| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Finished bonus room | ||||
| Finish bonus bath | ||||
| Luxury vinyl plank in bonus room | ||||
| Luxury vinyl plank upstairs | ||||
| Oak treads to bedroom level | ||||
| Eggshell paint | ||||
| Expanded driveway | ||||
| Farmhouse sink | ||||
| Cabinet crown molding | ||||
| Spice rack B 9” | ||||
| French style refrigerator | ||||
| Microwave vented two exterior | ||||
| Expanded 10 x 10 patio | ||||
| Expanded 10 x 18 Deck | ||||
| Amendment to increase price by $31,740 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 03.29.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 03.29.2025 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 04.24.2025 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 04.24.2025 | ||
| -- | -- | Inspection (Slab) (1) 05.12.2025 | ||
| -- | -- | Inspection (Drain Tile) (0) 07.22.2025 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 07.28.2025 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 07.28.2025 | ||
| -- | -- | Inspection (Rough In Electric) (1) 07.28.2025 | ||
| -- | -- | Inspection (Framing) (1) * 07.28.2025 | ||
| -- | -- | Inspection (Deck Piers) (0) 08.04.2025 | ||
| -- | -- | Inspection (Insulation) (1) 07.28.2025 | ||
| -- | -- | Inspection (Electric Service) (0) 08.21.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 08.14.2025 | ||
| -- | -- | Inspection (Main Water Line) (0) 08.14.2025 | ||
| -- | -- | Inspection (Final HVAC) (0) 10.02.2025 | ||
| -- | -- | Inspection (Final Plumbing) (0) 10.02.2025 | ||
| -- | -- | Inspection (Final Electric) (0) 10.02.2025 | ||
| -- | -- | Inspection (Final Building) (4) * 10.02.2025 | ||