Thu |
Nov 14 |
Order Windows & Doors (0)
|
|
|
Thu |
Nov 14 |
Inspection (Drain Tile) (0)
|
|
|
Thu |
Nov 14 |
Framing I (9)
|
|
|
Wed |
Nov 27 |
Order Steps (0)
|
|
|
Wed |
Nov 27 |
Order Tubs / Showers (0)
|
|
|
Wed |
Nov 27 |
Framing II (8)
|
|
|
Mon |
Dec 9 |
Framing III (8)
|
|
|
Thu |
Dec 19 |
Verify Window & Roof Structure (0)
|
|
|
Thu |
Dec 19 |
Install Stairs (0)
|
|
|
Thu |
Dec 19 |
Windows & Doors (0)
|
|
|
Thu |
Dec 19 |
House Number and Status in Window (0)
|
|
|
Thu |
Dec 19 |
Roofing (0)
|
|
|
Thu |
Dec 19 |
Order Cabinets (0)
|
|
|
Thu |
Dec 19 |
Order Appliances (0)
|
|
|
Thu |
Dec 19 |
Deck (0)
|
|
|
Thu |
Dec 19 |
Gutters (0)
|
|
|
Thu |
Dec 19 |
Driveway (0)
|
|
|
Thu |
Dec 19 |
Patio (0)
|
|
|
Thu |
Dec 19 |
Privacy Divider / Fence (0)
|
|
|
Thu |
Dec 19 |
Sod / Seed / Landscaping (0)
|
|
|
Thu |
Dec 19 |
HVAC Rough In (4)
|
|
|
Wed |
Dec 25 |
Inspection (Rough In HVAC) (1)
|
|
|
Thu |
Dec 26 |
Rough In Microwave Vent (0)
|
|
|
Thu |
Dec 26 |
Plumbing Rough In (4)
|
|
|
Wed |
Jan 1 |
Inspection (Rough In Plumbing) (1)
|
|
|
Thu |
Jan 2 |
Electric Rough In (4)
|
|
|
Wed |
Jan 8 |
Inspection (Rough In Electric) (1)
|
|
|
Thu |
Jan 9 |
Inspection (Deck Piers) (0)
|
|
|
Thu |
Jan 9 |
Inspection (Framing) (1)
|
|
|
Fri |
Jan 10 |
Exterior Vinyl (0)
|
|
|
Fri |
Jan 10 |
Exterior Stone (0)
|
|
|
Fri |
Jan 10 |
Insulation (2)
|
|
|
Tue |
Jan 14 |
Inspection (Insulation) (1)
|
|
|
Wed |
Jan 15 |
Inspection (Electric Service) (0)
|
|
|
Wed |
Jan 15 |
Set Electric Meter (0)
|
|
|
Wed |
Jan 15 |
Inspection (Main Sewer Line) (0)
|
|
|
Wed |
Jan 15 |
Inspection (Main Water Line) (0)
|
|
|
Wed |
Jan 15 |
Order Interior Doors & Trim (0)
|
|
|
Wed |
Jan 15 |
Drywall (Hang) (4)
|
|
|
Tue |
Jan 21 |
Loan Approval (0)
|
|
|
Tue |
Jan 21 |
Deed Preparation (0)
|
|
|
Tue |
Jan 21 |
Drywall (Tape, Block, Skim, Sand) (6)
|
|
|
Wed |
Jan 29 |
Paint 1 (1)
|
|
|
Thu |
Jan 30 |
Garage Door (0)
|
|
|
Thu |
Jan 30 |
House Numbers (0)
|
|
|
Thu |
Jan 30 |
Mailbox (0)
|
|
|
Thu |
Jan 30 |
Cabinet Installation (2)
|
|
|
Mon |
Feb 3 |
Granite Installation (1)
|
|
|
Tue |
Feb 4 |
Interior Trim - Install (3)
|
|
|
Fri |
Feb 7 |
Order Plumbing / Lighting Fixtures (0)
|
|
|
Fri |
Feb 7 |
Interior Trim - Paint (1)
|
|
|
Mon |
Feb 10 |
Luxury Vinyl Plank (3)
|
|
|
Thu |
Feb 13 |
Luxury Vinyl Tile (0)
|
|
|
Thu |
Feb 13 |
Paint 2 (3)
|
|
|
Tue |
Feb 18 |
Cover Floors (1)
|
|
|
Wed |
Feb 19 |
Deliver Plumbing / Lighting Fixtures (0)
|
|
|
Wed |
Feb 19 |
Shoe Moulding (0)
|
|
|
Wed |
Feb 19 |
Shelving, Door Knobs, Fire Extinguisher (0)
|
|
|
Wed |
Feb 19 |
Install Coded Lockbox (add extra keys) (0)
|
|
|
Wed |
Feb 19 |
Pay Water / Sewer Taps (0)
|
|
|
Wed |
Feb 19 |
Set Water Meter (0)
|
|
|
Wed |
Feb 19 |
Electric Trim Out (3)
|
|
|
Mon |
Feb 24 |
Ceiling Fans (0)
|
|
|
Mon |
Feb 24 |
