38 39 40 41 42 43 44 45 22 23 24 25 26 27 37 36 35 34 ADDR
CONGERS-3 - 38  ::  1627 Palomino Trail
[ BUILD: 20241831 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (Nov 13)    show all photos
    Finished bonus room  
    Finished bonus bath  
    Expanded 12 x 18 deck  
    Level 3 quartz  
    White/gray painted cabinetry in kitchen  
    Microwave vented to exterior  
    Expanded driveway  
    Oak steps to bedroom level  
    Luxury Vinyl Plank upstairs  
    Luxury vinyl plank, bonus room  
Thu    Nov 14      Order Windows & Doors (0)      
Thu    Nov 14      Inspection (Drain Tile) (0)      
Thu    Nov 14      Framing I (9)      
Wed    Nov 27      Order Steps (0)      
Wed    Nov 27      Order Tubs / Showers (0)      
Wed    Nov 27      Framing II (8)      
Mon    Dec 9      Framing III (8)      
Thu    Dec 19      Verify Window & Roof Structure (0)      
Thu    Dec 19      Install Stairs (0)      
Thu    Dec 19      Windows & Doors (0)      
Thu    Dec 19      House Number and Status in Window (0)      
Thu    Dec 19      Roofing (0)      
Thu    Dec 19      Order Cabinets (0)      
Thu    Dec 19      Order Appliances (0)      
Thu    Dec 19      Deck (0)      
Thu    Dec 19      Gutters (0)      
Thu    Dec 19      Driveway (0)      
Thu    Dec 19      Patio (0)      
Thu    Dec 19      Privacy Divider / Fence (0)      
Thu    Dec 19      Sod / Seed / Landscaping (0)      
Thu    Dec 19      HVAC Rough In (4)      
Wed    Dec 25      Inspection (Rough In HVAC) (1)      
Thu    Dec 26      Rough In Microwave Vent (0)      
Thu    Dec 26      Plumbing Rough In (4)      
Wed    Jan 1      Inspection (Rough In Plumbing) (1)      
Thu    Jan 2      Electric Rough In (4)      
Wed    Jan 8      Inspection (Rough In Electric) (1)      
Thu    Jan 9      Inspection (Deck Piers) (0)      
Thu    Jan 9      Inspection (Framing) (1)      
Fri    Jan 10      Exterior Vinyl (0)      
Fri    Jan 10      Exterior Stone (0)      
Fri    Jan 10      Insulation (2)      
Tue    Jan 14      Inspection (Insulation) (1)      
Wed    Jan 15      Inspection (Electric Service) (0)      
Wed    Jan 15      Set Electric Meter (0)      
Wed    Jan 15      Inspection (Main Sewer Line) (0)      
Wed    Jan 15      Inspection (Main Water Line) (0)      
Wed    Jan 15      Order Interior Doors & Trim (0)      
Wed    Jan 15      Drywall (Hang) (4)      
Tue    Jan 21      Loan Approval (0)      
Tue    Jan 21      Deed Preparation (0)      
Tue    Jan 21      Drywall (Tape, Block, Skim, Sand) (6)      
Wed    Jan 29      Paint 1 (1)      
Thu    Jan 30      Garage Door (0)      
Thu    Jan 30      House Numbers (0)      
Thu    Jan 30      Mailbox (0)      
Thu    Jan 30      Cabinet Installation (2)      
Mon    Feb 3      Granite Installation (1)      
Tue    Feb 4      Interior Trim - Install (3)      
Fri    Feb 7      Order Plumbing / Lighting Fixtures (0)      
Fri    Feb 7      Interior Trim - Paint (1)      
Mon    Feb 10      Luxury Vinyl Plank (3)      
Thu    Feb 13      Luxury Vinyl Tile (0)      
Thu    Feb 13      Paint 2 (3)      
Tue    Feb 18      Cover Floors (1)      
Wed    Feb 19      Deliver Plumbing / Lighting Fixtures (0)      
Wed    Feb 19      Shoe Moulding (0)      
Wed    Feb 19      Shelving, Door Knobs, Fire Extinguisher (0)      
Wed    Feb 19      Install Coded Lockbox (add extra keys) (0)      
Wed    Feb 19      Pay Water / Sewer Taps (0)      
Wed    Feb 19      Set Water Meter (0)      
Wed    Feb 19      Electric Trim Out (3)      
Mon    Feb 24      Ceiling Fans (0)      
Mon    Feb 24      HVAC Trim Out (1)      
Tue    Feb 25      Blower Door Test (1)      
Wed    Feb 26      Plumbing Trim Out (2)      
Fri    Feb 28      Install Appliances (0)      
Fri    Feb 28      Paint 3 (2)      
Tue    Mar 4      Carpet (2)      
Thu    Mar 6      Appraiser Confirms Construction Completion (0)      
Thu    Mar 6      Inspection (Final HVAC) (1)      
Fri    Mar 7      Inspection (Final Plumbing) (1)      
Mon    Mar 10      Inspection (Final Electric) (1)      
Tue    Mar 11      Inspection (Final Building) (2)      
Thu    Mar 13      Pre Walk Through (0)      
Thu    Mar 13      Stain Hardwood Stairs (1)      
Fri    Mar 14      Cleaning (1)      
Mon    Mar 17      Certificate of Occupancy (1)      
Tue    Mar 18      C.O. to Lender (0)      
Tue    Mar 18      Schedule Closing (0)      
Tue    Mar 18      Buyer Walk Through (1)      
Wed    Mar 19      Payment for Upgrades (0)      
Wed    Mar 19      Keys to Settlement Agent (0)      
Wed    Mar 19      Review Settlement Statement (0)      
Wed    Mar 19      Jerry Signs Closing Documents (0)      
Wed    Mar 19      Request Trash Tote From POA Manager (0)      
Wed    Mar 19      Closing (1)       Brittany @ West View Title
Thu    Mar 20      Remove Coded Lockbox (0)      
-- -- Ratified Contract? (0)  10.04.2024    
    Finished bonus room  
    Finished bonus bath  
    Expanded 12 x 18 deck  
    Level 3 quartz  
    White/gray painted cabinetry in kitchen  
    Microwave vented to exterior  
    Expanded driveway  
    Oak steps to bedroom level  
    Luxury Vinyl Plank upstairs  
    Luxury vinyl plank, bonus room  
-- -- $2500 Deposit Received (0)  10.09.2024    
-- -- Association Packet Requested (0)  10.04.2024    
-- -- Association Packet Received (0)  10.11.2024    
-- -- Selections Meeting (0)  10.15.2024     Requested for week of 10/14
-- -- Selections Sheet Signed (0)  10.24.2024     10/17: sent to Carlos
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.02.2024     11/2: sent to Jerry
-- -- Deposit For Upgrades Received (0)  11.02.2024    
-- -- Building Permit (30)  10.07.2024    
-- -- Order Roof & Floor Trusses (1)  10.17.2024    
-- -- Stake Out Home (1)  10.14.2024    
-- -- Excavate (2)  10.21.2024    
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Pour Footers (1)  10.21.2024    
-- -- Set Forms (2)  11.13.2024    
-- -- Pour Foundation Walls (1)  11.13.2024    
-- -- Plumb Slab (2)  11.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.13.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.13.2024    
-- -- Prepare Slab (1)  11.13.2024    
-- -- Inspection (Slab) (1)  11.13.2024    
-- -- Pour Slab (1)  11.13.2024    
-- -- Settlement Agent Confirmed (0)  11.08.2024