CONGERS-2 - 203  ::  1270 Constitution Court #203
[ BUILD: 1805-0146 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Apr 29      Ratified Contract? (0)      
Tue    Apr 29      $2500 Deposit Received (0)      
Tue    Apr 29      Association Packet Requested (0)      
Tue    Apr 29      Association Packet Received (0)      
Tue    Apr 29      Selections Meeting (0)      
Tue    Apr 29      Selections Sheet Signed (0)      
Tue    Apr 29      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Tue    Apr 29      Deposit For Upgrades Received (0)      
Tue    Apr 29      Inspection (Concrete Wall) (1)      
Wed    Apr 30      Inspection (Conduit Under Slab) (1)      
Thu    May 1      Inspection (Drain Tile) (0)      
Thu    May 1      Settlement Agent Confirmed (0)      
Thu    May 1      Verify Window & Roof Structure (0)      
Thu    May 1      Patio (0)      
Thu    May 1      Rough In Microwave Vent (0)      
Thu    May 1      Inspection (Rough In Plumbing) (1)      
Fri    May 2      Inspection (Rough In Electric) (1)      
Mon    May 5      Inspection (Deck Piers) (0)      
Mon    May 5      Inspection (Framing) (1) *       
Tue    May 6      Exterior Stone (0)      
Tue    May 6      Set Electric Meter (0) *       
Tue    May 6      Inspection (Main Water Line) (0)      
Tue    May 6      Loan Approval (0)      
Tue    May 6      Deed Preparation (0)      
Tue    May 6      Mailbox (0)      
Tue    May 6      Interior Trim - Paint (1)      
Wed    May 7      Ceiling Fans (0)      
Wed    May 7      Blower Door Test (1)      
Thu    May 8      Inspection (Final HVAC) (1)      
Fri    May 9      Inspection (Final Plumbing) (1)      
Mon    May 12      Inspection (Final Electric) (1)      
Tue    May 13      Stain Hardwood Stairs (1)      
Wed    May 14      Request Trash Tote From POA Manager (0)      
--   --   Needs final drywall sanding 11/4
--   --   CODED LOCKBOX 0203
--   --   Sprinkler issue? 1/23 Drywall repair needed
--   --   Missing door? 1/23 Tom will ask for it to be delivered-in living room
--   --   I think the numbers say 302 outside the door Tom or Jill
--   --   Fridge in unit-correct fridge??
--   --   Bathroom sink tops Kate is waiting to hear from Kimberly
--   --   Paint front door 2/24
--   --   Vanity lights and outlet covers Harry-he told me his working Saturday to do this 3/3
--   --   Snap light over shower Harry-not one 2/27
--   --   Paint - is it the correct color?
--   --   French style fridge is in kitchen 2/27
--   --   Cabinet floor trim needed 3/3 On top of cabinets just needs cut/installed
--   --   Home Inspection - Wed, Mar 10 @ 9AM Rudy Long
--   --   Screens needed
--   --   Fix missing part of dishwasher
--   --   Caulk MB sink top backsplash Painter-needs caulk at bottom of backsplash 3/17isilicone?
--   --   Cover electrical box Jill
--   --   Remove extra supplies from top of kitchen cabinets And back deck
--   --   Nail needed in extra shoe molding
--   --   Increase cold water pressure on left master bath sink Fixing 3/18-Tom
--   --   Make the dishwasher work (did not work during inspection) CJ taking care of today 3/18
--   --   Install weatherstripping at the front door to close gaps Painter
--   --   Secure half bathroom sink top with a wedge (?)
--   --   Pressure wash front window? Dirt/concrete
--   --   Change type of dryer outlet? From the buyer - The bottom prong that I have is an L shape and the outlet has a circle there
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0)      
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)       Hopefully week of Jan 18
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)       In process 7/12
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        Stocked 9/19
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 10/24
-- -- Paint 1 (1)      
-- -- Garage Door (0) *       
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivery Feb 15, install set for 2/16 GWB
-- -- Granite Installation (1) *        Scheduled for Feb 17-in process 2/17
-- -- Interior Trim - Install (3) *       
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        In process 2/27
-- -- Luxury Vinyl Tile (0)       In process 2/27
-- -- Paint 2 (3)       Not completed 2/24-looks like whole house is chantilly lace
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)       Ready 3/3
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *       
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3)       In process 2/24
-- -- HVAC Trim Out (1)      
-- -- Plumbing Trim Out (2)       Tomorrow morning 3/7
-- -- Install Appliances (0) *        Installed. Fridge needs pushed back 3/7
-- -- Paint 3 (2) *       
-- -- Carpet (2)       In process 2/27
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Monday, March 8
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       Kelly wants water
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Tuesday 3/16 at 4:00 PM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Fri, Mar 19 @ 1:30 PM (for the buyer)
-- -- Remove Coded Lockbox (0)