CRITICAL PATH
Sat
May 16
Building Permit
(30)
*
Fri
Jun 26
Order Roof & Floor Trusses
(1)
Order Windows & Doors
(0)
Mon
Jun 29
Inspection (Concrete Wall)
(1)
Tue
Jun 30
Set Forms
(2)
Thu
Jul 2
Pour Foundation Walls
(1)
Fri
Jul 3
Plumb Slab
(2)
Tue
Jul 7
Inspection (Plumbing Under Slab)
(1)
Wed
Jul 8
Inspection (Conduit Under Slab)
(1)
Thu
Jul 9
Prepare Slab
(1)
Fri
Jul 10
Inspection (Slab)
(1)
Inspection (Drain Tile)
(0)
Mon
Jul 13
Pour Slab
(1)
*
Tue
Jul 14
Framing I
(9)
Order Steps
(0)
Order Tubs / Showers
(0)
Mon
Jul 27
Framing II
(8)
Thu
Aug 6
Framing III
(8)
*
Verify Window & Roof Structure
(0)
Install Stairs
(0)
*
Windows & Doors
(0)
*
House Number and Status in Window
(0)
Roofing
(0)
*
Order Cabinets
(0)
Order Appliances
(0)
Deck
(0)
Gutters
(0)
Driveway
(0)
*
Patio
(0)
Sod / Seed / Landscaping
(0)
Tue
Aug 18
HVAC Rough In
(4)
Rough In Microwave Vent
(0)
Mon
Aug 24
Plumbing Rough In
(4)
Fri
Aug 28
Electric Rough In
(4)
Thu
Sep 3
Inspection (Rough In HVAC)
(1)
Fri
Sep 4
Inspection (Rough In Plumbing)
(1)
Mon
Sep 7
Inspection (Rough In Electric)
(1)
Tue
Sep 8
Inspection (Framing)
(1)
*
Inspection (Deck Piers)
(0)
Exterior Vinyl
(0)
*
Exterior Stone
(0)
Wed
Sep 9
Insulation
(2)
*
Fri
Sep 11
Inspection (Insulation)
(1)
Inspection (Electric Service)
(0)
Set Electric Meter
(0)
*
Inspection (Main Sewer Line)
(0)
Inspection (Main Water Line)
(0)
Order Interior Doors & Trim
(0)
Mon
Sep 14
Drywall (Hang)
(4)
*
Fri
Sep 18
Drywall (Tape, Block, Skim, Sand)
(6)
*
Mon
Sep 28
Paint 1
(1)
House Numbers
(0)
Mailbox
(0)
Tue
Sep 29
Cabinet Installation
(2)
*
Thu
Oct 1
Granite Installation
(1)
*
Fri
Oct 2
Interior Trim - Install
(3)
*
Order Plumbing / Lighting Fixtures
(0)
Wed
Oct 7
Interior Trim - Paint
(1)
Thu
Oct 8
Luxury Vinyl Plank
(3)
*
Luxury Vinyl Tile
(0)
Tue
Oct 13
Paint 2
(3)
Cover Floors
(0)
Deliver Plumbing / Lighting Fixtures
(0)
Shoe Moulding
(0)
Fri
Oct 16
Shelving, Door Knobs, Fire Extinguisher
(1)
*
Install Coded Lockbox (add extra keys)
(0)
Pay Water / Sewer Taps
(0)
Mon
Oct 19
Set Water Meter
(1)
*
Tue
Oct 20
Electric Trim Out
(3)
*
Ceiling Fans
(0)
Fri
Oct 23
HVAC Trim Out
(1)
*
Mon
Oct 26
Blower Door Test
(1)
Tue
Oct 27
Plumbing Trim Out
(2)
*
Install Appliances
(0)
*
Thu
Oct 29
Paint 3
(2)
*
Mon
Nov 2
Carpet
(2)
Inspection (Final HVAC)
(0)
Inspection (Final Plumbing)
(0)
Inspection (Final Electric)
(0)
Wed
Nov 4
Inspection (Final Building)
(4)
*
Pre Walk Through
(0)
Tue
Nov 10
Stain Hardwood Stairs
(1)
*
Wed
Nov 11
Cleaning
(1)
Thu
Nov 12
Certificate of Occupancy
(1)
*
Keys to Settlement Agent
(0)
Request Trash Tote From POA Manager
(0)
Fri
Nov 13
Closing
(1)
Remove Coded Lockbox
(0)
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
--
--
Ratified Contract?
(0) 09.25.2025
--
--
$2500 Deposit Received
(0) 09.25.2025
--
--
Association Packet Requested
(0) 09.25.2025
--
--
Association Packet Received
(0) 09.25.2025
--
--
Selections Meeting
(0) 09.25.2025
--
--
Selections Sheet Signed
(0) 09.25.2025
--
--
Amendment for Upgrades (B,S,L,T,BCP)
(0) 09.25.2025
--
--
Deposit For Upgrades Received
(0) 09.25.2025
--
--
Stake Out Home
(1) 10.09.2025
--
--
Excavate
(2) 10.09.2025
--
--
Inspection (Footers)
(1) 10.09.2025
--
--
Pour Footers
(1)
*
05.08.2026
--
--
Settlement Agent Confirmed
(0) 09.25.2025
--
--
Privacy Divider / Fence
(0)
*
09.25.2025
--
--
Loan Approval
(0) 09.25.2025
--
--
Deed Preparation
(0) 09.25.2025
--
--
Garage Door
(0) 09.25.2025
--
--
Appraiser Confirms Construction Completion
(0) 09.25.2025
--
--
C.O. to Lender
(0) 09.25.2025
--
--
Schedule Closing
(0) 09.25.2025
--
--
Buyer Walk Through
(1)
*
09.25.2025
--
--
Payment for Upgrades
(0) 09.25.2025
--
--
Review Settlement Statement
(0) 09.25.2025
--
--
Jerry Signs Closing Documents