| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Expanded Driveway | ||||
| Microwave vented to exterior | ||||
| French Model Refrigerator | ||||
| Three Drawer Base in place of B 36 | ||||
| Painted Carpet Grade Steps | ||||
| Upgraded LVT in Up Baths and Laundry | ||||
| Ceiling Fan in Living Room | ||||
| Amendment to increase price by $4,705 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 03.29.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 03.29.2025 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 04.24.2025 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 05.01.2025 | ||
| -- | -- | Inspection (Slab) (1) 05.12.2025 | ||
| -- | -- | Inspection (Drain Tile) (0) 05.12.2025 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 07.28.2025 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 07.28.2025 | ||
| -- | -- | Inspection (Rough In Electric) (1) 07.28.2025 | ||
| -- | -- | Inspection (Framing) (1) * 07.28.2025 | ||
| -- | -- | Inspection (Deck Piers) (0) 08.04.2025 | ||
| -- | -- | Inspection (Insulation) (1) 08.04.2025 | ||
| -- | -- | Inspection (Electric Service) (0) 08.14.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 08.14.2025 | ||
| -- | -- | Inspection (Main Water Line) (0) 08.14.2025 | ||
| -- | -- | Inspection (Final HVAC) (0) 10.13.2025 | ||
| -- | -- | Inspection (Final Plumbing) (0) 10.13.2025 | ||
| -- | -- | Inspection (Final Electric) (0) 10.13.2025 | ||
| -- | -- | Inspection (Final Building) (4) * 10.20.2025 | Thu, Oct 16 | |