CONGERS-3 - 43  ::  1601 Palomino Trail
[ BUILD: 20241826 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Jul 1      Sod / Seed / Landscaping (0)      
--   --   Kate - does the upgrade pricing need to be adjusted?
--   --   Framing adjustment per owner request completed per Jill 2/12
--   --   Some type of mesh is flaking off the bottom of the granite kitchen island countertop Jill checking it out
--   --   Patch drywall on side of master bedroom door, framing Jesus
--   --   Patch drywall framing around storage closet on main level as well Jesus
--   --   Trim needed in garage Jorge
--   --   Jim around garage is quite gapped Trim - nail it in - Buddy
--   --   Upgraded fridge? Move to 45
--   --   Brown receptacle covers needed Jill
--   --   CODED LOCKBOX 4343
--   --   Few electrical items in process 4/23 Finish foyer lights
--   --   Master bathroom fan has not been put together for multiple days, is something wrong? Benefield - ceiling fan
--   --   Need attic acces cover Jorge
--   --   Ceiling Fan in Master Bedroom needs to be completed Electrician
--   --   Starp wire in island Electrician
--   --   need blower doorntest
--   --   Closing May 23
--   --   Various places need to be sanded and painted Jesus. In process 5/7. One small space near the snap light above the refrigerator.
--   --   Cabin and trim at stairs leading up to main level Gap
--   --   Cable box cover needed Jill
--   --   Final set of stain needed on steps leading to the bedroom level of the home Jesus
--   --   Piece of shoe mold needs nailed at top level of staircase Jorge
--   --   Gap in trim at stairs leading up to main level Caulk - Jesus
--   --   CLOSING - MAY 22 (out of town)
--   --   BUYER WALK THROUGH - MAY 22 (morning) Thursday AM
--   --   Repaint wall from shenanigans Jesus
--   --   Install deck screen Tom
--   --   Remove broken fan from master bedroom Jill
--   --   Closet under first set of steps, LVP does not go under shoe mold in the corner Denny
--   --   Install window screens Jill
--   --   Clean out bonus room Jill
--   --   Sweep off patio Jill
--   --   Clean out garage Jill
--   --   Stain on stairs a shade too dark (for future reference)
--   --   Dark Mark on island next to receptacle Jill
--   --   Remove yellow covers from smoke detector Jill
--   --   Adjust upstairs bedroom closet doors Jill
--   --   Remove the needed fan remote from wall- patch and paint Jesus
--   --   A few more obvious gaps in deck boards Tom
--   --   Exterior microwave vent cover a little wonky Tom
--   --   Trim under master bump out window looks a little rough Exterior trim - Davenport
--   --   Clean off deck Jill
--   --   Kate to go back with blue tape once home is cleaned Kate
--   --   Red staining on garage floor Jill
--   --   Painter needs to clean up paint on the luxury vinyl plank Jesus
--   --   Pressure wash front of house Jill
--   --   BUYER WALK THROUGH - MAY 22 (11AM)
--   --   Repaint front door
--   --   Pressure wash front
--   --   Repaint front door
--   --   Owner stuff is in the garage
-- -- Ratified Contract? (0)  11.19.2024    
    Level II Granite- Fantasy Brown  
    3 drawer stack in place of B36"- kitchen  
    LVP Up Hallway, Bedrooms,closets  
    Oak Stairs to Bedroom Level  
    Expanded 12 x 18 Deck  
    Expanded 10x10 Patio under deck  
    Expanded Driveway  
    Amendment to increase price by $11,320  
-- -- $2500 Deposit Received (0)  12.05.2024    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  11.23.2024    
-- -- Selections Meeting (0)  12.05.2024     12/4: sent to Cindy
-- -- Selections Sheet Signed (0)  01.23.2025     12/4: sent to Cindy
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  01.24.2025     1/23: sent to Jerry
-- -- Deposit For Upgrades Received (0)  01.23.2025    
-- -- Building Permit (30)  10.07.2024    
-- -- Order Roof & Floor Trusses (1)  10.17.2024    
-- -- Order Windows & Doors (0)  12.02.2024    
-- -- Stake Out Home (1)  10.14.2024    
-- -- Excavate (2)  10.21.2024    
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Pour Footers (1) *   10.21.2024    
-- -- Set Forms (2)  11.13.2024    
-- -- Pour Foundation Walls (1)  11.13.2024    
-- -- Plumb Slab (2)  11.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.24.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.24.2024    
-- -- Prepare Slab (1)  11.24.2024    
-- -- Inspection (Slab) (1)  12.02.2024    
-- -- Inspection (Drain Tile) (0)  12.02.2024    
