000 40 37 20 13 32 31 30 29 28 12 11 10 9 5 6 7 8 1 2 3 4 ADDR
CONGERS-3 - 43  ::  1601 Palomino Trail
[ BUILD: 20241826 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Kate - does the upgrade pricing need to be adjusted?
Framing adjustment per owner request completed per Jill 2/12
Some type of mesh is flaking off the bottom of the granite kitchen island countertop Jill checking it out
Patch drywall on side of master bedroom door, framing Jesus
Patch drywall framing around storage closet on main level as well Jesus
Trim needed in garage Jorge
Jim around garage is quite gapped Trim - nail it in - Buddy
Upgraded fridge? Move to 45
Brown receptacle covers needed Jill
CODED LOCKBOX 4343
Few electrical items in process 4/23 Finish foyer lights
Master bathroom fan has not been put together for multiple days, is something wrong? Benefield - ceiling fan
Need attic acces cover Jorge
Ceiling Fan in Master Bedroom needs to be completed Electrician
Starp wire in island Electrician
need blower doorntest
Closing May 23
Various places need to be sanded and painted Jesus. In process 5/7. One small space near the snap light above the refrigerator.
Cabin and trim at stairs leading up to main level Gap
Cable box cover needed Jill
Final set of stain needed on steps leading to the bedroom level of the home Jesus
Piece of shoe mold needs nailed at top level of staircase Jorge
Gap in trim at stairs leading up to main level Caulk - Jesus
CLOSING - MAY 22 (out of town)
BUYER WALK THROUGH - MAY 22 (morning) Thursday AM
Repaint wall from shenanigans Jesus
Install deck screen Tom
Remove broken fan from master bedroom Jill
Closet under first set of steps, LVP does not go under shoe mold in the corner Denny
Install window screens Jill
Clean out bonus room Jill
Sweep off patio Jill
Clean out garage Jill
Stain on stairs a shade too dark (for future reference)
Dark Mark on island next to receptacle Jill
Remove yellow covers from smoke detector Jill
Adjust upstairs bedroom closet doors Jill
Remove the needed fan remote from wall- patch and paint Jesus
A few more obvious gaps in deck boards Tom
Exterior microwave vent cover a little wonky Tom
Trim under master bump out window looks a little rough Exterior trim - Davenport
Clean off deck Jill
Kate to go back with blue tape once home is cleaned Kate
Red staining on garage floor Jill
Painter needs to clean up paint on the luxury vinyl plank Jesus
Pressure wash front of house Jill
BUYER WALK THROUGH - MAY 22 (11AM)
Repaint front door
Pressure wash front
Repaint front door
Owner stuff is in the garage
Mailbox key
String in conduit for Comcast
UPGRADES - COMPLETED
    Level II Granite- Fantasy Brown  
    3 drawer stack in place of B36"- kitchen  
    LVP Up Hallway, Bedrooms,closets  
    Oak Stairs to Bedroom Level  
    Expanded 12 x 18 Deck  
    Expanded 10x10 Patio under deck  
    Expanded Driveway  
    Amendment to increase price by $11,320  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  11.19.2024    
-- -- $2500 Deposit Received (0)  12.05.2024    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  11.23.2024    
-- -- Selections Meeting (0)  12.05.2024     12/4: sent to Cindy
-- -- Selections Sheet Signed (0)  01.23.2025     12/4: sent to Cindy
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  01.24.2025     1/23: sent to Jerry
-- -- Deposit For Upgrades Received (0)  01.23.2025    
-- -- Building Permit (30) *   10.07.2024    
-- -- Order Roof & Floor Trusses (1)  10.17.2024    
-- -- Order Windows & Doors (0)  12.02.2024    
-- -- Stake Out Home (1)  10.14.2024    
-- -- Excavate (2)  10.21.2024    
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Pour Footers (1) *   10.21.2024    
-- -- Set Forms (2)  11.13.2024    
-- -- Pour Foundation Walls (1)  11.13.2024    
-- -- Plumb Slab (2)  11.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.24.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.24.2024    
-- -- Prepare Slab (1)  11.24.2024    
-- -- Inspection (Slab) (1)  12.02.2024    
-- -- Inspection (Drain Tile) (0)  12.02.2024    
-- -- Pour Slab (1) *   12.02.2024    
-- -- Settlement Agent Confirmed (0)  01.25.2025     Tomahawk Title
-- -- Framing I (9)  12.19.2024    
-- -- Order Steps (0)  01.16.2025    
-- -- Order Tubs / Showers (0)  01.23.2025    
