Paint stair railing; fill and paint holes near handle attachment |
Isaac |
|
-- |
-- |
Install air filter and inspect coil (low airflow) |
Osbaldo or Ronnie? |
|
-- |
-- |
Final cleaning |
Tuesday 6/20 |
|
Tue |
Apr 29 |
Ratified Contract? (0) |
|
|
Tue |
Apr 29 |
$2500 Deposit Received (0) |
|
|
Tue |
Apr 29 |
Association Packet Requested (0) |
|
|
Tue |
Apr 29 |
Association Packet Received (0) |
|
|
Tue |
Apr 29 |
Selections Meeting (0) |
|
|
Tue |
Apr 29 |
Selections Sheet Signed (0) |
|
|
Tue |
Apr 29 |
Amendment for Upgrades (B,S,L,T,BCP) (0) |
|
|
Tue |
Apr 29 |
Deposit For Upgrades Received (0) |
|
|
Tue |
Apr 29 |
Inspection (Concrete Wall) (1) |
|
|
Wed |
Apr 30 |
Inspection (Conduit Under Slab) (1) |
|
|
Thu |
May 1 |
Inspection (Drain Tile) (0) |
|
|
Thu |
May 1 |
Settlement Agent Confirmed (0) |
|
|
Thu |
May 1 |
Order Tubs / Showers (0) |
|
|
Thu |
May 1 |
Verify Window & Roof Structure (0) |
|
|
Thu |
May 1 |
Install Stairs (0) |
|
|
Thu |
May 1 |
House Number and Status in Window (0) |
|
|
Thu |
May 1 |
Order Appliances (0) |
|
|
Thu |
May 1 |
Patio (0) |
|
|
Thu |
May 1 |
Rough In Microwave Vent (0) |
|
|
Thu |
May 1 |
Inspection (Rough In Plumbing) (1) |
|
|
Fri |
May 2 |
Inspection (Rough In Electric) (1) |
|
|
Mon |
May 5 |
Inspection (Deck Piers) (0) |
|
|
Mon |
May 5 |
Inspection (Framing) (1) * |
|
|
Tue |
May 6 |
Exterior Stone (0) |
|
|
Tue |
May 6 |
Set Electric Meter (0) * |
|
|
Tue |
May 6 |
Inspection (Main Water Line) (0) |
|
|
Tue |
May 6 |
Loan Approval (0) |
|
|
Tue |
May 6 |
Deed Preparation (0) |
|
|
Tue |
May 6 |
Garage Door (0) * |
|
|
Tue |
May 6 |
Mailbox (0) |
|
|
Tue |
May 6 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Tue |
May 6 |
Interior Trim - Paint (1) |
|
|
Wed |
May 7 |
Deliver Plumbing / Lighting Fixtures (0) |
|
|
Wed |
May 7 |
Shoe Moulding (0) |
|
|
Wed |
May 7 |
Install Coded Lockbox (add extra keys) (0) |
|
|
Wed |
May 7 |
Set Water Meter (0) * |
|
|
Wed |
May 7 |
Ceiling Fans (0) |
|
|
Wed |
May 7 |
Blower Door Test (1) |
|
|
Thu |
May 8 |
Paint 3 (2) * |
|
|
Mon |
May 12 |
Appraiser Confirms Construction Completion (0) |
|
|
Mon |
May 12 |
Inspection (Final HVAC) (1) |
|
|
Tue |
May 13 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
May 14 |
Inspection (Final Electric) (1) |
|
|
Thu |
May 15 |
Stain Hardwood Stairs (1) |
|
|
Fri |
May 16 |
C.O. to Lender (0) |
|
|
Fri |
May 16 |
Schedule Closing (0) |
|
|
Fri |
May 16 |
Buyer Walk Through (1) |
June 26 |
|
Mon |
May 19 |
Payment for Upgrades (0) |
|
|
Mon |
May 19 |
Keys to Settlement Agent (0) |
|
|
Mon |
May 19 |
Review Settlement Statement (0) |
|
|
Mon |
May 19 |
Jerry Signs Closing Documents (0) |
|
|
Mon |
May 19 |
Request Trash Tote From POA Manager (0) |
|
|
Mon |
May 19 |
Closing (1) |
|
|
Tue |
May 20 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Finalize Selections; |
Kate will finalize; |
|
-- |
-- |
Repaint in wish. Leave hall bath and laundry soft leather |
|
|
-- |
-- |
Missing track light |
7/25:K: there- needs to be installed |
|
-- |
-- |
Finish installing lights |
7/25:K: kitchen pendant |
|
-- |
-- |
Trim in baths and laundry |
|
|
-- |
-- |
Missing cabinet piece |
|
|
-- |
-- |
Clean up outside front door |
|
|
-- |
-- |
Shoe mold in kitchen and living room |
|
|
-- |
-- |
Few odds and ends |
|
