Tue |
Jul 1 |
Sod / Seed / Landscaping (0) |
|
|
|
-- |
-- |
Concrete floors have multiple blemishes 3/5. Specifically garage |
|
|
-- |
-- |
Higher location for coffee station receptacle |
Kate to respond to buyer |
|
-- |
-- |
Duct for microwave exhaust ends lower than necessary? |
Kate to respond to buyer |
|
-- |
-- |
Unsightly meter box next to front door :-) |
Kate to respond to buyer |
|
-- |
-- |
When is low voltage box installed under stairs? |
Kate to respond to buyer |
|
-- |
-- |
Where will the water meter be located? |
Kate to respond to buyer |
|
-- |
-- |
I do not see an elevated wall outlet anywhere? |
Is it supposed to be above a future kitchen coffee cabinet? |
|
-- |
-- |
There are two three sets of drawers in kitchen cabinets |
|
|
-- |
-- |
Missing handle 7nder kitchen sink |
Under - Fred |
|
-- |
-- |
Hall and bonus cabinets are not white |
ready for pick up at Lowes |
|
-- |
-- |
Finish patching drywall near foyer space |
|
|
-- |
-- |
Can conduits going into electric meter be parallel? |
Buyer request |
|
-- |
-- |
Granite needs to have the side piece that goes against the wood be beside the refrigerator |
|
|
-- |
-- |
Hall and bonus cabinets - waiting |
Just need countertops |
|
-- |
-- |
Finish the bonus room closet drywall |
Drywaller |
|
-- |
-- |
Plastic piece needed for front faucet |
Munzur |
|
-- |
-- |
Is the kitchen sink faucet supposed to be farmhouse style? |
|
|
-- |
-- |
Cover carpet |
|
|
-- |
-- |
Farmhouse plumbing has not been installed. |
Munzur |
|
-- |
-- |
Bonus room needs carpet. I’m assuming they need light fixtures installed first. |
Denny |
|
-- |
-- |
Dori going into the closet in the foyer, does not open |
Jorge. It opens , but now it doesn’t close. |
|
-- |
-- |
Install doors so knobs can be installed. Maybe they need to be cu down? |
Jorge |
|
-- |
-- |
Hall bath popped lights and not working now |
Electrician |
|
-- |
-- |
Garage floor needs trim |
Jorge |
|
-- |
-- |
Trim doors in bonus room that won’t open due to carpet installation |
Jorge |
|
-- |
-- |
Repair the fan in the bonus room so that it functions properly. |
Electrician |
|
-- |
-- |
Basement closet needs trim inside of door. |
Jorge |
|
-- |
-- |
Door knob needed to utility room. |
Paul |
|
-- |
-- |
Shelving needs finished in master closet |
Paul |
|
-- |
-- |
Which plate cover needed on side of kitchen island |
Brown - Jill |
|
-- |
-- |
Light switch cover needed by front door |
Jesus |
|
-- |
-- |
Sand, bonus room, closet, and install shelving |
Drywaller |
|
-- |
-- |
Side-by-side refrigerator is in kitchen |
wrong refrigerator |
|
-- |
-- |
Remove shower rod as door needs to be installed |
Paul |
|
-- |
-- |
Cabinets are sitting in living room. Need to be installed. |
|
|
-- |
-- |
Pretty large scratch on the back panel of the kitchen island |
Jill |
|
-- |
-- |
LOCKBOX 2626 |
|
|
-- |
-- |
Finish weatherstripping on garage interior door |
Jill |
|
-- |
-- |
Install shelving in bonus room closet |
getting done 6/2 |
|
-- |
-- |
Install light fixture and bathroom fan in bonus bathroom |
Mast & Brunk |
|
-- |
-- |
Trim needs painting on exterior patio door |
Jesus |
|
-- |
-- |
Microwave vent does not function |
Tom |
|
-- |
-- |
Cable covers needed in all units |
Tom |
|
-- |
-- |
Install shoe mold in bathrooms, still awaiting vanities to be installed |
Jorge |
|
-- |
-- |
Install side splash and handles on cabinets |
Tom |
|
-- |
-- |
Bonus bath needs mirror |
Paul |
|
-- |
-- |
Thermostat is here but not on |
Tom |
|
-- |
-- |
Final paint needed |
Jesus |
|
-- |
-- |
Where are the vanity handles? |
Jill will put on before walkthrough |
|
-- |
-- |
Fridge stair scratches - will coat of poly cover |
|
|
-- |
-- |
Caulk in side vanity pieces |
|
|
-- |
-- |
Add PVC/Vinyl below patio door |
Tom |
|
-- |
-- |
Awning Roof Line |
Davenport |
|
-- |
-- |
Adjust door lock to patio |
Paul/Joe |
|
-- |
-- |
Microwave vent flap not lifting |
|
|
-- |
-- |
Need pieces for the side of the farm sink |
Fred has ordered it |
|
-- |
-- |
Adjust lower cabinet door hinge so it does not hit wall under kitchen window |
