000 40 37 20 13 32 31 30 29 28 12 11 10 9 5 6 7 8 1 2 3 4 ADDR
CONGERS-3 - 18  ::  1407 Derby Drive
[ BUILD: 20250193 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
There’s a concrete bump out in the foyer area. Are we just going to frame that in?
Primary bathroom cabinet door is too small Fred
Primary door framing issue Drywall
8 boxes of lvt tile needed
Primary bedroom door needs to be repaired so that carpet can be laid easily
Trim needed around primary door from
Trim needed around primary door frame
This refrigerator sticks out really far from the cabinets. Is this a new model or do they always look like this?
Microwave vent does not work Tom
CODED LOCKBOX 1818
The stain on the step looks really dark
Few paint touchups needed around powder bath light fixture Jesus
Secure insulation in bonus room Jill
Put splash blocks in place After sod
Clean out garage Jill
Sweep off deck Jill
Clean paint off of floor Jesus
Need plugs in front door Jill
Power wash front of house and sweep After sod
Finish cleaning garage floor and scrape Jill
Install bathroom screen after cleaning window frame Jill
Pressure wash front and back of home
Back patio light isn’t right missing parts Jill - needs to be attached
Paint touchup throughout Jesus
Patch imperfections in painted staircase Jesus
Install cable cover under closet Jill
Secure trim around island Jorge
Personal belongings in house 10/25
UPGRADES - COMPLETED
    Expanded Driveway  
    Microwave vented to exterior  
    French Model Refrigerator  
    Three Drawer Base in place of B 36  
    Painted Carpet Grade Steps  
    Upgraded LVT in Up Baths and Laundry  
    Ceiling Fan in Living Room  
    Amendment to increase price by $4,705  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  01.17.2025    
-- -- $2500 Deposit Received (0)  01.23.2025    
-- -- Association Packet Requested (0)  06.30.2025    
-- -- Association Packet Received (0)  01.24.2025    
-- -- Selections Meeting (0)  03.18.2025    
-- -- Selections Sheet Signed (0)  03.29.2025     3/27: sent to Colton
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  04.03.2025     3/28: sent to Colton
-- -- Deposit For Upgrades Received (0)  03.29.2025    
-- -- Building Permit (30) *   01.24.2025    
-- -- Order Roof & Floor Trusses (1)  04.03.2025    
-- -- Order Windows & Doors (0)  06.16.2025    
-- -- Stake Out Home (1)  03.29.2025    
-- -- Excavate (2)  03.29.2025    
-- -- Inspection (Footers) (1)  03.29.2025    
-- -- Inspection (Concrete Wall) (1)  03.29.2025    
-- -- Pour Footers (1) *   03.29.2025    
-- -- Set Forms (2)  03.29.2025    
-- -- Pour Foundation Walls (1)  03.29.2025    
-- -- Plumb Slab (2)  04.24.2025    
-- -- Inspection (Plumbing Under Slab) (1)  04.24.2025    
-- -- Inspection (Conduit Under Slab) (1)  05.01.2025    
-- -- Prepare Slab (1)  05.01.2025    
-- -- Inspection (Slab) (1)  05.12.2025    
-- -- Inspection (Drain Tile) (0)  05.12.2025    
-- -- Pour Slab (1) *   05.01.2025    
-- -- Settlement Agent Confirmed (0)  01.23.2025    
-- -- Framing I (9)  05.27.2025    
-- -- Order Steps (0)  06.16.2025    
-- -- Order Tubs / Showers (0)  06.16.2025    
-- -- Framing II (8)  06.15.2025    
-- -- Framing III (8) *   06.30.2025    
-- -- Verify Window & Roof Structure (0)  07.03.2025    
-- -- Install Stairs (0) *   06.30.2025    
-- -- Windows & Doors (0) *   07.14.2025    
-- -- House Number and Status in Window (0)  07.17.2025    
-- -- Roofing (0) *   07.10.2025    
-- -- Order Cabinets (0)  07.28.2025    
-- -- Order Appliances (0)  08.18.2025    
-- -- Deck (0)  07.30.2025     Standard
-- -- Gutters (0)  09.17.2025    
-- -- Driveway (0) *   09.24.2025    
-- -- Patio (0)  08.23.2025     Standard
-- -- Privacy Divider / Fence (0) *   09.17.2025    
