VILLAS - 507  ::  507 Roman Way
[ BUILD: 507 Approved Plans ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
Sat    May 16      Building Permit (30) *       
Fri    Jun 26      Order Roof & Floor Trusses (1)      
    Order Windows & Doors (0)      
Mon    Jun 29      Stake Out Home (1)      
Tue    Jun 30      Excavate (2)      
Thu    Jul 2      Inspection (Footers) (1)      
Fri    Jul 3      Inspection (Concrete Wall) (1)      
Mon    Jul 6      Pour Footers (1) *       
Tue    Jul 7      Set Forms (2)      
Thu    Jul 9      Pour Foundation Walls (1)      
Fri    Jul 10      Plumb Slab (2)      
Tue    Jul 14      Inspection (Plumbing Under Slab) (1)      
Wed    Jul 15      Inspection (Conduit Under Slab) (1)      
Thu    Jul 16      Prepare Slab (1)      
Fri    Jul 17      Inspection (Slab) (1)      
    Inspection (Drain Tile) (0)      
Mon    Jul 20      Pour Slab (1) *       
    Settlement Agent Confirmed (0)      
Tue    Jul 21      Framing I (9)      
    Order Steps (0)      
    Order Tubs / Showers (0)      
Mon    Aug 3      Framing II (8)      
Thu    Aug 13      Framing III (8) *       
    Verify Window & Roof Structure (0)      
    Install Stairs (0) *       
    Windows & Doors (0) *       
    House Number and Status in Window (0)      
    Roofing (0) *       
    Order Cabinets (0)      
    Order Appliances (0)      
    Deck (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Privacy Divider / Fence (0) *       
    Sod / Seed / Landscaping (0)      
Tue    Aug 25      HVAC Rough In (4)      
    Rough In Microwave Vent (0)      
Mon    Aug 31      Plumbing Rough In (4)      
Fri    Sep 4      Electric Rough In (4)      
Thu    Sep 10      Inspection (Rough In HVAC) (1)      
Fri    Sep 11      Inspection (Rough In Plumbing) (1)      
Mon    Sep 14      Inspection (Rough In Electric) (1)      
Tue    Sep 15      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Vinyl (0) *       
    Exterior Stone (0)      
Wed    Sep 16      Insulation (2) *       
Fri    Sep 18      Inspection (Insulation) (1)      
    Inspection (Electric Service) (0)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Mon    Sep 21      Drywall (Hang) (4) *       
    Loan Approval (0)      
    Deed Preparation (0)      
Fri    Sep 25      Drywall (Tape, Block, Skim, Sand) (6) *       
Mon    Oct 5      Paint 1 (1)      
    Garage Door (0)      
    House Numbers (0)      
    Mailbox (0)      
Tue    Oct 6      Cabinet Installation (2) *       
Thu    Oct 8      Granite Installation (1) *       
Fri    Oct 9      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Wed    Oct 14      Interior Trim - Paint (1)      
Thu    Oct 15      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Tue    Oct 20      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Fri    Oct 23      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Mon    Oct 26      Set Water Meter (1) *       
Tue    Oct 27      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Fri    Oct 30      HVAC Trim Out (1) *       
Mon    Nov 2      Blower Door Test (1)      
Tue    Nov 3      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Thu    Nov 5      Paint 3 (2) *       
Mon    Nov 9      Carpet (2)      
    Appraiser Confirms Construction Completion (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Wed    Nov 11      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Tue    Nov 17      Stain Hardwood Stairs (1) *       
Wed    Nov 18      Cleaning (1)      
Thu    Nov 19      Certificate of Occupancy (1) *       
    C.O. to Lender (0)      
    Schedule Closing (0)      
Fri    Nov 20      Buyer Walk Through (1) *       
    Payment for Upgrades (0)      
    Keys to Settlement Agent (0)      
    Review Settlement Statement (0)      
    Jerry Signs Closing Documents (0)      
    Request Trash Tote From POA Manager (0)      
Mon    Nov 23      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED