Put tub in bonus room |
|
|
-- |
-- |
Don’t forget to put insulation in all bathtubs |
|
|
-- |
-- |
Siding color at top peak of townhouse correct? |
|
|
-- |
-- |
Back and side splashes of kitchen quartz are not correct |
|
|
-- |
-- |
Garage needs trim |
|
|
-- |
-- |
Are we OK with with the courts sides/be slightly different than previous townhouses in the kitchen? |
Quartz |
|
-- |
-- |
Bottom faucet piece of hall bathroom needs installed |
tub overflow drain cover |
|
-- |
-- |
Needs lots of lightbulbs |
Electrician |
|
-- |
-- |
Sand8ng needed at drywall touchup in primary bathroom |
|
|
-- |
-- |
Tell JoDee when to order final inspection by appraiser |
Johnny Hensley |
|
-- |
-- |
Trim needed in front of all bathtubs |
Bonus bath and up hallway |
|
-- |
-- |
All electrical covers needed after paint 3 |
Jesus |
|
-- |
-- |
Hall light covers need installed |
In stairway |
|
-- |
-- |
It appears painters started painting the back patio door? And then stopped? |
Painter |
|
-- |
-- |
Garage door opener needed |
Davenport |
|
-- |
-- |
What is the wire in the foyer inside the garage door? It looks like where the garage door opener is wired. |
Davenport |
|
-- |
-- |
Powder bath light fixture needed |
electrician |
|
-- |
-- |
Front door lock and hall bath mirror needed |
Hall mirror needed 3/22 |
|
-- |
-- |
Front electrical outlet needs complete completed |
|
|
-- |
-- |
Lots of gravel in the back? |
|
|
-- |
-- |
Install shower rod in primary bathroom |
Paul |
|
-- |
-- |
CODED LOCKBOX 3838 |
|
|
-- |
-- |
Light fixture needed, in bonus bath |
Electrician |
|
-- |
-- |
Thermostat needed |
|
|
-- |
-- |
Trim above the garage needs to be nailed in in a few places |
Tom |
|
-- |
-- |
Patch hole from where garage door opener wire was routed inside the house |
|
|
-- |
-- |
Trim needed in bonus and hall bathroom 4/9 |
|
|
-- |
-- |
Install railings |
|
|
-- |
-- |
Probably needs painter to wrap up and touch up before painting can begin |
In process 4/12 |
|
-- |
-- |
Bathtub trim needed in bonus bathroom 4/9 |
|
|
-- |
-- |
Gray outlet covers needed on kitchen island |
Electrician |
|
-- |
-- |
Microwave vent does not function. It does appear that metal mesh on exterior is bent and that may be causing the issue. |
Tom |
|
-- |
-- |
Attic cover needed |
after inspection |
|
-- |
-- |
Send and repaint a few bumpy areas in the front foyer |
Ceiling in foyer |
|
-- |
-- |
Lots of scratched up areas on the stair treads |
Jill, Jesus |
|
-- |
-- |
Window screens needed |
Jill |
|
-- |
-- |
Remove yellow covers from smoke detectors |
Jill |
|
-- |
-- |
Cover needed for cables under stairs |
Tom |
|
-- |
-- |
Clean home and garage |
Lynn. In process 4/16 |
|
-- |
-- |
Front door weatherstripping |
Jill |
|
-- |
-- |
Hardwood steps need to be touched up |
Jill, Jesus |
|
-- |
-- |
Caulk on trim in front of bathtubs |
Painter |
|
-- |
-- |
Home inspection - Sat, Apr 19, 8am |
|
|
-- |
-- |
Should we mop out the garage? Lots of glue and drywall |
|
|
-- |
-- |
Touch up paint |
|
|
-- |
-- |
Are we planning to cut down the tree on the back left-hand corner of their property line? It does not look in good shape and is definitely at risk of hitting the house. |
|
|
-- |
-- |
Push the refrigerator back in place |
|
|
-- |
-- |
Vent cover appears to be repaired, but microwave vent is still not functioning |
|
|
-- |
-- |
Fix handle in smaller bedroom that has come apart |
|
|
-- |
-- |
Repair the rear exterior deck door rubs at the frame when closed. |
Jeremiah |
|
-- |
-- |
Need Gutter downspout extensions |
|
|
-- |
-- |
damaged window sill Bonus Room |
Epoxy - Tom |
|
-- |
-- |
Adjust door to deck- rubs when closed |
Jeremiah |
|
-- |
-- |
Noted larger than average gaps at the outer rim joist and decking materials |
Tom |
|
-- |
-- |
Noted improper slope at the rear left corner gutter; |
Greg |
|
-- |
-- |
front bedroom door appears to be warped as it does not close as intended |
Jorge |
|
-- |
-- |
loose trim at the corner of the kitchen island; recommend repair. |
Jorge |
|
-- |
-- |
attic access panel is too small for the opening; recommend replacing the attic access panel to reduce the exchange of air with the attic. |
Tom |
|
-- |
-- |
The water heater temperature seemed to be set too low at the time of inspection - just 106 degrees F. The range of 120-125 degrees F is the generally recommended temperature. This high tank temperature will reduce risks of Legionella developing in the tank. |
Tom or Jill |
|
-- |
-- |
The refrigerator ice maker and water dispenser was not functional-the water source was not activated; recommend having water activated and the unit tested for proper operation |
Jill |
|
-- |
-- |
Attic: Observed approximately 14 inches of insulation in the attic which is minimal for current standards; recommend installing additional insulation in the attic to conserve energy. |
|
|
-- |
-- |
Clean behind fridge |
Jill |
|
-- |
-- |
Cut down tree in back yard |
Buddy |
|
-- |
-- |
clean dust from staircase lights |
|
|
-- |
-- |
Remove dust from sconce lights |
Lynn |
|
-- |
-- |
Broken closet door handle in Bedroom 2 |
Savannah |
|
-- |
-- |
Is wire at liftmaster too long? |
Tom |
|
-- |
-- |
Clean out garage |
Jill or Lynn |
|
-- |
-- |
Paint touch up throughout |
Jesus |
|
-- |
-- |
Splash blocks |
Courtney will ask Bub |
|
-- |
-- |
Replace deck board that shrunk |
Tom |
|
-- |
-- |
Install screens |
Jill |
|
-- |
-- |
Folks are moving in4/26 |
|
|
-- |
-- |
Mail keys (x4) |
|
|
-- |
-- |
Carlos Olaechea, 540-830-2508 |
|
|
-- |
-- |
Ratified Contract? (0) 10.04.2024 |
|
|
|
|
Finished bonus room
|
|
|
|
Finished bonus bath
|
|
|
|
Expanded 12 x 18 deck
|
|
|
|
Level 3 quartz
|
|
|
|
White/gray painted cabinetry in kitchen
|
|
|
|
Microwave vented to exterior
|
|
|
|
Expanded driveway
|
|
|
|
Oak steps to bedroom level
|
|
|
|
Luxury Vinyl Plank upstairs
|
|
|
|
Luxury vinyl plank, bonus room
|
|
|
|
Amendment to increase price by $30,530
|
|
-- |
-- |
$2500 Deposit Received (0) 10.09.2024 |
|
|
-- |
-- |
Association Packet Requested (0) 10.04.2024 |
|
|
-- |
-- |
Association Packet Received (0) 10.11.2024 |
|
|
-- |
-- |
Selections Meeting (0) 10.15.2024 |
Requested for week of 10/14 |
|
-- |
-- |
Selections Sheet Signed (0) 10.24.2024 |
10/17: sent to Carlos |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 11.02.2024 |
11/2: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 11.02.2024 |
|
|
-- |
-- |
Building Permit (30) 10.07.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 10.17.2024 |
|
|
-- |
-- |
Order Windows & Doors (0) 12.02.2024 |
|
|
-- |
-- |
Stake Out Home (1) 10.14.2024 |
|
|
-- |
-- |
Excavate (2) 10.21.2024 |
|
|
-- |
-- |
Inspection (Footers) (1) 10.21.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.21.2024 |
|
|
-- |
-- |
Pour Footers (1) * 10.21.2024 |
|
|
-- |
-- |
Set Forms (2) 11.13.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1) 11.13.2024 |
|
|
-- |
-- |
Plumb Slab (2) 11.13.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 11.13.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 11.13.2024 |
|
|
-- |
-- |
Prepare Slab (1) 11.13.2024 |
|
|
-- |
-- |
Inspection (Slab) (1) 11.13.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 12.02.2024 |
|
|
-- |
-- |
Pour Slab (1) * 11.13.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 11.08.2024 |
|
|
-- |
-- |
Framing I (9) 11.24.2024 |
|
|
-- |
-- |
Order Steps (0) 12.09.2024 |
|
|
-- |
-- |
Order Tubs / Showers (0) 12.23.2024 |
|
|
-- |
-- |
Framing II (8) 12.02.2024 |
|
|
-- |
-- |
Framing III (8) * 12.19.2024 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.19.2024 |
|
|
-- |
-- |
Install Stairs (0) 12.23.2024 |
|
|
-- |
-- |
Windows & Doors (0) * 01.05.2025 |
|
|
-- |
-- |
House Number and Status in Window (0) 01.16.2025 |
|
|
-- |
-- |
Roofing (0) * 01.05.2025 |
|
|
-- |
-- |
Order Cabinets (0) 12.31.2024 |
|
|
-- |
-- |
Order Appliances (0) 02.20.2025 |
200509339240360269 |
|
-- |
-- |
Deck (0) 02.26.2025 |
|
|
-- |
-- |
Gutters (0) 02.16.2025 |
|
|
-- |
-- |
Driveway (0) * 03.26.2025 |
March 25 |
|
-- |
-- |
Patio (0) 03.15.2025 |
Framed 3/5 |
|
-- |
-- |
Privacy Divider / Fence (0) 03.15.2025 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 04.23.2025 |
