CONGERS-3 - 44  ::  1597 Palomino Trail
[ BUILD: 20241824 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 14      Inspection (Plumbing Under Slab) (1)      
Fri    Nov 15      Inspection (Conduit Under Slab) (1)      
Mon    Nov 18      Inspection (Slab) (1)      
Tue    Nov 19      Inspection (Drain Tile) (0)      
Tue    Nov 19      Inspection (Rough In HVAC) (1)      
Wed    Nov 20      Inspection (Rough In Plumbing) (1)      
Thu    Nov 21      Inspection (Rough In Electric) (1)      
Fri    Nov 22      Inspection (Deck Piers) (0)      
Fri    Nov 22      Inspection (Framing) (1)      
Mon    Nov 25      Inspection (Insulation) (1)      
Tue    Nov 26      Inspection (Electric Service) (0)      
Tue    Nov 26      Inspection (Main Sewer Line) (0)      
Tue    Nov 26      Inspection (Main Water Line) (0)      
Tue    Nov 26      Inspection (Final HVAC) (1)      
Wed    Nov 27      Inspection (Final Plumbing) (1)      
Thu    Nov 28      Inspection (Final Electric) (1)      
Fri    Nov 29      Inspection (Final Building) (2)      
-- -- Inspection (Footers) (1)  10.21.2024    
-- -- Inspection (Concrete Wall) (1)  10.21.2024