1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 39  ::  1665 Bald Eagle Circle
[ BUILD: 16060127 ]       [ ELEC: 16080113 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Further Punch Out? Tom to visit; Sue met with Tom in January? Still no action as of Mar 27?
Thu    Nov 28      Ratified Contract? (0)      
Thu    Nov 28      $2500 Deposit Received (0)      
Thu    Nov 28      Association Packet Requested (0)      
Thu    Nov 28      Association Packet Received (0)      
Thu    Nov 28      Selections Meeting (0)      
Thu    Nov 28      Selections Sheet Signed (0)      
Thu    Nov 28      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Thu    Nov 28      Deposit For Upgrades Received (0)      
Thu    Nov 28      Inspection (Concrete Wall) (1)      
Fri    Nov 29      Inspection (Conduit Under Slab) (1)      
Mon    Dec 2      Inspection (Drain Tile) (0)      
Mon    Dec 2      Settlement Agent Confirmed (0)      
Mon    Dec 2      Verify Window & Roof Structure (0)      
Mon    Dec 2      Order Appliances (0)      
Mon    Dec 2      Patio (0)      
Mon    Dec 2      Rough In Microwave Vent (0)      
Mon    Dec 2      Inspection (Rough In Plumbing) (1)      
Tue    Dec 3      Inspection (Rough In Electric) (1)      
Wed    Dec 4      Inspection (Deck Piers) (0)      
Wed    Dec 4      Inspection (Framing) (1)      
Thu    Dec 5      Exterior Stone (0)      
Thu    Dec 5      Set Electric Meter (0)      
Thu    Dec 5      Inspection (Main Water Line) (0)      
Thu    Dec 5      Loan Approval (0)      
Thu    Dec 5      Deed Preparation (0)      
Thu    Dec 5      Mailbox (0)      
Thu    Dec 5      Interior Trim - Paint (1)      
Fri    Dec 6      Ceiling Fans (0)      
Fri    Dec 6      Blower Door Test (1)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Stain Hardwood Stairs (1)      
Fri    Dec 13      Request Trash Tote From POA Manager (0)      
--   --   Review Contract in Operations Meeting
--   --   Review master bath configuration
--   --   Determine standard hardwood flooring with Jerry
--   --   Gabby will mark off kitchen on Mon, Nov 20
--   --   Did you check with buyer on brick color?
--   --   Need trash can on site. Needs to be cleaned up
--   --   Valley Renovators for trim- Tom call to schedule
--   --   Trim around garage door into house
--   --   Who is trimming stairs
--   --   When fireplace being installed?
--   --   Fireplace? Install mantle today
--   --   Check with buyer, hardwood or hearth to fireplace?
--   --   Replace cracked hearth
--   --   Install stove after closing (back ordered)
--   --   Front Door & Garage Door Color Benjamin Moore, Bittersweet Chocolate 2114-10
--   --   Paint touch up Mar 6
--   --   Install bathroom accessories Monday 2/27
--   --   Finish installing closet shelving Monday 2/27
--   --   Paint and stain steps and risers Wednesday and Thursday, March 1 and 2
--   --   Yellow tape everywhere on floors Eric, Tues 2/28
--   --   Set screen doors
--   --   Patch hole in basement ceiling Isaac, Wednesday, March 1
--   --   Hang bathroom mirrors Monday 2/27
--   --   Wrap
--   --   Wrap posts
--   --   Front door weatherstripping
--   --   Sagging patio door
--   --   Scratched glass on main level door On order
--   --   Clean up scratch on deck boards Premiere Vinyl will buff it out;
--   --   Straighten floor register in living room
--   --   Straighten floor register in living room
--   --   Drywall repairs pendant lights, basement, garage, tile shower
--   --   Install garage door trim Greg will coordinate this;
--   --   Install gutters at back of home
--   --   Install outside light
--   --   Scratch across decking boards
--   --   Need lock box
--   --   Cau
--   --   Install missing fascia board on deck
--   --   Missing trim on fireplace
--   --   Install trim at patio door
--   --   Install door threshold on patio door
--   --   Install missing piece of trim at fireplace When doing H-24 fireplace
--   --   Low voltage trim out Tom
--   --   Carpet stain at the bottom of the stairs Eric
--   --   Replace scratched deck boards Premiere Vinyl
-- -- Building Permit (30)      
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1)      
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *        Sept 6
-- -- Framing I (9)       9/15 complete?
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)       10/3
-- -- Framing III (8) *        10/10
-- -- Install Stairs (0)      
-- -- Windows & Doors (0)      
-- -- House Number and Status in Window (0)      
-- -- Roofing (0)      
-- -- Order Cabinets (0)      
-- -- Deck (0)       Finished by 2/20/2017;
-- -- Gutters (0)       Waiting on deck
-- -- Driveway (0)       Jan 30 - Patio
-- -- Privacy Divider / Fence (0)      
-- -- Sod / Seed / Landscaping (0)       2/20/2017
-- -- HVAC Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Plumbing Rough In (4)       11/14 - starting
-- -- Electric Rough In (4)      
-- -- Exterior Vinyl (0) *        11/10: Stucco starting soon
-- -- Insulation (2)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)       Line is buried, waiting on connection from HEC;
-- -- Inspection (Main Sewer Line) (0)       Need to dig a ditch
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        12/8 materials on site
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        12/19 nearly complete
-- -- Paint 1 (1)      
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *        Delivered Jan 10; Installed Jan 10-13;
-- -- Granite Installation (1) *        Tues, Feb 14
-- -- Interior Trim - Install (3)       One days work- after flooring
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *       
-- -- Luxury Vinyl Tile (0)       Will be complete by 2/2
-- -- Paint 2 (3)       Nearly complete
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)      
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0)       Wednesday Feb 1
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)       Ben is getting a check to the City
-- -- Set Water Meter (0)      
-- -- Electric Trim Out (3)       2/27- nearly complete
-- -- HVAC Trim Out (1)       Need to set outside unit
-- -- Plumbing Trim Out (2)       Done 2/20/2017
-- -- Install Appliances (0) *        Install Feb 17
-- -- Paint 3 (2) *       
-- -- Carpet (2)       Tues, Feb 14
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Mon, Feb 27
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)      
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1)       Thursday, March 30, 11:00 AM
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)      
-- -- Remove Coded Lockbox (0)