-- -- Pour Slab (1) *   12.02.2024    
-- -- Settlement Agent Confirmed (0)  01.25.2025     Tomahawk Title
-- -- Framing I (9)  12.19.2024    
-- -- Order Steps (0)  01.16.2025    
-- -- Order Tubs / Showers (0)  01.23.2025    
-- -- Framing II (8)  12.28.2024    
-- -- Framing III (8) *   01.13.2025    
-- -- Verify Window & Roof Structure (0)  01.16.2025    
-- -- Install Stairs (0)  01.16.2025    
-- -- Windows & Doors (0) *   01.23.2025    
-- -- House Number and Status in Window (0)  01.29.2025    
-- -- Roofing (0) *   02.02.2025    
-- -- Order Cabinets (0)  01.28.2025    
-- -- Order Appliances (0)  02.20.2025     Order # 200509355240380212
-- -- Deck (0)  03.21.2025     In process 3/19
-- -- Gutters (0)  03.19.2025    
-- -- Driveway (0) *   04.06.2025    
-- -- Patio (0)  03.15.2025    
-- -- Privacy Divider / Fence (0)  04.06.2025    
-- -- HVAC Rough In (4)  01.25.2025     in process 1/25
-- -- Inspection (Rough In HVAC) (1)  02.08.2025    
-- -- Rough In Microwave Vent (0)  01.25.2025    
-- -- Plumbing Rough In (4)  01.29.2025    
-- -- Inspection (Rough In Plumbing) (1)  02.08.2025    
-- -- Electric Rough In (4)  02.05.2025     In process 2/1
-- -- Inspection (Rough In Electric) (1)  02.08.2025    
-- -- Inspection (Deck Piers) (0)  02.20.2025    
-- -- Inspection (Framing) (1) *   02.08.2025    
-- -- Exterior Vinyl (0) *   03.15.2025    
-- -- Exterior Stone (0)  04.12.2025    
-- -- Insulation (2) *   02.08.2025    
-- -- Inspection (Insulation) (1)  02.12.2025    
-- -- Inspection (Electric Service) (0)  02.20.2025    
-- -- Set Electric Meter (0) *   04.09.2025    
-- -- Inspection (Main Sewer Line) (0)  02.20.2025    
-- -- Inspection (Main Water Line) (0)  02.20.2025    
-- -- Order Interior Doors & Trim (0)  02.20.2025    
-- -- Drywall (Hang) (4) *   02.16.2025     In process 2/12
-- -- Loan Approval (0)  04.28.2025     Cash
-- -- Deed Preparation (0)  04.14.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.26.2025    
-- -- Paint 1 (1)  03.01.2025    
-- -- Garage Door (0) *   03.19.2025    
-- -- House Numbers (0)  04.28.2025    
-- -- Mailbox (0)  04.16.2025    
-- -- Cabinet Installation (2) *   03.05.2025     Install Tuesday, March 4
-- -- Granite Installation (1) *   03.08.2025    
-- -- Interior Trim - Install (3) *   03.15.2025    
-- -- Order Plumbing / Lighting Fixtures (0)  03.24.2025    
-- -- Interior Trim - Paint (1)  03.21.2025     In process 3/19
-- -- Luxury Vinyl Plank (3) *   04.06.2025     In process 3/28. Almost completed.
-- -- Luxury Vinyl Tile (0)  03.28.2025     In process 3/26
-- -- Paint 2 (3)  03.08.2025    
-- -- Cover Floors (1)  04.12.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.24.2025    
-- -- Shoe Moulding (0)  04.06.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   04.19.2025     In process 4/16. Shelving and mirrors need finishing.
-- -- Install Coded Lockbox (add extra keys) (0)  04.21.2025    
-- -- Pay Water / Sewer Taps (0)  03.27.2025    
-- -- Set Water Meter (0) *   04.14.2025    
-- -- Electric Trim Out (3)  04.16.2025     In process 4/12
-- -- Ceiling Fans (0)  04.12.2025    
-- -- HVAC Trim Out (1)  04.12.2025    
-- -- Blower Door Test (1)  05.06.2025     Monday, May 5th at 4pm
-- -- Plumbing Trim Out (2)  04.06.2025    
-- -- Install Appliances (0) *   04.27.2025     Microwave and refrigerator need installed
-- -- Paint 3 (2) *   04.06.2025    
-- -- Carpet (2)  04.06.2025    
-- -- Appraiser Confirms Construction Completion (0)  05.23.2025    
-- -- Inspection (Final HVAC) (1)  05.08.2025     Tuesday, May 6
-- -- Inspection (Final Plumbing) (1)  05.08.2025    
-- -- Inspection (Final Electric) (1)  05.08.2025    
-- -- Inspection (Final Building) (2) *   05.08.2025    
-- -- Pre Walk Through (0)  05.17.2025    
-- -- Stain Hardwood Stairs (1)  05.07.2025     Started 4/27
-- -- Cleaning (1)  05.17.2025    
-- -- Certificate of Occupancy (1) *   05.09.2025    
-- -- C.O. to Lender (0)  05.09.2025    
-- -- Schedule Closing (0)  05.23.2025    
-- -- Buyer Walk Through (1)  05.23.2025    
-- -- Payment for Upgrades (0)  05.05.2025    
-- -- Keys to Settlement Agent (0)  05.22.2025    
-- -- Review Settlement Statement (0)  05.22.2025    
-- -- Jerry Signs Closing Documents (0)  05.23.2025    
-- -- Request Trash Tote From POA Manager (0)  05.08.2025    
-- -- Closing (1)  05.23.2025     Tomahawk Title, Ashley, ashley@jwlpc.com, 757-340-8822
-- -- Remove Coded Lockbox (0)  05.31.2025