000 40 37 20 13 32 31 30 29 28 12 11 10 9 5 6 7 8 1 2 3 4 ADDR
CONGERS-3 - 43  ::  1601 Palomino Trail
[ BUILD: 20241826 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Level II Granite- Fantasy Brown  
    3 drawer stack in place of B36"- kitchen  
    LVP Up Hallway, Bedrooms,closets  
    Oak Stairs to Bedroom Level  
    Expanded 12 x 18 Deck  
    Expanded 10x10 Patio under deck  
    Expanded Driveway  
    Amendment to increase price by $11,320  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024    
-- -- Inspection (Plumbing Under Slab) (1)  11.24.2024    
-- -- Inspection (Conduit Under Slab) (1)  11.24.2024    
-- -- Inspection (Slab) (1)  12.02.2024    
-- -- Inspection (Drain Tile) (0)  12.02.2024    
-- -- Inspection (Rough In HVAC) (1)  02.08.2025    
-- -- Inspection (Rough In Plumbing) (1)  02.08.2025    
-- -- Inspection (Rough In Electric) (1)  02.08.2025    
-- -- Inspection (Framing) (1) *   02.08.2025    
-- -- Inspection (Deck Piers) (0)  02.20.2025    
-- -- Inspection (Insulation) (1)  02.12.2025    
-- -- Inspection (Electric Service) (0)  02.20.2025    
-- -- Inspection (Main Sewer Line) (0)  02.20.2025    
-- -- Inspection (Main Water Line) (0)  02.20.2025    
-- -- Inspection (Final HVAC) (0)  05.08.2025     Tuesday, May 6
-- -- Inspection (Final Plumbing) (0)  05.08.2025    
-- -- Inspection (Final Electric) (0)  05.08.2025    
-- -- Inspection (Final Building) (4) *   05.08.2025