|
-- |
-- |
Install track light above kitchen |
|
|
-- |
-- |
Install missing heat register in closet |
|
|
-- |
-- |
Remove furnishings |
|
|
-- |
-- |
Repair chipped fascia on cabinet under sink |
Gabby |
|
-- |
-- |
Finish screwing in cabinet to wall |
Osbaldo |
|
-- |
-- |
Connect and test ice maker |
Osbaldo |
|
-- |
-- |
Adjust upper cabinet that does not close properly |
Gabby |
|
-- |
-- |
Paint stair railing |
|
|
-- |
-- |
Fill and paint holes in trim and cap trim at top of stairs |
|
|
-- |
-- |
Cap trim at top of stairwell |
Osbaldo |
|
-- |
-- |
Install GFCI outlet in the master bathroom |
Osbaldo |
|
-- |
-- |
Adjust back sliding glass door to latch properly |
Osbaldo |
|
-- |
-- |
Install drain for overflow pan for washing machine |
Osbaldo |
|
-- |
-- |
Touch up paint throughout |
Isaac |
|
-- |
-- |
Move belongings in on June 29? |
|
|
-- |
-- |
Building Permit (30) |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) |
|
|
-- |
-- |
Order Windows & Doors (0) |
|
|
-- |
-- |
Stake Out Home (1) |
|
|
-- |
-- |
Excavate (2) |
|
|
-- |
-- |
Inspection (Footers) (1) |
|
|
-- |
-- |
Pour Footers (1) * |
|
|
-- |
-- |
Set Forms (2) |
|
|
-- |
-- |
Pour Foundation Walls (1) |
|
|
-- |
-- |
Plumb Slab (2) |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) |
|
|
-- |
-- |
Prepare Slab (1) |
|
|
-- |
-- |
Inspection (Slab) (1) |
|
|
-- |
-- |
Pour Slab (1) * |
|
|
-- |
-- |
Framing I (9) |
|
|
-- |
-- |
Order Steps (0) |
|
|
-- |
-- |
Framing II (8) |
|
|
-- |
-- |
Framing III (8) * |
|
|
-- |
-- |
Windows & Doors (0) * |
|
|
-- |
-- |
Roofing (0) * |
|
|
-- |
-- |
Order Cabinets (0) |
|
|
-- |
-- |
Deck (0) |
|
|
-- |
-- |
Gutters (0) |
|
|
-- |
-- |
Driveway (0) * |
|
|
-- |
-- |
Privacy Divider / Fence (0) |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) |
|
|
-- |
-- |
HVAC Rough In (4) |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) |
|
|
-- |
-- |
Plumbing Rough In (4) |
|
|
-- |
-- |
Electric Rough In (4) |
|
|
-- |
-- |
Exterior Vinyl (0) * |
|
|
-- |
-- |
Insulation (2) * |
|
|
-- |
-- |
Inspection (Insulation) (1) |
|
|
-- |
-- |
Inspection (Electric Service) (0) |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) |
|
|
-- |
-- |
Order Interior Doors & Trim (0) |
|
|
-- |
-- |
Drywall (Hang) (4) * |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * |
|
|
-- |
-- |
Paint 1 (1) |
|
|
-- |
-- |
House Numbers (0) |
|
|
-- |
-- |
Cabinet Installation (2) * |
Deliver May 13, Install May 16 |
|
-- |
-- |
Granite Installation (1) * |
June 8 |
|
-- |
-- |
Interior Trim - Install (3) * |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * |
|
|
-- |
-- |
Luxury Vinyl Tile (0) |
K: 7/4 in process (not using spacers/crooked)? |
|
-- |
-- |
Paint 2 (3) |
|
|
-- |
-- |
Cover Floors (1) |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) * |
In process |
|
-- |
-- |
Pay Water / Sewer Taps (0) |
|
|
-- |
-- |
Electric Trim Out (3) |
|
|
-- |
-- |
HVAC Trim Out (1) |
|
|
-- |
-- |
Plumbing Trim Out (2) |
7/25: plumbing still needs to be installed |
|
-- |
-- |
Install Appliances (0) * |
|
|
-- |
-- |
Carpet (2) |
|
|
-- |
-- |
Inspection (Final Building) (2) * |
Mindy will check |
|
-- |
-- |
Pre Walk Through (0) |
|
|
-- |
-- |
Cleaning (1) |
|
|
-- |
-- |
Certificate of Occupancy (1) * |
Obtain copy |
|