in process 4/19 |
|
-- |
-- |
HVAC Rough In (4) 01.18.2025 |
In Process 1/15 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 01.23.2025 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 01.05.2025 |
|
|
-- |
-- |
Plumbing Rough In (4) 01.16.2025 |
almost completed 1/11 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 01.23.2025 |
|
|
-- |
-- |
Electric Rough In (4) 01.23.2025 |
Started 1/18 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 01.23.2025 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 01.23.2025 |
|
|
-- |
-- |
Inspection (Framing) (1) * 01.23.2025 |
|
|
-- |
-- |
Exterior Vinyl (0) * 02.16.2025 |
|
|
-- |
-- |
Exterior Stone (0) 03.12.2025 |
|
|
-- |
-- |
Insulation (2) * 01.25.2025 |
|
|
-- |
-- |
Inspection (Insulation) (1) 01.27.2025 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 02.20.2025 |
|
|
-- |
-- |
Set Electric Meter (0) * 04.09.2025 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 02.20.2025 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 02.20.2025 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 01.27.2025 |
|
|
-- |
-- |
Drywall (Hang) (4) * 02.01.2025 |
|
|
-- |
-- |
Loan Approval (0) 03.24.2025 |
JoDee @ United Bank (80% LTV) |
|
-- |
-- |
Deed Preparation (0) 03.06.2025 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 02.08.2025 |
In process 2/5 |
|
-- |
-- |
Paint 1 (1) 02.08.2025 |
|
|
-- |
-- |
Garage Door (0) * 03.12.2025 |
|
|
-- |
-- |
House Numbers (0) 03.22.2025 |
|
|
-- |
-- |
Mailbox (0) 04.16.2025 |
end of this week 4/10 or 4/11 |
|
-- |
-- |
Cabinet Installation (2) * 02.10.2025 |
Fri, Feb 7 |
|
-- |
-- |
Granite Installation (1) * 02.20.2025 |
Monday 2/17 |
|
-- |
-- |
Interior Trim - Install (3) * 02.16.2025 |
In process 2/12 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 02.17.2025 |
|
|
-- |
-- |
Interior Trim - Paint (1) 02.16.2025 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 02.26.2025 |
|
|
-- |
-- |
Luxury Vinyl Tile (0) 02.26.2025 |
|
|
-- |
-- |
Paint 2 (3) 02.26.2025 |
|
|
-- |
-- |
Cover Floors (1) 02.26.2025 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 02.20.2025 |
|
|
-- |
-- |
Shoe Moulding (0) 03.12.2025 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) * 03.15.2025 |
|
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 03.26.2025 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 03.03.2025 |
|
|
-- |
-- |
Set Water Meter (0) * 04.14.2025 |
|
|
-- |
-- |
Electric Trim Out (3) 03.12.2025 |
In process 3/5 |
|
-- |
-- |
Ceiling Fans (0) 03.05.2025 |
|
|
-- |
-- |
HVAC Trim Out (1) 03.26.2025 |
Needs thermostat |
|
-- |
-- |
Blower Door Test (1) 04.16.2025 |
|
|
-- |
-- |
Plumbing Trim Out (2) 03.05.2025 |
|
|
-- |
-- |
Install Appliances (0) * 04.16.2025 |
Dishwasher needs to be installed 4/6 |
|
-- |
-- |
Paint 3 (2) * 03.15.2025 |
In process 3/12 |
|
-- |
-- |
Carpet (2) 02.26.2025 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 04.22.2025 |
Mon, Apr 21 |
|
-- |
-- |
Inspection (Final HVAC) (1) 04.16.2025 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 04.16.2025 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 04.16.2025 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 04.16.2025 |
Wed, Apr 16 |
|
-- |
-- |
Pre Walk Through (0) 04.17.2025 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 04.06.2025 |
In process 3/22 |
|
-- |
-- |
Cleaning (1) 04.19.2025 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 04.22.2025 |
|
|
-- |
-- |
C.O. to Lender (0) 04.22.2025 |
|
|
-- |
-- |
Schedule Closing (0) 04.24.2025 |
|
|
-- |
-- |
Buyer Walk Through (1) 04.24.2025 |
was this completed? Blue tape on walls? |
|
-- |
-- |
Payment for Upgrades (0) 04.17.2025 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 04.17.2025 |
|
|
-- |
-- |
Review Settlement Statement (0) 04.22.2025 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 04.22.2025 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 04.21.2025 |
|
|
-- |
-- |
Closing (1) 04.24.2025 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 04.28.2025 |
|
|