CONGERS-3 - 38  ::  1627 Palomino Trail
[ BUILD: 20241831 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Put tub in bonus room
Don’t forget to put insulation in all bathtubs
Siding color at top peak of townhouse correct?
Back and side splashes of kitchen quartz are not correct
Garage needs trim
Are we OK with with the courts sides/be slightly different than previous townhouses in the kitchen? Quartz
Bottom faucet piece of hall bathroom needs installed tub overflow drain cover
Needs lots of lightbulbs Electrician
Sand8ng needed at drywall touchup in primary bathroom
Tell JoDee when to order final inspection by appraiser Johnny Hensley
Trim needed in front of all bathtubs Bonus bath and up hallway
All electrical covers needed after paint 3 Jesus
Hall light covers need installed In stairway
It appears painters started painting the back patio door? And then stopped? Painter
Garage door opener needed Davenport
What is the wire in the foyer inside the garage door? It looks like where the garage door opener is wired. Davenport
Powder bath light fixture needed electrician
Front door lock and hall bath mirror needed Hall mirror needed 3/22
Front electrical outlet needs complete completed
Lots of gravel in the back?
Install shower rod in primary bathroom Paul
CODED LOCKBOX 3838
Light fixture needed, in bonus bath Electrician
Thermostat needed
Trim above the garage needs to be nailed in in a few places Tom
Patch hole from where garage door opener wire was routed inside the house
Trim needed in bonus and hall bathroom 4/9
Install railings
Probably needs painter to wrap up and touch up before painting can begin In process 4/12
Bathtub trim needed in bonus bathroom 4/9
Gray outlet covers needed on kitchen island Electrician
Microwave vent does not function. It does appear that metal mesh on exterior is bent and that may be causing the issue. Tom
Attic cover needed after inspection
Send and repaint a few bumpy areas in the front foyer Ceiling in foyer
Lots of scratched up areas on the stair treads Jill, Jesus
Window screens needed Jill
Remove yellow covers from smoke detectors Jill
Cover needed for cables under stairs Tom
Clean home and garage Lynn. In process 4/16
Front door weatherstripping Jill
Hardwood steps need to be touched up Jill, Jesus
Caulk on trim in front of bathtubs Painter
Home inspection - Sat, Apr 19, 8am
Should we mop out the garage? Lots of glue and drywall
Touch up paint
Are we planning to cut down the tree on the back left-hand corner of their property line? It does not look in good shape and is definitely at risk of hitting the house.
Push the refrigerator back in place
Vent cover appears to be repaired, but microwave vent is still not functioning
Fix handle in smaller bedroom that has come apart
Repair the rear exterior deck door rubs at the frame when closed. Jeremiah
Need Gutter downspout extensions
damaged window sill Bonus Room Epoxy - Tom
Adjust door to deck- rubs when closed Jeremiah
Noted larger than average gaps at the outer rim joist and decking materials Tom
Noted improper slope at the rear left corner gutter; Greg
front bedroom door appears to be warped as it does not close as intended Jorge
loose trim at the corner of the kitchen island; recommend repair. Jorge
attic access panel is too small for the opening; recommend replacing the attic access panel to reduce the exchange of air with the attic. Tom
The water heater temperature seemed to be set too low at the time of inspection - just 106 degrees F. The range of 120-125 degrees F is the generally recommended temperature. This high tank temperature will reduce risks of Legionella developing in the tank. Tom or Jill
The refrigerator ice maker and water dispenser was not functional-the water source was not activated; recommend having water activated and the unit tested for proper operation Jill
Attic: Observed approximately 14 inches of insulation in the attic which is minimal for current standards; recommend installing additional insulation in the attic to conserve energy.
