Need white De Soto and Coco touch up kits for kitchen and bathroom cabinetry |
Ordered, will be dropped off at the property |
|
-- |
-- |
Tom adjust vinyl ceiling |
Greg - at front door |
|
-- |
-- |
Buff countertop in second bathroom |
At warehouse, Mindy will coordinate install |
|
-- |
-- |
CODED LOCKBOX --- 4625 |
|
|
Tue |
Apr 29 |
Ratified Contract? (0) |
|
|
Tue |
Apr 29 |
$2500 Deposit Received (0) |
|
|
Tue |
Apr 29 |
Association Packet Requested (0) |
|
|
Tue |
Apr 29 |
Association Packet Received (0) |
|
|
Tue |
Apr 29 |
Selections Meeting (0) |
|
|
Tue |
Apr 29 |
Selections Sheet Signed (0) |
|
|
Tue |
Apr 29 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Tue |
Apr 29 |
Deposit For Upgrades Received (0) |
|
|
Tue |
Apr 29 |
Inspection (Concrete Wall) (1) |
|
|
Wed |
Apr 30 |
Inspection (Conduit Under Slab) (1) |
|
|
Thu |
May 1 |
Inspection (Drain Tile) (0) |
|
|
Thu |
May 1 |
Settlement Agent Confirmed (0) |
|
|
Thu |
May 1 |
Order Tubs / Showers (0) |
|
|
Thu |
May 1 |
Verify Window & Roof Structure (0) |
|
|
Thu |
May 1 |
Install Stairs (0) |
|
|
Thu |
May 1 |
House Number and Status in Window (0) |
|
|
Thu |
May 1 |
Order Appliances (0) |
|
|
Thu |
May 1 |
Patio (0) |
|
|
Thu |
May 1 |
Rough In Microwave Vent (0) |
|
|
Thu |
May 1 |
Inspection (Rough In Plumbing) (1) |
|
|
Fri |
May 2 |
Inspection (Rough In Electric) (1) |
|
|
Mon |
May 5 |
Inspection (Deck Piers) (0) |
|
|
Mon |
May 5 |
Inspection (Framing) (1) * |
|
|
Tue |
May 6 |
Exterior Stone (0) |
|
|
Tue |
May 6 |
Set Electric Meter (0) * |
|
|
Tue |
May 6 |
Inspection (Main Water Line) (0) |
|
|
Tue |
May 6 |
Loan Approval (0) |
|
|
Tue |
May 6 |
Deed Preparation (0) |
|
|
Tue |
May 6 |
Garage Door (0) * |
|
|
Tue |
May 6 |
Mailbox (0) |
|
|
Tue |
May 6 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Tue |
May 6 |
Interior Trim - Paint (1) |
|
|
Wed |
May 7 |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
Wed |
May 7 |
Shoe Moulding (0) |
|
|
Wed |
May 7 |
Set Water Meter (0) * |
|
|
Wed |
May 7 |
Ceiling Fans (0) |
|
|
Wed |
May 7 |
Blower Door Test (1) |
|
|
Thu |
May 8 |
Paint 3 (2) * |
|
|
Mon |
May 12 |
Inspection (Final HVAC) (1) |
|
|
Tue |
May 13 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
May 14 |
Inspection (Final Electric) (1) |
|
|
Thu |
May 15 |
Stain Hardwood Stairs (1) |
|
|
Fri |
May 16 |
Schedule Closing (0) |
|
|
Fri |
May 16 |
Payment for Upgrades (0) |
|
|
Fri |
May 16 |
Keys to Settlement Agent (0) |
|
|
Fri |
May 16 |
Review Settlement Statement (0) |
|
|
Fri |
May 16 |
Jerry Signs Closing Documents (0) |
|
|
Fri |
May 16 |
Request Trash Tote From POA Manager (0) |
|
|
Fri |
May 16 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Patch / Paint at Railing to Loft |
|
|
-- |
-- |
Thorough Cleaning |
|
|
-- |
-- |
Add screen at ridge vent |
|
|
-- |
-- |
Remove furnishings |
Take to 104 |
|
-- |
-- |
Replace water filter in refrigerator. See red light. |
Waiting on Fergusons to supply |
|
-- |
-- |
Touch up staining on the steps and boards leading up to front door |
HOA |
|
-- |
-- |
Paint touch up |
Isaac Monday 8/7 |
|
-- |
-- |
Laminate floor touch up. Several scratches. |
Eric |
|
-- |
-- |
I just trim at miter on attic access panel in loft |
|
|
-- |
-- |
Adjust trim at miter is n up loft panel |
Tom |
|
-- |
-- |
|
|
|
-- |
-- |
Replace filter |
|
|
-- |
-- |
Clean off siding on deck |
Tom |
|
-- |
-- |
Bath countertop in second bathroom |
|
|
-- |
-- |
I just crooked fan in second bathroom |
Tom |
|
-- |
-- |
Water sealant on deck |
Isaac |
|
-- |
-- |
Chain on utility door on deck |
|
|
-- |
-- |
Change door locks |
|
|
-- |
-- |
Install fanin master and not flush mount |
Tom |
|
-- |
-- |
Blue x near front door buyer says floor has too much give |
Eric |
|
-- |
-- |
AC not working properly? |
Ronnie |
|
-- |
-- |
Replace air filter |
Ronnie |
|
-- |
-- |
Remove selections from front bedroom |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) * |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Windows & Doors (0) * |
|
|
-- |
-- |
Roofing (0) * |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) * |
|
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
-- |
-- |
Plumbing Rough In (4) |
|
|
-- |
-- |
Electric Rough In (4) |
|
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) * |
|
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
|
|
-- |
-- |
Paint 1 (1) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
|
|
-- |
-- |
Granite Installation (1) * |
|
|
-- |
-- |
Interior Trim - Install (3) * |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
|
|
-- |
-- |
Paint 2 (3) |
|
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) * |
|
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
|
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
|
|
-- |
-- |
Install Appliances (0) * |
|
|
-- |
-- |
Carpet (2) |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
|
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
|
|
-- |
-- |
Certificate of Occupancy (1) * |
|
|
-- |
-- |
C.O. to Lender (0) |
|
|
-- |
-- |
Buyer Walk Through (1) |
Final Wednesday 8/9 |
|
-- |
-- |
Closing (1) |
THURSDAY, AUG 10 |
|