Tue    Feb 3      Building Permit (30) *       
Tue    Mar 17      Order Roof & Floor Trusses (1)      
    Order Windows & Doors (0)      
Wed    Mar 18      Inspection (Concrete Wall) (1)      
Thu    Mar 19      Set Forms (2)      
Mon    Mar 23      Pour Foundation Walls (1)      
Tue    Mar 24      Plumb Slab (2)      
Thu    Mar 26      Inspection (Plumbing Under Slab) (1)      
Fri    Mar 27      Inspection (Conduit Under Slab) (1)      
Mon    Mar 30      Prepare Slab (1)      
Tue    Mar 31      Inspection (Slab) (1)      
    Inspection (Drain Tile) (0)      
Wed    Apr 1      Pour Slab (1) *       
Thu    Apr 2      Framing I (9)      
    Order Steps (0)      
    Order Tubs / Showers (0)      
Wed    Apr 15      Framing II (8)      
Mon    Apr 27      Framing III (8) *       
    Verify Window & Roof Structure (0)      
    Install Stairs (0) *       
    Windows & Doors (0) *       
    House Number and Status in Window (0)      
    Roofing (0) *       
    Order Cabinets (0)      
    Order Appliances (0)      
    Deck (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Sod / Seed / Landscaping (0)      
Thu    May 7      HVAC Rough In (4)      
    Rough In Microwave Vent (0)      
Wed    May 13      Plumbing Rough In (4)      
Tue    May 19      Electric Rough In (4)      
Mon    May 25      Inspection (Rough In HVAC) (1)      
Tue    May 26      Inspection (Rough In Plumbing) (1)      
Wed    May 27      Inspection (Rough In Electric) (1)      
Thu    May 28      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Vinyl (0) *       
    Exterior Stone (0)      
Fri    May 29      Insulation (2) *       
Tue    Jun 2      Inspection (Insulation) (1)      
    Inspection (Electric Service) (0)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Wed    Jun 3      Drywall (Hang) (4) *       
Tue    Jun 9      Drywall (Tape, Block, Skim, Sand) (6) *       
Wed    Jun 17      Paint 1 (1)      
    House Numbers (0)      
    Mailbox (0)      
Thu    Jun 18      Cabinet Installation (2) *       
Mon    Jun 22      Granite Installation (1) *       
Tue    Jun 23      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Fri    Jun 26      Interior Trim - Paint (1)      
Mon    Jun 29      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Thu    Jul 2      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Tue    Jul 7      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Wed    Jul 8      Set Water Meter (1) *       
Thu    Jul 9      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Tue    Jul 14      HVAC Trim Out (1) *       
Wed    Jul 15      Blower Door Test (1)      
Thu    Jul 16      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Mon    Jul 20      Paint 3 (2) *       
Wed    Jul 22      Carpet (2)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Fri    Jul 24      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Thu    Jul 30      Stain Hardwood Stairs (1) *       
Fri    Jul 31      Cleaning (1)      
Mon    Aug 3      Certificate of Occupancy (1) *       
    Keys to Settlement Agent (0)      
    Request Trash Tote From POA Manager (0)      
Tue    Aug 4      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  09.25.2025    
-- -- $2500 Deposit Received (0)  09.25.2025    
-- -- Association Packet Requested (0)  09.25.2025    
-- -- Association Packet Received (0)  09.25.2025    
-- -- Selections Meeting (0)  09.25.2025    
-- -- Selections Sheet Signed (0)  09.25.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.25.2025    
-- -- Deposit For Upgrades Received (0)  09.25.2025    
-- -- Stake Out Home (1)  10.09.2025    
-- -- Excavate (2)  10.09.2025    
-- -- Inspection (Footers) (1)  10.09.2025    
-- -- Pour Footers (1) *   10.09.2025    
-- -- Settlement Agent Confirmed (0)  09.25.2025    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Garage Door (0)  09.25.2025    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025