VILLAS - 507-201  ::  507 Roman Way #201
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
Sat    May 16      Building Permit (30) *       
Fri    Jun 26      Order Roof & Floor Trusses (1)      
    Order Windows & Doors (0)      
Mon    Jun 29      Inspection (Concrete Wall) (1)      
Tue    Jun 30      Set Forms (2)      
Thu    Jul 2      Pour Foundation Walls (1)      
Fri    Jul 3      Plumb Slab (2)      
Tue    Jul 7      Inspection (Plumbing Under Slab) (1)      
Wed    Jul 8      Inspection (Conduit Under Slab) (1)      
Thu    Jul 9      Prepare Slab (1)      
Fri    Jul 10      Inspection (Slab) (1)      
    Inspection (Drain Tile) (0)      
Mon    Jul 13      Pour Slab (1) *       
Tue    Jul 14      Framing I (9)      
    Order Steps (0)      
    Order Tubs / Showers (0)      
Mon    Jul 27      Framing II (8)      
Thu    Aug 6      Framing III (8) *       
    Verify Window & Roof Structure (0)      
    Install Stairs (0) *       
    Windows & Doors (0) *       
    House Number and Status in Window (0)      
    Roofing (0) *       
    Order Cabinets (0)      
    Order Appliances (0)      
    Deck (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Sod / Seed / Landscaping (0)      
Tue    Aug 18      HVAC Rough In (4)      
    Rough In Microwave Vent (0)      
Mon    Aug 24      Plumbing Rough In (4)      
Fri    Aug 28      Electric Rough In (4)      
Thu    Sep 3      Inspection (Rough In HVAC) (1)      
Fri    Sep 4      Inspection (Rough In Plumbing) (1)      
Mon    Sep 7      Inspection (Rough In Electric) (1)      
Tue    Sep 8      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Vinyl (0) *       
    Exterior Stone (0)      
Wed    Sep 9      Insulation (2) *       
Fri    Sep 11      Inspection (Insulation) (1)      
    Inspection (Electric Service) (0)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Mon    Sep 14      Drywall (Hang) (4) *       
Fri    Sep 18      Drywall (Tape, Block, Skim, Sand) (6) *       
Mon    Sep 28      Paint 1 (1)      
    House Numbers (0)      
    Mailbox (0)      
Tue    Sep 29      Cabinet Installation (2) *       
Thu    Oct 1      Granite Installation (1) *       
Fri    Oct 2      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Wed    Oct 7      Interior Trim - Paint (1)      
Thu    Oct 8      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Tue    Oct 13      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Fri    Oct 16      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Mon    Oct 19      Set Water Meter (1) *       
Tue    Oct 20      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Fri    Oct 23      HVAC Trim Out (1) *       
Mon    Oct 26      Blower Door Test (1)      
Tue    Oct 27      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Thu    Oct 29      Paint 3 (2) *       
Mon    Nov 2      Carpet (2)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Wed    Nov 4      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Tue    Nov 10      Stain Hardwood Stairs (1) *       
Wed    Nov 11      Cleaning (1)      
Thu    Nov 12      Certificate of Occupancy (1) *       
    Keys to Settlement Agent (0)      
    Request Trash Tote From POA Manager (0)      
Fri    Nov 13      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  09.25.2025    
-- -- $2500 Deposit Received (0)  09.25.2025    
-- -- Association Packet Requested (0)  09.25.2025    
-- -- Association Packet Received (0)  09.25.2025    
-- -- Selections Meeting (0)  09.25.2025    
-- -- Selections Sheet Signed (0)  09.25.2025    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.25.2025    
-- -- Deposit For Upgrades Received (0)  09.25.2025    
-- -- Stake Out Home (1)  10.09.2025    
-- -- Excavate (2)  10.09.2025    
-- -- Inspection (Footers) (1)  10.09.2025    
-- -- Pour Footers (1) *   10.09.2025    
-- -- Settlement Agent Confirmed (0)  09.25.2025    
-- -- Privacy Divider / Fence (0) *   09.25.2025    
-- -- Loan Approval (0)  09.25.2025    
-- -- Deed Preparation (0)  09.25.2025    
-- -- Garage Door (0)  09.25.2025    
-- -- Appraiser Confirms Construction Completion (0)  09.25.2025    
-- -- C.O. to Lender (0)  09.25.2025    
-- -- Schedule Closing (0)  09.25.2025    
-- -- Buyer Walk Through (1) *   09.25.2025    
-- -- Payment for Upgrades (0)  09.25.2025    
-- -- Review Settlement Statement (0)  09.25.2025    
-- -- Jerry Signs Closing Documents (0)  09.25.2025