Hinge restrictor clip - Fred |
|
-- |
-- |
epaint front door |
|
|
-- |
-- |
Nail pop above powwder vantiy |
Painter |
|
-- |
-- |
Several windows hard to open - please check all |
This is normal. |
|
-- |
-- |
Bathrooms- switch knobs to bar pulls- bonus and hall |
Tom |
|
-- |
-- |
Adjust 1upper bedroom door- locks you inside |
Paul/Joe |
|
-- |
-- |
Remove pencil mark in LVP on floor of powder |
Jill |
|
-- |
-- |
Sweep off patio |
Jill |
|
-- |
-- |
Several island scratches and nail pops |
Jill |
|
-- |
-- |
several cabient door scratches |
Jill |
|
-- |
-- |
double check insulation in HVAC closet |
|
|
-- |
-- |
HVAC closet- drywall only half done |
not adding drywall - Kate will email |
|
-- |
-- |
Adjust door stop on Bonus Room door |
Paul/joe |
|
-- |
-- |
Add door stop to bonus bath |
Paul/Joe |
|
-- |
-- |
Paint touchup |
Jesus |
|
-- |
-- |
Front door handle lock |
Paul |
|
-- |
-- |
Clean concrete back patio |
|
|
-- |
-- |
Irene or Victor, 804-314-7253 |
|
|
-- |
-- |
Ratified Contract? (0) 12.13.2024 |
|
|
|
|
Finished Bonus Room
|
|
|
|
Finished Bonus Bathroom
|
|
|
|
Level 2 Granite
|
|
|
|
Three Drawer Stacks in B 36" and B18"
|
|
|
|
Expanded Driveway
|
|
|
|
Oak Stairs to Bedroom Level
|
|
|
|
LVP in upstairs hallway
|
|
|
|
Upgraded Gardenia LVT in Master, Hall and Bonus Baths
|
|
|
|
Farmhouse sink
|
|
|
|
Elevated Wall Outlet - fee for custom request and management charge
|
|
|
|
Upgraded French Model Fridge
|
|
|
|
Added Fan in Bonus Room and Living Room
|
|
|
|
Farmhouse plumbing package
|
|
|
|
Upgraded carpet pad in bonus and upstairs bedrooms
|
|
|
|
Microwave vent to exterior
|
|
|
|
Expanded patio 10x18
|
|
|
|
Digital deadbolt
|
|
|
|
Shower door master bath
|
|
|
|
White Painted cabinetry in Hall Bath and Bonus Bath
|
|
|
|
Amendment to increase price by $28,720
|
|
-- |
-- |
$2500 Deposit Received (0) 12.19.2024 |
|
|
-- |
-- |
Association Packet Requested (0) 06.30.2025 |
|
|
-- |
-- |
Association Packet Received (0) 12.14.2024 |
|
|
-- |
-- |
Selections Meeting (0) 01.28.2025 |
1 PM Friday 1/17 |
|
-- |
-- |
Selections Sheet Signed (0) 02.12.2025 |
2/10: sent to Mattias |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 03.05.2025 |
3/4: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 03.04.2025 |
|
|
-- |
-- |
Building Permit (30) 11.21.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 12.30.2024 |
|
|
-- |
-- |
Order Windows & Doors (0) 12.30.2024 |
|
|
-- |
-- |
Stake Out Home (1) 12.02.2024 |
|
|
-- |
-- |
Excavate (2) 12.02.2024 |
|
|
-- |
-- |
Inspection (Footers) (1) 12.02.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 12.02.2024 |
|
|
-- |
-- |
Pour Footers (1) * 12.02.2024 |
|
|
-- |
-- |
Set Forms (2) 12.19.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1) 12.19.2024 |
|
|
-- |
-- |
Plumb Slab (2) 12.19.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 12.28.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 12.28.2024 |
|
|
-- |
-- |
Prepare Slab (1) 12.28.2024 |
|
|
-- |
-- |
Inspection (Slab) (1) 12.28.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 02.20.2025 |
|
|
-- |
-- |
Pour Slab (1) * 12.28.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 03.11.2025 |
3/5: sent to Brittany |
|
-- |
-- |
Framing I (9) 01.13.2025 |
|
|
-- |
-- |
Order Steps (0) 02.27.2025 |
|
|
-- |
-- |
Order Tubs / Showers (0) 02.27.2025 |
|
|
-- |
-- |
Framing II (8) 02.02.2025 |
|
|
-- |
-- |
Framing III (8) * 02.27.2025 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 03.03.2025 |
|
|
-- |
-- |
Install Stairs (0) 03.12.2025 |
|
|
-- |
-- |
Windows & Doors (0) * 03.08.2025 |
|
|
-- |
-- |
House Number and Status in Window (0) 03.09.2025 |
|
|
-- |
-- |
Roofing (0) * 03.13.2025 |
|
|
-- |
-- |
Order Cabinets (0) 02.26.2025 |
Ordered 2/25 |
|
-- |
-- |
Order Appliances (0) 04.14.2025 |
|
|
-- |
-- |
Deck (0) 04.06.2025 |
|
|
-- |
-- |
Gutters (0) 05.07.2025 |
|
|
-- |
-- |
Driveway (0) * 05.07.2025 |
Expanded |
|
-- |
-- |
Patio (0) 04.14.2025 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 05.17.2025 |
|
|
-- |
-- |
HVAC Rough In (4) 03.12.2025 |