-- -- Framing II (8)  12.28.2024    
-- -- Framing III (8) *   01.13.2025    
-- -- Verify Window & Roof Structure (0)  01.16.2025    
-- -- Install Stairs (0) *   01.16.2025    
-- -- Windows & Doors (0) *   01.23.2025    
-- -- House Number and Status in Window (0)  01.29.2025    
-- -- Roofing (0) *   02.02.2025    
-- -- Order Cabinets (0)  01.28.2025    
-- -- Order Appliances (0)  02.20.2025     Order # 200509355240380212
-- -- Deck (0)  03.21.2025     In process 3/19
-- -- Gutters (0)  03.19.2025    
-- -- Driveway (0) *   04.06.2025    
-- -- Patio (0)  03.15.2025    
-- -- Privacy Divider / Fence (0) *   04.06.2025    
-- -- Sod / Seed / Landscaping (0)  08.07.2025    
-- -- HVAC Rough In (4)  01.25.2025     in process 1/25
-- -- Rough In Microwave Vent (0)  01.25.2025    
-- -- Plumbing Rough In (4)  01.29.2025    
-- -- Electric Rough In (4)  02.05.2025     In process 2/1
-- -- Inspection (Rough In HVAC) (1)  02.08.2025    
-- -- Inspection (Rough In Plumbing) (1)  02.08.2025    
-- -- Inspection (Rough In Electric) (1)  02.08.2025    
-- -- Inspection (Framing) (1) *   02.08.2025    
-- -- Inspection (Deck Piers) (0)  02.20.2025    
-- -- Exterior Vinyl (0) *   03.15.2025    
-- -- Exterior Stone (0)  04.12.2025    
-- -- Insulation (2) *   02.08.2025    
-- -- Inspection (Insulation) (1)  02.12.2025    
-- -- Inspection (Electric Service) (0)  02.20.2025    
-- -- Set Electric Meter (0) *   04.09.2025    
-- -- Inspection (Main Sewer Line) (0)  02.20.2025    
-- -- Inspection (Main Water Line) (0)  02.20.2025    
-- -- Order Interior Doors & Trim (0)  02.20.2025    
-- -- Drywall (Hang) (4) *   02.16.2025     In process 2/12
-- -- Loan Approval (0)  04.28.2025     Cash
-- -- Deed Preparation (0)  04.14.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.26.2025    
-- -- Paint 1 (1)  03.01.2025    
-- -- Garage Door (0)  03.19.2025    
-- -- House Numbers (0)  04.28.2025    
-- -- Mailbox (0)  04.16.2025    
-- -- Cabinet Installation (2) *   03.05.2025     Install Tuesday, March 4
-- -- Granite Installation (1) *   03.08.2025    
-- -- Interior Trim - Install (3) *   03.15.2025    
-- -- Order Plumbing / Lighting Fixtures (0)  03.24.2025    
-- -- Interior Trim - Paint (1)  03.21.2025     In process 3/19
-- -- Luxury Vinyl Plank (3) *   04.06.2025     In process 3/28. Almost completed.
-- -- Luxury Vinyl Tile (0)  03.28.2025     In process 3/26
-- -- Paint 2 (3)  03.08.2025    
-- -- Cover Floors (0)  04.12.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.24.2025    
-- -- Shoe Moulding (0)  04.06.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   04.19.2025     In process 4/16. Shelving and mirrors need finishing.
-- -- Install Coded Lockbox (add extra keys) (0)  04.21.2025    
-- -- Pay Water / Sewer Taps (0)  03.27.2025    
-- -- Set Water Meter (1) *   04.14.2025    
-- -- Electric Trim Out (3) *   04.16.2025     In process 4/12
-- -- Ceiling Fans (0)  04.12.2025    
-- -- HVAC Trim Out (1) *   04.12.2025    
-- -- Blower Door Test (1)  05.06.2025     Monday, May 5th at 4pm
-- -- Plumbing Trim Out (2) *   04.06.2025    
-- -- Install Appliances (0) *   04.27.2025     Microwave and refrigerator need installed
-- -- Paint 3 (2) *   04.06.2025    
-- -- Carpet (2)  04.06.2025    
-- -- Appraiser Confirms Construction Completion (0)  05.23.2025    
-- -- Inspection (Final HVAC) (0)  05.08.2025     Tuesday, May 6
-- -- Inspection (Final Plumbing) (0)  05.08.2025    
-- -- Inspection (Final Electric) (0)  05.08.2025    
-- -- Inspection (Final Building) (4) *   05.08.2025    
-- -- Pre Walk Through (0)  05.17.2025    
-- -- Stain Hardwood Stairs (1) *   05.07.2025     Started 4/27
-- -- Cleaning (1)  05.17.2025    
-- -- Certificate of Occupancy (1) *   05.09.2025    
-- -- C.O. to Lender (0)  05.09.2025    
-- -- Schedule Closing (0)  05.23.2025    
-- -- Buyer Walk Through (1) *   05.23.2025    
-- -- Payment for Upgrades (0)  05.05.2025    
-- -- Keys to Settlement Agent (0)  05.22.2025    
-- -- Review Settlement Statement (0)  05.22.2025    
-- -- Jerry Signs Closing Documents (0)  05.23.2025    
-- -- Request Trash Tote From POA Manager (0)  05.08.2025    
-- -- Closing (1)  05.23.2025     Tomahawk Title, Ashley, ashley@jwlpc.com, 757-340-8822
-- -- Remove Coded Lockbox (0)  05.31.2025