Clean behind fridge Jill
Cut down tree in back yard Buddy
clean dust from staircase lights
Remove dust from sconce lights Lynn
Broken closet door handle in Bedroom 2 Savannah
Is wire at liftmaster too long? Tom
Clean out garage Jill or Lynn
Paint touch up throughout Jesus
Splash blocks Courtney will ask Bub
Replace deck board that shrunk Tom
Install screens Jill
Folks are moving in4/26
Mail keys (x4)
Carlos Olaechea, 540-830-2508
UPGRADES - COMPLETED
    Finished bonus room  
    Finished bonus bath  
    Expanded 12 x 18 deck  
    Level 3 quartz  
    White/gray painted cabinetry in kitchen  
    Microwave vented to exterior  
    Expanded driveway  
    Oak steps to bedroom level  
    Luxury Vinyl Plank upstairs  
    Luxury vinyl plank, bonus room  
    Amendment to increase price by $30,530  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  10.04.2024    
-- -- $2500 Deposit Received (0)  10.09.2024    
-- -- Association Packet Requested (0)  10.04.2024    
-- -- Association Packet Received (0)  10.11.2024    
-- -- Selections Meeting (0)  10.15.2024     Requested for week of 10/14
-- -- Selections Sheet Signed (0)  10.24.2024     10/17: sent to Carlos
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.02.2024     11/2: sent to Jerry
-- -- Deposit For Upgrades Received (0)  11.02.2024    
-- -- Building Permit (30) *   10.07.2024    
-- -- Order Roof & Floor Trusses (1)  10.17.2024    
-- -- Order Windows & Doors (0)  12.02.2024    
-- -- Stake Out Home (1)  10.14.2024    
-- -- Excavate (2)  10.21.2024    
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Pour Footers (1) *   10.21.2024    
-- -- Set Forms (2)  11.13.2024    
-- -- Pour Foundation Walls (1)  11.13.2024    
-- -- Plumb Slab (2)  11.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.13.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.13.2024    
-- -- Prepare Slab (1)  11.13.2024    
-- -- Inspection (Slab) (1)  11.13.2024    
-- -- Inspection (Drain Tile) (0)  12.02.2024    
-- -- Pour Slab (1) *   11.13.2024    
-- -- Settlement Agent Confirmed (0)  11.08.2024    
-- -- Framing I (9)  11.24.2024    
-- -- Order Steps (0)  12.09.2024    
-- -- Order Tubs / Showers (0)  12.23.2024    
-- -- Framing II (8)  12.02.2024    
-- -- Framing III (8) *   12.19.2024    
-- -- Verify Window & Roof Structure (0)  12.19.2024    
-- -- Install Stairs (0) *   12.23.2024    
-- -- Windows & Doors (0) *   01.05.2025    
-- -- House Number and Status in Window (0)  01.16.2025    
-- -- Roofing (0) *   01.05.2025    
-- -- Order Cabinets (0)  12.31.2024    
-- -- Order Appliances (0)  02.20.2025     200509339240360269
-- -- Deck (0)  02.26.2025    
-- -- Gutters (0)  02.16.2025    
-- -- Driveway (0) *   03.26.2025     March 25
-- -- Patio (0)  03.15.2025     Framed 3/5
-- -- Privacy Divider / Fence (0) *   03.15.2025    
-- -- Sod / Seed / Landscaping (0)  04.23.2025     in process 4/19
-- -- HVAC Rough In (4)  01.18.2025     In Process 1/15
-- -- Rough In Microwave Vent (0)  01.05.2025    
-- -- Plumbing Rough In (4)  01.16.2025     almost completed 1/11
-- -- Electric Rough In (4)  01.23.2025     Started 1/18
-- -- Inspection (Rough In HVAC) (1)  01.23.2025    
-- -- Inspection (Rough In Plumbing) (1)  01.23.2025    