In process 3/5 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 03.24.2025 |
Friday, March 21 |
|
-- |
-- |
Rough In Microwave Vent (0) 03.08.2025 |
|
|
-- |
-- |
Plumbing Rough In (4) 03.15.2025 |
Almost complete 3/12 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 03.24.2025 |
|
|
-- |
-- |
Electric Rough In (4) 03.19.2025 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 03.24.2025 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 05.12.2025 |
|
|
-- |
-- |
Inspection (Framing) (1) * 03.24.2025 |
|
|
-- |
-- |
Exterior Vinyl (0) * 04.19.2025 |
|
|
-- |
-- |
Exterior Stone (0) 05.05.2025 |
|
|
-- |
-- |
Insulation (2) * 03.24.2025 |
|
|
-- |
-- |
Inspection (Insulation) (1) 03.26.2025 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 04.14.2025 |
|
|
-- |
-- |
Set Electric Meter (0) * 05.12.2025 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 04.14.2025 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 04.14.2025 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 04.12.2025 |
|
|
-- |
-- |
Drywall (Hang) (4) * 03.28.2025 |
In process 3/26 |
|
-- |
-- |
Loan Approval (0) 04.03.2025 |
Cash |
|
-- |
-- |
Deed Preparation (0) 05.05.2025 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 04.12.2025 |
In process 4/9. Sanding. |
|
-- |
-- |
Paint 1 (1) 04.12.2025 |
|
|
-- |
-- |
Garage Door (0) * 05.10.2025 |
|
|
-- |
-- |
House Numbers (0) 05.24.2025 |
|
|
-- |
-- |
Mailbox (0) 06.12.2025 |
|
|
-- |
-- |
Cabinet Installation (2) * 04.12.2025 |
Apr 9 |
|
-- |
-- |
Granite Installation (1) * 05.02.2025 |
|
|
-- |
-- |
Interior Trim - Install (3) * 04.19.2025 |
In process 4/16 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 04.14.2025 |
|
|
-- |
-- |
Interior Trim - Paint (1) 04.23.2025 |
Prepping to paint 4/19 |
|
-- |
-- |
Luxury Vinyl Plank (3) * 05.02.2025 |
In process 4/30 |
|
-- |
-- |
Luxury Vinyl Tile (0) 05.02.2025 |
|
|
-- |
-- |
Paint 2 (3) 05.02.2025 |
In process 4/30 |
|
-- |
-- |
Cover Floors (1) 05.21.2025 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 04.21.2025 |
|
|
-- |
-- |
Shoe Moulding (0) 05.10.2025 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) * 05.28.2025 |
Bonus bathroom mirror needs to be hung |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 05.21.2025 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 05.12.2025 |
|
|
-- |
-- |
Set Water Meter (0) * 05.22.2025 |
|
|
-- |
-- |
Electric Trim Out (3) 05.17.2025 |
In process 5/14. Just needs bonus and installed and lights above bonus bathroom vanity. |
|
-- |
-- |
Ceiling Fans (0) 05.14.2025 |
|
|
-- |
-- |
HVAC Trim Out (1) 05.17.2025 |
|
|
-- |
-- |
Blower Door Test (1) 05.29.2025 |
|
|
-- |
-- |
Plumbing Trim Out (2) 05.28.2025 |
Plumbing fixtures need installed on new vanities that will be installed |
|
-- |
-- |
Install Appliances (0) * 05.31.2025 |
Fridge needs installed 5/24 |
|
-- |
-- |
Paint 3 (2) * 05.14.2025 |
|
|
-- |
-- |
Carpet (2) 05.10.2025 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 06.04.2025 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 06.04.2025 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 06.04.2025 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 06.04.2025 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 06.04.2025 |
|
|
-- |
-- |
Pre Walk Through (0) 06.02.2025 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 05.31.2025 |
In process 5/28 |
|
-- |
-- |
Cleaning (1) 05.31.2025 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 06.04.2025 |
|
|
-- |
-- |
C.O. to Lender (0) 06.04.2025 |
|
|
-- |
-- |
Schedule Closing (0) 06.06.2025 |
potentially 6/5 |
|
-- |
-- |
Buyer Walk Through (1) 06.04.2025 |
3:30pm 6/2 |
|
-- |
-- |
Payment for Upgrades (0) 06.04.2025 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 06.05.2025 |
|
|
-- |
-- |
Review Settlement Statement (0) 06.06.2025 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 06.06.2025 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 06.04.2025 |
|
|
-- |
-- |
Closing (1) 06.06.2025 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 06.12.2025 |
|
|