-- -- Sod / Seed / Landscaping (0)  10.22.2025    
-- -- HVAC Rough In (4)  07.02.2025    
-- -- Rough In Microwave Vent (0)  07.16.2025    
-- -- Plumbing Rough In (4)  07.28.2025    
-- -- Electric Rough In (4)  07.28.2025    
-- -- Inspection (Rough In HVAC) (1)  07.28.2025    
-- -- Inspection (Rough In Plumbing) (1)  07.28.2025    
-- -- Inspection (Rough In Electric) (1)  07.28.2025    
-- -- Inspection (Framing) (1) *   07.28.2025    
-- -- Inspection (Deck Piers) (0)  08.04.2025    
-- -- Exterior Vinyl (0) *   08.27.2025     In process 8/23
-- -- Exterior Stone (0)  09.08.2025    
-- -- Insulation (2) *   08.03.2025    
-- -- Inspection (Insulation) (1)  08.04.2025    
-- -- Inspection (Electric Service) (0)  08.14.2025    
-- -- Set Electric Meter (0) *   09.16.2025    
-- -- Inspection (Main Sewer Line) (0)  08.14.2025    
-- -- Inspection (Main Water Line) (0)  08.14.2025    
-- -- Order Interior Doors & Trim (0)  07.31.2025    
-- -- Drywall (Hang) (4) *   08.07.2025     Stocked 8/3
-- -- Loan Approval (0)  10.22.2025     Ron @ Integrity (97% Conventional)
-- -- Deed Preparation (0)  09.26.2025    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.16.2025     In process 8/13
-- -- Paint 1 (1)  08.20.2025    
-- -- Garage Door (0)  08.20.2025    
-- -- House Numbers (0)  10.04.2025    
-- -- Mailbox (0)  09.08.2025    
-- -- Cabinet Installation (2) *   08.20.2025     Delivery 8/20, Install 8/21
-- -- Granite Installation (1) *   08.27.2025     August 25
-- -- Interior Trim - Install (3) *   09.01.2025     In process 8/23
-- -- Order Plumbing / Lighting Fixtures (0)  08.21.2025    
-- -- Interior Trim - Paint (1)  09.03.2025     In process 9/1
-- -- Luxury Vinyl Plank (3) *   09.10.2025     In process 9/6
-- -- Luxury Vinyl Tile (0)  09.10.2025    
-- -- Paint 2 (3)  09.26.2025     In process 9/24
-- -- Cover Floors (0)  09.13.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  08.28.2025    
-- -- Shoe Moulding (0)  09.13.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   10.15.2025     In process 10/11Shelving needed and mirrors.
-- -- Install Coded Lockbox (add extra keys) (0)  10.08.2025    
-- -- Pay Water / Sewer Taps (0)  09.04.2025    
-- -- Set Water Meter (1) *   10.07.2025    
-- -- Electric Trim Out (3) *   10.11.2025     Bonus vanity, light, and a few light switch covers still need to be installed
-- -- Ceiling Fans (0)  10.04.2025    
-- -- HVAC Trim Out (1) *   10.08.2025    
-- -- Blower Door Test (1)  10.13.2025    
-- -- Plumbing Trim Out (2) *   10.01.2025     In process 9/26
-- -- Install Appliances (0) *   10.08.2025     French/ 7/30
-- -- Paint 3 (2) *   10.08.2025    
-- -- Carpet (2)  09.10.2025    
-- -- Appraiser Confirms Construction Completion (0)  10.23.2025     Tell Ron Ross when ready
-- -- Inspection (Final HVAC) (0)  10.13.2025    
-- -- Inspection (Final Plumbing) (0)  10.13.2025    
-- -- Inspection (Final Electric) (0)  10.13.2025    
-- -- Inspection (Final Building) (4) *   10.20.2025     Thu, Oct 16
-- -- Pre Walk Through (0)  10.23.2025    
-- -- Stain Hardwood Stairs (1) *   10.22.2025     In process 10/118
-- -- Cleaning (1)  10.22.2025    
-- -- Certificate of Occupancy (1) *   10.22.2025    
-- -- C.O. to Lender (0)  10.22.2025    
-- -- Schedule Closing (0)  10.22.2025    
-- -- Buyer Walk Through (1) *   10.22.2025     Wed, Oct 22 at 1PM ?
-- -- Payment for Upgrades (0)  10.13.2025    
-- -- Keys to Settlement Agent (0)  10.13.2025    
-- -- Review Settlement Statement (0)  10.21.2025    
-- -- Jerry Signs Closing Documents (0)  08.27.2025    
-- -- Request Trash Tote From POA Manager (0)  10.15.2025    
-- -- Closing (1)  10.27.2025     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  10.31.2025