VILLAS - 507 :: 507 Roman Way
[ BUILD:
507 Approved Plans
]
CRITICAL PATH
|
INSPECTIONS
|
FLOOR PLANS
|
SELECTIONS
|
SPECS
|
CHANGES
|
NHS
Sunday (Jun 28)
show all photos
TO DO
---
UPGRADES
---
CRITICAL PATH
Order Steps
(0)
Install Stairs
(0)
*
Windows & Doors
(0)
*
06.12.2026
House Number and Status in Window
(0)
Gutters
(0)
Sod / Seed / Landscaping
(0)
Wed
Jul 1
Plumbing Rough In
(4)
Tue
Jul 7
Electric Rough In
(4)
Mon
Jul 13
Inspection (Rough In HVAC)
(1)
Tue
Jul 14
Inspection (Rough In Plumbing)
(1)
Wed
Jul 15
Inspection (Rough In Electric)
(1)
Thu
Jul 16
Inspection (Framing)
(1)
*
Exterior Stone
(0)
Fri
Jul 17
Insulation
(2)
*
Tue
Jul 21
Inspection (Insulation)
(1)
Inspection (Electric Service)
(0)
Set Electric Meter
(0)
*
Inspection (Main Sewer Line)
(0)
Inspection (Main Water Line)
(0)
Order Interior Doors & Trim
(0)
Wed
Jul 22
Drywall (Hang)
(4)
*
Loan Approval
(0)
Deed Preparation
(0)
Tue
Jul 28
Drywall (Tape, Block, Skim, Sand)
(6)
*
Wed
Aug 5
Paint 1
(1)
Garage Door
(0)
House Numbers
(0)
Mailbox
(0)
Thu
Aug 6
Cabinet Installation
(2)
*
Mon
Aug 10
Granite Installation
(1)
*
Tue
Aug 11
Interior Trim - Install
(3)
*
Order Plumbing / Lighting Fixtures
(0)
Fri
Aug 14
Interior Trim - Paint
(1)
Mon
Aug 17
Luxury Vinyl Plank
(3)
*
Luxury Vinyl Tile
(0)
Thu
Aug 20
Paint 2
(3)
Cover Floors
(0)
Deliver Plumbing / Lighting Fixtures
(0)
Shoe Moulding
(0)
Tue
Aug 25
Shelving, Door Knobs, Fire Extinguisher
(1)
*
Install Coded Lockbox (add extra keys)
(0)
Pay Water / Sewer Taps
(0)
Wed
Aug 26
Set Water Meter
(1)
*
Thu
Aug 27
Electric Trim Out
(3)
*
Ceiling Fans
(0)
Tue
Sep 1
HVAC Trim Out
(1)
*
Wed
Sep 2
Blower Door Test
(1)
Thu
Sep 3
Plumbing Trim Out
(2)
*
Install Appliances
(0)
*
Mon
Sep 7
Paint 3
(2)
*
Wed
Sep 9
Carpet
(2)
Appraiser Confirms Construction Completion
(0)
Inspection (Final HVAC)
(0)
Inspection (Final Plumbing)
(0)
Inspection (Final Electric)
(0)
Fri
Sep 11
Inspection (Final Building)
(4)
*
Pre Walk Through
(0)
Thu
Sep 17
Stain Hardwood Stairs
(1)
*
Fri
Sep 18
Cleaning
(1)
Mon
Sep 21
Certificate of Occupancy
(1)
*
C.O. to Lender
(0)
Schedule Closing
(0)
Tue
Sep 22
Buyer Walk Through
(1)
*
Payment for Upgrades
(0)
Keys to Settlement Agent
(0)
Review Settlement Statement
(0)
Jerry Signs Closing Documents
(0)
Request Trash Tote From POA Manager
(0)
Wed
Sep 23
Closing
(1)
Remove Coded Lockbox
(0)
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
--
--
Ratified Contract?
(0) 06.12.2026
--
--
$2500 Deposit Received
(0) 06.12.2026
--
--
Association Packet Requested
(0) 06.12.2026
--
--
Association Packet Received
(0) 06.12.2026
--
--
Selections Meeting
(0) 06.12.2026
--
--
Selections Sheet Signed
(0) 06.12.2026
--
--
Amendment for Upgrades (B,S,L,T,BCP)
(0) 06.12.2026
--
--
Deposit For Upgrades Received
(0) 06.12.2026
--
--
Building Permit
(30)
*
06.12.2026
--
--
Order Roof & Floor Trusses
(1) 06.12.2026
--
--
Order Windows & Doors
(0) 06.15.2026
--
--
Stake Out Home
(1) 06.12.2026
--
--
Excavate
(2) 06.12.2026
--
--
Inspection (Footers)
(1) 06.12.2026
--
--
Inspection (Concrete Wall)
(1) 06.12.2026
--
--
Pour Footers
(1)
*
06.12.2026
--
--
Set Forms
(2) 06.12.2026
--
--
Pour Foundation Walls
(1) 06.12.2026
--
--
Plumb Slab
(2) 06.12.2026
--
--
Inspection (Plumbing Under Slab)
(1) 06.12.2026
--
--
Inspection (Conduit Under Slab)
(1) 06.12.2026
--
--
Prepare Slab
(1) 06.12.2026
--
--
Inspection (Slab)
(1) 06.12.2026
--
--
Inspection (Drain Tile)
(0) 06.12.2026
--
--
Pour Slab
(1)
*
06.12.2026
--
--
Settlement Agent Confirmed
(0) 06.12.2026
--
--
Framing I
(9) 06.12.2026
--
--
Order Tubs / Showers
(0) 06.22.2026
--
--
Framing II
(8) 06.12.2026
--
--
Framing III
(8)
*
06.18.2026
--
--
Verify Window & Roof Structure
(0) 06.12.2026
--
--
Roofing
(0)
*
06.18.2026
--
--
Order Cabinets
(0) 06.12.2026
--
--
Order Appliances
(0) 06.12.2026
--
--
Deck
(0) 06.22.2026
--
--
Driveway
(0)
*
06.12.2026
--
--
Patio
(0) 06.12.2026
--
--
Privacy Divider / Fence
(0)
*
06.12.2026
--
--
HVAC Rough In
(4) 06.29.2026
--
--
Rough In Microwave Vent
(0) 06.12.2026
--
--
Inspection (Deck Piers)
(0) 06.12.2026
--
--
Exterior Vinyl
(0)
*
06.12.2026