-- -- Inspection (Rough In Electric) (1)  01.23.2025    
-- -- Inspection (Framing) (1) *   01.23.2025    
-- -- Inspection (Deck Piers) (0)  01.23.2025    
-- -- Exterior Vinyl (0) *   02.16.2025    
-- -- Exterior Stone (0)  03.12.2025    
-- -- Insulation (2) *   01.25.2025    
-- -- Inspection (Insulation) (1)  01.27.2025    
-- -- Inspection (Electric Service) (0)  02.20.2025    
-- -- Set Electric Meter (0) *   04.09.2025    
-- -- Inspection (Main Sewer Line) (0)  02.20.2025    
-- -- Inspection (Main Water Line) (0)  02.20.2025    
-- -- Order Interior Doors & Trim (0)  01.27.2025    
-- -- Drywall (Hang) (4) *   02.01.2025    
-- -- Loan Approval (0)  03.24.2025     JoDee @ United Bank (80% LTV)
-- -- Deed Preparation (0)  03.06.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.08.2025     In process 2/5
-- -- Paint 1 (1)  02.08.2025    
-- -- Garage Door (0)  03.12.2025    
-- -- House Numbers (0)  03.22.2025    
-- -- Mailbox (0)  04.16.2025     end of this week 4/10 or 4/11
-- -- Cabinet Installation (2) *   02.10.2025     Fri, Feb 7
-- -- Granite Installation (1) *   02.20.2025     Monday 2/17
-- -- Interior Trim - Install (3) *   02.16.2025     In process 2/12
-- -- Order Plumbing / Lighting Fixtures (0)  02.17.2025    
-- -- Interior Trim - Paint (1)  02.16.2025    
-- -- Luxury Vinyl Plank (3) *   02.26.2025    
-- -- Luxury Vinyl Tile (0)  02.26.2025    
-- -- Paint 2 (3)  02.26.2025    
-- -- Cover Floors (0)  02.26.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.20.2025    
-- -- Shoe Moulding (0)  03.12.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   03.15.2025    
-- -- Install Coded Lockbox (add extra keys) (0)  03.26.2025    
-- -- Pay Water / Sewer Taps (0)  03.03.2025    
-- -- Set Water Meter (1) *   04.14.2025    
-- -- Electric Trim Out (3) *   03.12.2025     In process 3/5
-- -- Ceiling Fans (0)  03.05.2025    
-- -- HVAC Trim Out (1) *   03.26.2025     Needs thermostat
-- -- Blower Door Test (1)  04.16.2025    
-- -- Plumbing Trim Out (2) *   03.05.2025    
-- -- Install Appliances (0) *   04.16.2025     Dishwasher needs to be installed 4/6
-- -- Paint 3 (2) *   03.15.2025     In process 3/12
-- -- Carpet (2)  02.26.2025    
-- -- Appraiser Confirms Construction Completion (0)  04.22.2025     Mon, Apr 21
-- -- Inspection (Final HVAC) (0)  04.16.2025    
-- -- Inspection (Final Plumbing) (0)  04.16.2025    
-- -- Inspection (Final Electric) (0)  04.16.2025    
-- -- Inspection (Final Building) (4) *   04.16.2025     Wed, Apr 16
-- -- Pre Walk Through (0)  04.17.2025    
-- -- Stain Hardwood Stairs (1) *   04.06.2025     In process 3/22
-- -- Cleaning (1)  04.19.2025    
-- -- Certificate of Occupancy (1) *   04.22.2025    
-- -- C.O. to Lender (0)  04.22.2025    
-- -- Schedule Closing (0)  04.24.2025    
-- -- Buyer Walk Through (1) *   04.24.2025     was this completed? Blue tape on walls?
-- -- Payment for Upgrades (0)  04.17.2025    
-- -- Keys to Settlement Agent (0)  04.17.2025    
-- -- Review Settlement Statement (0)  04.22.2025    
-- -- Jerry Signs Closing Documents (0)  04.22.2025    
-- -- Request Trash Tote From POA Manager (0)  04.21.2025    
-- -- Closing (1)  04.24.2025     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  04.28.2025