CONGERS-3
VILLAS
CONGERS-4
CONGERS-2
CONGERS
000
•
501
501-101
501-102
501-201
501-202
501-301
501-302
•
507-101
507-102
507-201
507-202
507-301
507-302
•
ADDR
VILLAS - 507-201 :: 507 Roman Way #201
CRITICAL PATH
|
INSPECTIONS
|
FLOOR PLANS
|
SELECTIONS
|
SPECS
|
CHANGES
|
NHS
view photo archive
TO DO
---
UPGRADES
---
CRITICAL PATH
Wed
Mar 25
Building Permit
(30)
*
Wed
May 6
Order Roof & Floor Trusses
(1)
Order Windows & Doors
(0)
Thu
May 7
Inspection (Concrete Wall)
(1)
Fri
May 8
Set Forms
(2)
Tue
May 12
Pour Foundation Walls
(1)
Wed
May 13
Plumb Slab
(2)
Fri
May 15
Inspection (Plumbing Under Slab)
(1)
Mon
May 18
Inspection (Conduit Under Slab)
(1)
Tue
May 19
Prepare Slab
(1)
Wed
May 20
Inspection (Slab)
(1)
Inspection (Drain Tile)
(0)
Thu
May 21
Pour Slab
(1)
*
Fri
May 22
Framing I
(9)
Order Steps
(0)
Order Tubs / Showers
(0)
Thu
Jun 4
Framing II
(8)
Tue
Jun 16
Framing III
(8)
*
Verify Window & Roof Structure
(0)
Install Stairs
(0)
*
Windows & Doors
(0)
*
House Number and Status in Window
(0)
Roofing
(0)
*
Order Cabinets
(0)
Order Appliances
(0)
Deck
(0)
Gutters
(0)
Driveway
(0)
*
Patio
(0)
Sod / Seed / Landscaping
(0)
Fri
Jun 26
HVAC Rough In
(4)
Rough In Microwave Vent
(0)
Thu
Jul 2
Plumbing Rough In
(4)
Wed
Jul 8
Electric Rough In
(4)
Tue
Jul 14
Inspection (Rough In HVAC)
(1)
Wed
Jul 15
Inspection (Rough In Plumbing)
(1)
Thu
Jul 16
Inspection (Rough In Electric)
(1)
Fri
Jul 17
Inspection (Framing)
(1)
*
Inspection (Deck Piers)
(0)
Exterior Vinyl
(0)
*
Exterior Stone
(0)
Mon
Jul 20
Insulation
(2)
*
Wed
Jul 22
Inspection (Insulation)
(1)
Inspection (Electric Service)
(0)
Set Electric Meter
(0)
*
Inspection (Main Sewer Line)
(0)
Inspection (Main Water Line)
(0)
Order Interior Doors & Trim
(0)
Thu
Jul 23
Drywall (Hang)
(4)
*
Wed
Jul 29
Drywall (Tape, Block, Skim, Sand)
(6)
*
Thu
Aug 6
Paint 1
(1)
House Numbers
(0)
Mailbox
(0)
Fri
Aug 7
Cabinet Installation
(2)
*
Tue
Aug 11
Granite Installation
(1)
*
Wed
Aug 12
Interior Trim - Install
(3)
*
Order Plumbing / Lighting Fixtures
(0)
Mon
Aug 17
Interior Trim - Paint
(1)
Tue
Aug 18
Luxury Vinyl Plank
(3)
*
Luxury Vinyl Tile
(0)
Fri
Aug 21
Paint 2
(3)
Cover Floors
(0)
Deliver Plumbing / Lighting Fixtures
(0)
Shoe Moulding
(0)
Wed
Aug 26
Shelving, Door Knobs, Fire Extinguisher
(1)
*
Install Coded Lockbox (add extra keys)
(0)
Pay Water / Sewer Taps
(0)
Thu
Aug 27
Set Water Meter
(1)
*
Fri
Aug 28
Electric Trim Out
(3)
*
Ceiling Fans
(0)
Wed
Sep 2
HVAC Trim Out
(1)
*
Thu
Sep 3
Blower Door Test
(1)
Fri
Sep 4
Plumbing Trim Out
(2)
*
Install Appliances
(0)
*
Tue
Sep 8
Paint 3
(2)
*
Thu
Sep 10
Carpet
(2)
Inspection (Final HVAC)
(0)
Inspection (Final Plumbing)
(0)
Inspection (Final Electric)
(0)
Mon
Sep 14
Inspection (Final Building)
(4)
*
Pre Walk Through
(0)
Fri
Sep 18
Stain Hardwood Stairs
(1)
*
Mon
Sep 21
Cleaning
(1)
Tue
Sep 22
Certificate of Occupancy
(1)
*
Keys to Settlement Agent
(0)
Request Trash Tote From POA Manager
(0)
Wed
Sep 23
Closing
(1)
Remove Coded Lockbox
(0)
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
--
--
Ratified Contract?
(0) 09.25.2025
--
--
$2500 Deposit Received
(0) 09.25.2025
--
--
Association Packet Requested
(0) 09.25.2025
--
--
Association Packet Received
(0) 09.25.2025
--
--
Selections Meeting
(0) 09.25.2025
--
--
Selections Sheet Signed
(0) 09.25.2025
--
--
Amendment for Upgrades (B,S,L,T,BCP)
(0) 09.25.2025
--
--
Deposit For Upgrades Received
(0) 09.25.2025
--
--
Stake Out Home
(1) 10.09.2025
--
--
Excavate
(2) 10.09.2025
--
--
Inspection (Footers)
(1) 10.09.2025
--
--
Pour Footers
(1)
*
10.09.2025
--
--
Settlement Agent Confirmed
(0) 09.25.2025
--
--
Privacy Divider / Fence
(0)
*
09.25.2025
--
--
Loan Approval
(0) 09.25.2025
--
--
Deed Preparation
(0) 09.25.2025
--
--
Garage Door
(0) 09.25.2025
--
--
Appraiser Confirms Construction Completion
(0) 09.25.2025
--
--
C.O. to Lender
(0) 09.25.2025
--
--
Schedule Closing
(0) 09.25.2025
--
--
Buyer Walk Through
(1)
*
09.25.2025
--
--
Payment for Upgrades
(0) 09.25.2025
--
--
Review Settlement Statement
(0) 09.25.2025
--
--
Jerry Signs Closing Documents
(0) 09.25.2025