HVAC Trim Out (1)
|
|
|
Tue |
Feb 25 |
Blower Door Test (1)
|
|
|
Wed |
Feb 26 |
Plumbing Trim Out (2)
|
|
|
Fri |
Feb 28 |
Install Appliances (0)
|
|
|
Fri |
Feb 28 |
Paint 3 (2)
|
|
|
Tue |
Mar 4 |
Carpet (2)
|
|
|
Thu |
Mar 6 |
Appraiser Confirms Construction Completion (0)
|
|
|
Thu |
Mar 6 |
Inspection (Final HVAC) (1)
|
|
|
Fri |
Mar 7 |
Inspection (Final Plumbing) (1)
|
|
|
Mon |
Mar 10 |
Inspection (Final Electric) (1)
|
|
|
Tue |
Mar 11 |
Inspection (Final Building) (2)
|
|
|
Thu |
Mar 13 |
Pre Walk Through (0)
|
|
|
Thu |
Mar 13 |
Stain Hardwood Stairs (1)
|
|
|
Fri |
Mar 14 |
Cleaning (1)
|
|
|
Mon |
Mar 17 |
Certificate of Occupancy (1)
|
|
|
Tue |
Mar 18 |
C.O. to Lender (0)
|
|
|
Tue |
Mar 18 |
Schedule Closing (0)
|
|
|
Tue |
Mar 18 |
Buyer Walk Through (1)
|
|
|
Wed |
Mar 19 |
Payment for Upgrades (0)
|
|
|
Wed |
Mar 19 |
Keys to Settlement Agent (0)
|
|
|
Wed |
Mar 19 |
Review Settlement Statement (0)
|
|
|
Wed |
Mar 19 |
Jerry Signs Closing Documents (0)
|
|
|
Wed |
Mar 19 |
Request Trash Tote From POA Manager (0)
|
|
|
Wed |
Mar 19 |
Closing (1)
|
Brittany @ West View Title |
|
Thu |
Mar 20 |
Remove Coded Lockbox (0)
|
|
|
|
-- |
-- |
Ratified Contract? (0)
10.04.2024 |
|
|
|
|
Finished bonus room
|
|
|
|
Finished bonus bath
|
|
|
|
Expanded 12 x 18 deck
|
|
|
|
Level 3 quartz
|
|
|
|
White/gray painted cabinetry in kitchen
|
|
|
|
Microwave vented to exterior
|
|
|
|
Expanded driveway
|
|
|
|
Oak steps to bedroom level
|
|
|
|
Luxury Vinyl Plank upstairs
|
|
|
|
Luxury vinyl plank, bonus room
|
|
-- |
-- |
$2500 Deposit Received (0)
10.09.2024 |
|
|
-- |
-- |
Association Packet Requested (0)
10.04.2024 |
|
|
-- |
-- |
Association Packet Received (0)
10.11.2024 |
|
|
-- |
-- |
Selections Meeting (0)
10.15.2024 |
Requested for week of 10/14 |
|
-- |
-- |
Selections Sheet Signed (0)
10.24.2024 |
10/17: sent to Carlos |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
11.02.2024 |
11/2: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0)
11.02.2024 |
|
|
-- |
-- |
Building Permit (30)
10.07.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
10.17.2024 |
|
|
-- |
-- |
Stake Out Home (1)
10.14.2024 |
|
|
-- |
-- |
Excavate (2)
10.21.2024 |
|
|
-- |
-- |
Inspection (Footers) (1)
10.21.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
10.21.2024 |
|
|
-- |
-- |
Pour Footers (1)
10.21.2024 |
|
|
-- |
-- |
Set Forms (2)
11.13.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1)
11.13.2024 |
|
|
-- |
-- |
Plumb Slab (2)
11.13.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
11.13.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
11.13.2024 |
|
|
-- |
-- |
Prepare Slab (1)
11.13.2024 |
|
|
-- |
-- |
Inspection (Slab) (1)
11.13.2024 |
|
|
-- |
-- |
Pour Slab (1)
11.13.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
11.08.2024 |
|
|