VILLAS - 507-202  ::  507 Roman Way #202
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
Wed    Mar 25      Building Permit (30) *       
Wed    May 6      Order Roof & Floor Trusses (1)      
    Order Windows & Doors (0)      
Thu    May 7      Inspection (Concrete Wall) (1)      
Fri    May 8      Set Forms (2)      
Tue    May 12      Pour Foundation Walls (1)      
Wed    May 13      Plumb Slab (2)      
Fri    May 15      Inspection (Plumbing Under Slab) (1)      
Mon    May 18      Inspection (Conduit Under Slab) (1)      
Tue    May 19      Prepare Slab (1)      
Wed    May 20      Inspection (Slab) (1)      
    Inspection (Drain Tile) (0)      
Thu    May 21      Pour Slab (1) *       
Fri    May 22      Framing I (9)      
    Order Steps (0)      
    Order Tubs / Showers (0)      
Thu    Jun 4      Framing II (8)      
Tue    Jun 16      Framing III (8) *       
    Verify Window & Roof Structure (0)      
    Install Stairs (0) *       
    Windows & Doors (0) *       
    House Number and Status in Window (0)      
    Roofing (0) *       
    Order Cabinets (0)      
    Order Appliances (0)      
    Deck (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Sod / Seed / Landscaping (0)      
Fri    Jun 26      HVAC Rough In (4)      
    Rough In Microwave Vent (0)      
Thu    Jul 2      Plumbing Rough In (4)      
Wed    Jul 8      Electric Rough In (4)      
Tue    Jul 14      Inspection (Rough In HVAC) (1)      
Wed    Jul 15      Inspection (Rough In Plumbing) (1)      
Thu    Jul 16      Inspection (Rough In Electric) (1)      
Fri    Jul 17      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Vinyl (0) *       
    Exterior Stone (0)      
Mon    Jul 20      Insulation (2) *       
Wed    Jul 22      Inspection (Insulation) (1)      
    Inspection (Electric Service) (0)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Thu    Jul 23      Drywall (Hang) (4) *       
Wed    Jul 29      Drywall (Tape, Block, Skim, Sand) (6) *       
Thu    Aug 6      Paint 1 (1)      
    House Numbers (0)      
    Mailbox (0)      
Fri    Aug 7      Cabinet Installation (2) *       
Tue    Aug 11      Granite Installation (1) *       
Wed    Aug 12      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Mon    Aug 17      Interior Trim - Paint (1)      
Tue    Aug 18      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Fri    Aug 21      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Wed    Aug 26      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Thu    Aug 27      Set Water Meter (1) *       
Fri    Aug 28      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Wed    Sep 2      HVAC Trim Out (1) *       
Thu    Sep 3      Blower Door Test (1)      
Fri    Sep 4      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Tue    Sep 8      Paint 3 (2) *       
Thu    Sep 10      Carpet (2)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Mon    Sep 14      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Fri    Sep 18      Stain Hardwood Stairs (1) *       
Mon    Sep 21      Cleaning (1)      
Tue    Sep 22      Certificate of Occupancy (1) *       
    Keys to Settlement Agent (0)      
    Request Trash Tote From POA Manager (0)      
Wed    Sep 23      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  09.25.2025    
-- -- $2500 Deposit Received (0)  09.25.2025    
-- -- Association Packet Requested (0)  09.25.2025    
-- -- Association Packet Received (0)  09.25.2025    
-- -- Selections Meeting (0)  09.25.2025    
-- -- Selections Sheet Signed (0)  09.25.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.25.2025    
-- -- Deposit For Upgrades Received (0)  09.25.2025    
-- -- Stake Out Home (1)  10.09.2025    
-- -- Excavate (2)  10.09.2025    
-- -- Inspection (Footers) (1)  10.09.2025    
-- -- Pour Footers (1) *   10.09.2025    
-- -- Settlement Agent Confirmed (0)  09.25.2025    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Garage Door (0)  09.25.2025    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025