VILLAS - 507  ::  507 Roman Way
[ BUILD: 507 Approved Plans ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Sunday (Jun 28)    show all photos
TO DO
---
UPGRADES
---
CRITICAL PATH
    Order Steps (0)      
    Install Stairs (0) *       
    Windows & Doors (0) *   06.12.2026    
    House Number and Status in Window (0)      
    Gutters (0)      
    Sod / Seed / Landscaping (0)      
Wed    Jul 1      Plumbing Rough In (4)      
Tue    Jul 7      Electric Rough In (4)      
Mon    Jul 13      Inspection (Rough In HVAC) (1)      
Tue    Jul 14      Inspection (Rough In Plumbing) (1)      
Wed    Jul 15      Inspection (Rough In Electric) (1)      
Thu    Jul 16      Inspection (Framing) (1) *       
    Exterior Stone (0)      
Fri    Jul 17      Insulation (2) *       
Tue    Jul 21      Inspection (Insulation) (1)      
    Inspection (Electric Service) (0)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Wed    Jul 22      Drywall (Hang) (4) *       
    Loan Approval (0)      
    Deed Preparation (0)      
Tue    Jul 28      Drywall (Tape, Block, Skim, Sand) (6) *       
Wed    Aug 5      Paint 1 (1)      
    Garage Door (0)      
    House Numbers (0)      
    Mailbox (0)      
Thu    Aug 6      Cabinet Installation (2) *       
Mon    Aug 10      Granite Installation (1) *       
Tue    Aug 11      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Fri    Aug 14      Interior Trim - Paint (1)      
Mon    Aug 17      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Thu    Aug 20      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Tue    Aug 25      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Wed    Aug 26      Set Water Meter (1) *       
Thu    Aug 27      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Tue    Sep 1      HVAC Trim Out (1) *       
Wed    Sep 2      Blower Door Test (1)      
Thu    Sep 3      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Mon    Sep 7      Paint 3 (2) *       
Wed    Sep 9      Carpet (2)      
    Appraiser Confirms Construction Completion (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Fri    Sep 11      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Thu    Sep 17      Stain Hardwood Stairs (1) *       
Fri    Sep 18      Cleaning (1)      
Mon    Sep 21      Certificate of Occupancy (1) *       
    C.O. to Lender (0)      
    Schedule Closing (0)      
Tue    Sep 22      Buyer Walk Through (1) *       
    Payment for Upgrades (0)      
    Keys to Settlement Agent (0)      
    Review Settlement Statement (0)      
    Jerry Signs Closing Documents (0)      
    Request Trash Tote From POA Manager (0)      
Wed    Sep 23      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  06.12.2026    
-- -- $2500 Deposit Received (0)  06.12.2026    
-- -- Association Packet Requested (0)  06.12.2026    
-- -- Association Packet Received (0)  06.12.2026    
-- -- Selections Meeting (0)  06.12.2026    
-- -- Selections Sheet Signed (0)  06.12.2026    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  06.12.2026    
-- -- Deposit For Upgrades Received (0)  06.12.2026    
-- -- Building Permit (30) *   06.12.2026    
-- -- Order Roof & Floor Trusses (1)  06.12.2026    
-- -- Order Windows & Doors (0)  06.15.2026    
-- -- Stake Out Home (1)  06.12.2026    
-- -- Excavate (2)  06.12.2026    
-- -- Inspection (Footers) (1)  06.12.2026    
-- -- Inspection (Concrete Wall) (1)  06.12.2026    
-- -- Pour Footers (1) *   06.12.2026    
-- -- Set Forms (2)  06.12.2026    
-- -- Pour Foundation Walls (1)  06.12.2026    
-- -- Plumb Slab (2)  06.12.2026    
-- -- Inspection (Plumbing Under Slab) (1)  06.12.2026    
-- -- Inspection (Conduit Under Slab) (1)  06.12.2026    
-- -- Prepare Slab (1)  06.12.2026    
-- -- Inspection (Slab) (1)  06.12.2026    
-- -- Inspection (Drain Tile) (0)  06.12.2026    
-- -- Pour Slab (1) *   06.12.2026    
-- -- Settlement Agent Confirmed (0)  06.12.2026    
-- -- Framing I (9)  06.12.2026    
-- -- Order Tubs / Showers (0)  06.22.2026    
-- -- Framing II (8)  06.12.2026    
-- -- Framing III (8) *   06.18.2026    
-- -- Verify Window & Roof Structure (0)  06.12.2026    
-- -- Roofing (0) *   06.18.2026    
-- -- Order Cabinets (0)  06.12.2026    
-- -- Order Appliances (0)  06.12.2026    
-- -- Deck (0)  06.22.2026    
-- -- Driveway (0) *   06.12.2026    
-- -- Patio (0)  06.12.2026    
-- -- Privacy Divider / Fence (0) *   06.12.2026    
-- -- HVAC Rough In (4)  06.29.2026    
-- -- Rough In Microwave Vent (0)  06.12.2026    
-- -- Inspection (Deck Piers) (0)  06.12.2026    
-- -- Exterior Vinyl (0) *   06.12.2026