Electric Meter (0) *       
Tue    Jun 17      Inspection (Main Water Line) (0)      
Tue    Jun 17      Loan Approval (0)      
Tue    Jun 17      Deed Preparation (0)      
Tue    Jun 17      Mailbox (0)      
Tue    Jun 17      Interior Trim - Paint (1)      
Wed    Jun 18      Ceiling Fans (0)      
Wed    Jun 18      Blower Door Test (1)      
Thu    Jun 19      Inspection (Final HVAC) (1)      
Fri    Jun 20      Inspection (Final Plumbing) (1)      
Mon    Jun 23      Inspection (Final Electric) (1)      
Tue    Jun 24      Stain Hardwood Stairs (1)      
Wed    Jun 25      Request Trash Tote From POA Manager (0)      
--   --   Handicapped accessible walkway?
--   --   CODED LOCKBOX 0201
--   --   Weather stripping After paint 3
--   --   Bathroom vanity countertops On order per Kimberly-Kimberly sending date-MB in 4/7
--   --   Threshold where shower meets bathroom floor Jill to install
--   --   Guest bathroom top Installed Thursday, 4/15
--   --   Bedroom door needs shaved down 4/17 Trim guys - Courtney will check it
--   --   One closet needs shelving 4/17 Not complete 5/1
--   --   One closet needs shelving 4/17
--   --   Few handles Ron
--   --   White receptacle in kitchen needs grey Jill will tell Harry
--   --   Cracked tub (MB) Jill to schedule
--   --   Adjust front door threshold
--   --   Patch hole at bathroom light
--   --   Sweep out debris and repair and secure shower to floor
--   --   Cut light in over shower
--   --   Patch drywall hole in master bath as well as vent in laundry room In process 4/28
--   --   Swap front door closet shelving with coat closet shelving
--   --   Swap front door closet shelving with coat closet shelving
--   --   Leave construction lockbox
--   --   Leave construction lockbox
--   --   Swap front door closet shelving with coat closet shelving
--   --   Clean outdoor siding
--   --   Cleaning again?
--   --   Shower update
--   --   Hole in back of shower in hall bathroom Jill is scheduling
--   --   Shower grab bar Ron
--   --   Tile shower
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       in process 5/3
-- -- Electric Rough In (4)       In process 6/17
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        stocked 9/19
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Needs final sanding 10/10
-- -- Paint 1 (1)      
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        In process 3/17
-- -- Granite Installation (1) *        Kitchen in 3/21. Vanities are not.
-- -- Interior Trim - Install (3) *        On site 11/18
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        After first week of April
-- -- Luxury Vinyl Tile (0)      
-- -- Paint 2 (3)       Agreeable grey is completed 2/24
-- -- Cover Floors (1)       Jill after install
-- -- Deliver Plumbing / Lighting Fixtures (0)       Kate will check on this
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       In process 4/21
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       in process 4/15
-- -- Install Appliances (0) *        Waiting on range plug install from Harry
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Mon, 4/12
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        After Harry finishes
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       5/14
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       West View Title
-- -- Remove Coded Lockbox (0)